2018
Jan
15

Method Statement for Pile Reinforcement and Concrete Casting

Piling Cage Installation

Subsequent to the completion of the pile drilling, the borehole depth will be checked and verified versus the depth given on daily piling sequence and pile data.  Only after borehole depth check can the cage be lowered into the borehole.  A reference

2018
Jan
7

Method Statement for Piling Works Constructions – Drilling

Below is a brief method statement of piling work that can be used for any kind of project piling works. A crawler mounted piling rig will be used to install bored cast in situ piles of dia 1200 mm. The procedure for

2017
Nov
13

CCTV Camera Testing & Commissioning Procedure

Pan Tilt & Zoom or PTZ CCTV Camera

The purpose of this method statement is to specify the detailed requirements and procedure for testing & commissioning of installed CCTV System at a project in accordance to the specification and manufacture’s recommendation to reach the required quality and satisfying the requirements

2017
Sep
5

Cartridge Filters UV Sterilization Unit and Chlorine Dosing System Installation

domestic water treatment

Before starting the site installation work domestic water treatment system, ensure all civil works are completed for the area of installation, and civil clearance is obtained from respective authorities to proceed further. Prior to start the installation, refer to the approved shop

2017
Jul
5

Car Parking Management System Testing Commissioning Procedure

Electric installation and maintenance work may be carried out only by appropriately qualified licensed electricians. Mains connections must be hard-wired. Please ensure full compliance with all applicable national and international rules and regulations concerning electric connections, as well as all applicable safety

2017
Jul
2

Bypass Terminal Reheat Units Testing & Commissioning Method

Pre-Commissioning Procedure Before starting the commissioning activities check and ensure that bypass Terminal Reheat units are installed as per the approved shop drawings and manufacturer’s instructions and approved. Check that sensing grids tubing connection from the grids to the transducers are correct

2017
Jun
15

Lead Acid Batteries Installation Operating Maintenance Instructions

Before starting the batteries installation begins, inspect for signs of damage or missing components. Store the battery in a dry, clean and preferably cool and frost-free location. Do not expose the cells to direct sunlight as damage to the container and cover