2025
Jun
15

Safety Instructions for the use of Compressed Air Tools and Units

Safety Instructions for the use of Compressed Air Tools and Units

The purpose of this safety procedure is to provide instruction and direction as to what the correct usage of compressed air tools and equipment should be to minimize the risk of injury to personnel and assets. Below procedure is applicable for all

2025
May
3

Construction Methodology for Underground Services Protection

Construction Methodology for Underground Services Protection

Purpose of below safety method statement is to provide instructions for ensuring the safe operations involved with ground penetrations so that underground services are not damaged and also to ensure the safety of workers. Overall the project manager is having responsibilities for

2025
Apr
25

Plastering Method Statement

Plastering Method Statement

Below is a precise plastering work method statement that is very useful for civil engineers to understand how best quality plaster work can be done. This procedure covers the methodology to be followed for carrying out plastering in line with the approved

2025
Apr
22

Flooring Installation Method Statement for Marble and Granite Tiles Installation

Flooring Installation Method Statement for Marble and Granite Tiles Installation

This flooring installation method statement covers the detailed procedure to be followed for supply & installation of Marble and Granite tiles on floor, stairs, walls and counters and other areas as per the schedule of finishes for the project. Civil site engineer

2025
Feb
6

Lifting Work Safety Method Statement

Lifting Work Safety Method Statement

This document covers the procedure to establish a method statement for all lifting activities for any kind of project especially laying of large transmission pipelines. The purpose of this document is to follow proper methodology and to carry out the activities and

2025
Jan
27

Method Statement for Demolition Works

Demolition-Method-Statement

Below is precise method statement for demolition works that has been prepared to demonstrate the safe working method for the soft strip of internal fixtures/fixings and identified items, asbestos removal and demolition of the existing structure. This safework method is to be

2024
Nov
3

Earthworks Method Statement

Earthworks Method Statement

This method statement for earthworks defines requirements for civil work related activities, but it doesn’t cover the earthwork activities related to underground piping, conduits and ducts which are covered under different earthworks method statements. All the earthworks shall be done in accordance

2024
Oct
20

Micro Pile Installation and Pile Test Method of Statement

Micro Pile Installation and Pile Test Method of Statement

Scope of this work method statement shall apply on the reinforced concrete works and the objective is to define and establish the work method of statement for the reinforced concrete work for the installation of micro pile. The piling installation work shall

error: Content is protected !!