2025
Feb
6

Lifting Work Safety Method Statement

Lifting Work Safety Method Statement

This document covers the procedure to establish a method statement for all lifting activities for any kind of project especially laying of large transmission pipelines. The purpose of this document is to follow proper methodology and to carry out the activities and

2025
Jan
27

Method Statement for Demolition Works

Demolition-Method-Statement

Below is precise method statement for demolition works that has been prepared to demonstrate the safe working method for the soft strip of internal fixtures/fixings and identified items, asbestos removal and demolition of the existing structure. This safework method is to be

2024
Nov
3

Earthworks Method Statement

Earthworks Method Statement

This method statement for earthworks defines requirements for civil work related activities, but it doesn’t cover the earthwork activities related to underground piping, conduits and ducts which are covered under different earthworks method statements. All the earthworks shall be done in accordance

2024
Oct
20

Micro Pile Installation and Pile Test Method of Statement

Micro Pile Installation and Pile Test Method of Statement

Scope of this work method statement shall apply on the reinforced concrete works and the objective is to define and establish the work method of statement for the reinforced concrete work for the installation of micro pile. The piling installation work shall

2024
Sep
30

Scaffolding Method Statement

Scaffolding Method Statement

Below is a precise method statement for scaffolding installation for any kind of project. The following method statement is written to provide a safe and efficient system of work for the installation of general working scaffold to all areas of construction sites

2024
Sep
25

Method Statement for Road Construction

Road work Binder Course Spreading with Asphalt Paver Machine

This roadwork method statement describes work methodology for road construction covering the activities from subgrade to asphalt work. All personnel working at site shall have full knowledge and expertise in the excavation, backfilling, compaction and road testing process. Occupational health and safety

2024
Jul
22

Earth Retention Shoring System for Excavations – Part 2 of 2

Diaphragm-Walls-Requirements-and-design

Diaphragm & Guide Walls Requirements The design and construction of the diaphragm wall including all its associated works such as guide walls, anchors, etc., shall be the responsibility of the Contractor and shall take into account the actual site, ground conditions, the equipment

error: Content is protected !!