2024
Dec
7

Fire Protection Pipes and Fittings Installation Method Statement

Fire Protection Pipes and Fittings Installation Method Statement

This method statement covers the detailed procedure for installation of Fire Protection Pipes and Fittings. Procedure also defines the method used to ensure that the pipe work and fittings installation has been carried out as per the contract specification requirements. This method

2024
Dec
2

Disinfection and Flushing of Water Mains

Disinfection and Flushing of Water Mains

Purpose of this plumbing method statement is to ensure that disinfection and flushing of water mains and related pipe lines are executed safely and in accordance with the contract requirements and that all quality assurance / control activities are conducted in a

2024
Nov
6

HVAC Method Statement for Grill Diffuser and Louver Installation

HVAC Method Statement for Grill Diffuser and Louver Installation

This hvac method statement covers the supply & installation of grilles, diffusers louvers & disc valves in line with project requirements as indicated in the approved shop drawings, reflected ceiling plans, specifications and manufacturer’s instructions. Plant and equipment required General tool box

2024
Nov
3

Earthworks Method Statement

Earthworks Method Statement

This method statement for earthworks defines requirements for civil work related activities, but it doesn’t cover the earthwork activities related to underground piping, conduits and ducts which are covered under different earthworks method statements. All the earthworks shall be done in accordance

2024
Oct
20

Micro Pile Installation and Pile Test Method of Statement

Micro Pile Installation and Pile Test Method of Statement

Scope of this work method statement shall apply on the reinforced concrete works and the objective is to define and establish the work method of statement for the reinforced concrete work for the installation of micro pile. The piling installation work shall

2024
Oct
14

Water Booster Pump Installation Testing and Commissioning Method Statement

Water Booster Pump Installation Testing and Commissioning Method Statement

Below is a precise method of statement for water pump or booster pump installation including the testing and commissioning steps. Make sure that proper clearance is available from civil side before commencement of water pump installation works. Ensure that the work area

2024
Oct
9

Heat Exchanger Installation Testing and Commissioning Method Statement

Heat Exchanger Installation Testing and Commissioning Method Statement

Unless otherwise specified, all plate heat exchanger installation shall be in accordance to approved shop drawings, manufacturer instructions and contract specifications. Drawing plans, schematics, and diagrams indicate general location and arrangement of Heat Exchanger’s. Install Plate Heat  Exchanger’s as indicated unless deviations

2024
Sep
30

Scaffolding Method Statement

Scaffolding Method Statement

Below is a precise method statement for scaffolding installation for any kind of project. The following method statement is written to provide a safe and efficient system of work for the installation of general working scaffold to all areas of construction sites

error: Content is protected !!