Construction Method Statement Example

Piling Cage Installation

If you are looking for a professional construction method statement example then this page is helpful for you. We help you to understand the structure and requirements of a typical construction method statement. The information given is useful for engineers and other construction professionals in their work. This leads obviously to prepare a good and safe work method statement i.e. …

Read More »

Installation Of Passenger’s Elevator Hooks, Hook Beams & Divider Beams

Prior transferring materials from lay down, the foreman shall make a materials inventory at the lay down area as per approved shop drawings if the all materials required for the passenger’s elevator hooks, hook beams and divider beams are all available at site. If found the materials available at site, the foreman shall take permission from the site Engineers that …

Read More »

Procedure for Installation of Steel Structure for Pump Rooms

Installation-of-Steel-Structure-method-statement

The following Method Statement describes the procedure and equipment required for the installation of steel structure for pump room. Following equipment shall be arranged: Lifting Equipment: Tower Crane (if available) To lift the beams/Purlins structure from ground floor to the roof where  the area of installation is located. JCB or Fork Lift To bring the beams structure from laydown area to …

Read More »

Cables & Wires Installation and Termination Method

Cables-and-wires-method-statement

Storage of Materials at Site All materials received at site shall be inspected and ensured that the materials are as per approved material submittal. Any discrepancies, damages etc.shall be notified and reported for further action. Material found not suitable for the project are removed from site immediately. Cables are stored with the factory packing on the flat surface with stoppers …

Read More »

Cable Trays and Ladders Installation Procedure

a) Storage All materials received at site shall be inspected and ensure that the materials are as per approved material submittal. Any discrepancies, damages etc. shall be notified and reported for further action. Materials found not suitable for the project are removed from site immediately. Cable trays and ladders are stored in horizontal position on flat surface with timber support …

Read More »

GI Cable Trunking Installation Method Statement

a) Storage of Material All materials received at site shall be inspected and ensured that the materials are as per approved material submittal. Any discrepancies, damages etc.shall be notified and reported for further action. Material found not suitable for the project are removed from site immediately. GI Trunking are stored in horizontal position on flat surface with timber support at …

Read More »

Ring Main Unit Testing and Commissioning Method Statement

Required tools for ring main unit testing and commissioning procedure: Primary Injection kit Contact Resistance kit High Voltage test kit 5.0 KV Megger Multi meters (Fluke Meters) Commissioning Phase The following sequence will be carried out for testing. Check the Bus bar tightness check with torque table mentioned below Check the Earthing Busbar tightness check with torque table below as …

Read More »