Construction Method Statement Example

Piling Cage Installation

If you are looking for a professional construction method statement example then this page is helpful for you. We help you to understand the structure and requirements of a typical construction method statement. The information given is useful for engineers and other construction professionals in their work. This leads obviously to prepare a good and safe work method statement i.e. …

Read More »

Cables & Wires Installation Procedure

Cables-and-wires-method-statement

a) Storage of Materials at Site All materials received at site shall be inspected and ensured that the materials are as per approved material submittal. Any discrepancies, damages etc.shall be notified and reported for further action. Material found not suitable for the project are removed from site immediately. Cables are stored with the factory packing on the flat surface with …

Read More »

Cable Trays and Ladders Installation Procedure

a) Storage All materials received at site shall be inspected and ensure that the materials are as per approved material submittal. Any discrepancies, damages etc. shall be notified and reported for further action. Materials found not suitable for the project are removed from site immediately. Cable trays and ladders are stored in horizontal position on flat surface with timber support …

Read More »

GI Cable Trunking Installation Method Statement

a) Storage of Material All materials received at site shall be inspected and ensured that the materials are as per approved material submittal. Any discrepancies, damages etc.shall be notified and reported for further action. Material found not suitable for the project are removed from site immediately. GI Trunking are stored in horizontal position on flat surface with timber support at …

Read More »

Ring Main Unit Testing and Commissioning Method Statement

Required tools for ring main unit testing and commissioning procedure: Primary Injection kit Contact Resistance kit High Voltage test kit 5.0 KV Megger Multi meters (Fluke Meters) Commissioning Phase The following sequence will be carried out for testing. Check the Bus bar tightness check with torque table mentioned below Check the Earthing Busbar tightness check with torque table below as …

Read More »

UV Sterilization System Testing and Commissioning Method Statement

Pre-Commissioning Phase and Start-Up Phase System Pre-Commissioning Checks for Filter Before commissioning the system the following shall be ensured. The system has been checked against the approved installation drawings. Check that the upstream pressure at the filter inlet is more than 2.5 bar (38psi) during the rinse cycle. Check that the filter is mounted in the correct flow direction. Check …

Read More »

Method Statement for Testing & Commissioning of Air Handling Units AHU & FAHU

Air Handling Unit AHU FAHU Testing and commissioning Method Statement

Prior to testing & commissioning ensure that all the sections of the Air Handling Units are thoroughly cleaned. In case units are supplied with per alumna panels, polythene protective film must be peeled off and must be ensured that no traces of film is left loose within the unit. Only qualified & experienced personnel shall perform testing & commissioning. Ensure …

Read More »