2024
Dec
7

Fire Protection Pipes and Fittings Installation Method Statement

Fire Protection Pipes and Fittings Installation Method Statement

This method statement covers the detailed procedure for installation of Fire Protection Pipes and Fittings. Procedure also defines the method used to ensure that the pipe work and fittings installation has been carried out as per the contract specification requirements. This method

2024
Dec
2

Disinfection and Flushing of Water Mains

Disinfection and Flushing of Water Mains

Purpose of this plumbing method statement is to ensure that disinfection and flushing of water mains and related pipe lines are executed safely and in accordance with the contract requirements and that all quality assurance / control activities are conducted in a

2024
Nov
6

HVAC Method Statement for Grill Diffuser and Louver Installation

HVAC Method Statement for Grill Diffuser and Louver Installation

This hvac method statement covers the supply & installation of grilles, diffusers louvers & disc valves in line with project requirements as indicated in the approved shop drawings, reflected ceiling plans, specifications and manufacturer’s instructions. Plant and equipment required General tool box

2024
Oct
9

Heat Exchanger Installation Testing and Commissioning Method Statement

Heat Exchanger Installation Testing and Commissioning Method Statement

Unless otherwise specified, all plate heat exchanger installation shall be in accordance to approved shop drawings, manufacturer instructions and contract specifications. Drawing plans, schematics, and diagrams indicate general location and arrangement of Heat Exchanger’s. Install Plate Heat  Exchanger’s as indicated unless deviations

2024
Sep
7

Chilled Water Dosing System Dosing Pot Installation and Testing Method Statement

Chilled Water Dosing System Dosing Pot Installation and Testing Method Statement

The purpose of this method statement is to define the steps to implement the correct practices for the installation of chemical dosing system (pot) for chilled water piping. By following this procedure contractor shall ensure that the performance of the chemical dozing

2024
Aug
29

Fan Coil Unit FCU Testing Pre-commissioning & Commissioning Method Statement

Fan Coil Unit FCU Testing Pre-commissioning & Commissioning Method Statement

This method statement is applicable for the Testing & Commissioning of Fan Coil Units for the project as mentioned in the project specifications & approved shop drawings. Before commencement of FCU testing & commissioning activity, the supervisor must ensure that pre-commissioning of

2024
Aug
24

Split Unit Testing and Commissioning Method Statement

split unit ac testing and commissioning

Below is a precise HVAC method statement that briefly explains testing and commissioning of split unit ac air conditioner. The test will be commenced after Split Unit installation and power supply panel T&C activities completed. All areas and fan inlet & outlet

error: Content is protected !!