Plumbing Method Statements

Sump Pump Testing Method Statement

This method statement covers the testing and commissioning of sump pump. The objective of this method of statement is to check that the sump pump installation is correct as per the manufacturer’s recommendations and to prove that sump pump volumetric performance is achieved. Testing and commissioning also covers the testing of the alarms associated with […]

Sump Pump Testing Method Statement Read More »

Construction Method Statements, Method Statements, Plumbing Method Statements

Vacuum System Testing & Commissioning Procedure

This method statement covers all processes related to the testing and commissioning of laboratory or hospital vacuum system. Implementation of this method statement requires reference to other relevant documents like inspection and testing plan outlining the responsibility and the quality verification to be performed by various parties. Other references include: Latest Approved shop drawings for

Vacuum System Testing & Commissioning Procedure Read More »

Method Statements, Plumbing Method Statements, Testing & Commissioning
water-heater-installation-method-statement

Method Statement for Installation of Electric Water Heater

The procedures for the installation and fixing of electric water heater with supports and accessories shall be done as per the manufacturer’s recommended guidelines and installation instructions and as per the approved water supply drawings/layouts and detailed drawing as follows. This method statement for installation of electric water heater must be changed as per site

Method Statement for Installation of Electric Water Heater Read More »

Method Statements, Plumbing Method Statements
hdpe pipe installation method statement pdf

hdpe pipe installation method statement

Below is a classic method statement for the installation of HDPE piping network for domestic water supply system. Any plumbing engineer can get benefit from below method of statement for submission to consultant for a construction project. Material received at site shall be inspected and stored according to manufacturer recommendations. Store the hdpe piping material

hdpe pipe installation method statement Read More »

Method Statements, Piping Method Statements, Piping Works, Plumbing Method Statements
Chilled Water Pipe Installation Method Statement

Chilled Water Pipe Installation Method Statement

This method statement covers on site installation of pre fabricated and site fabricated mild steel pipework including supports, expansion and anchor points for chilled water pipe system. By implementing this mechanical method statement on a project site contractor shall make sure that the chilled water piping system installation is as per project requirements i.e. specifications,

Chilled Water Pipe Installation Method Statement Read More »

Construction Method Statements, HVAC Method Statements, Piping Method Statements

Method Statement for Drainage Pipe Installation – PVC uPVC Drainage Piping Under / Above Ground

This method statement is applicable for all drainage pipe works underground, above ground, horizontal and vertical drainage piping for any kind of the project as specified in project specification. It is responsibility of project manager and project plumbing engineer to ensure the availability of coordinated drawings and the required materials as per the project specifications.

Method Statement for Drainage Pipe Installation – PVC uPVC Drainage Piping Under / Above Ground Read More »

Construction Method Statements, Method Statements, Piping Method Statements, Plumbing Method Statements
Copper Piping Method Of Statement For Installation

Copper Pipe Joint Method Statement | Flaring & Swaging

The purpose of this method statement is to establish a standard procedure for the proper cutting and jointing of copper pipe by using the right tools and procedure i.e. flaring or swaging joints. Below method will also serve as guideline for newly hired employee which will be dealing with air conditioning unit maintenance activity or

Copper Pipe Joint Method Statement | Flaring & Swaging Read More »

HVAC Method Statements, Method Statements, Piping Method Statements

Method Statement for Fire Fighting System Installation Testing & Flushing

The purpose of this method statement for fire fighting system installation is to ensure that correct materials & equipment are used and agreed procedures are implemented during fabrication, installation, testing and flushing of firefighting piping sprinkler system. This method statement specifies the sequence and construction methodology to be followed for the installation and testing of firefighting piping,

Method Statement for Fire Fighting System Installation Testing & Flushing Read More »

Construction Method Statements, Method Statements, Piping Works, Plumbing Method Statements
error: Content is protected !!
Scroll to Top