Category Archives: Plumbing Method Statements

Water Booster Pump Installation Testing and Commissioning Method Statement

Below is a precise method of statement for water pump or booster pump installation including the testing and commissioning steps. Make sure that proper clearance is available from civil side before commencement of water pump installation works. Ensure that the work area is clean and safe for carrying out the activities. Also prior to start… Read More »

Laboratory Gas Piping System Testing & Commissioning Method

This method statement covers all processes related to Testing & Commissioning of Laboratory Gas System, procedure is to be read in conjunction with the relevant ITP, outlining the responsibility and the quality verification to be performed by various parties. Project manager is overall responsible to make sure that all installations and testing activities are done… Read More »

Best Sanitary Installation Method Statement

This document describes best method for the sanitary installation to ensure that the installation works are conducted in compliance with the approved design, drawings and material submittals. Prior to the installation of Sanitary Wares, the supervisor and foreman will verify and ensure that all the health and safety requirements are considered and necessary control measures… Read More »

Piping Installation, Welding & Fabrication Method Statement

TABLE OF CONTENTS PURPOSE SCOPE REFERENCES DEFINITIONS RESOURCES RESPONSIBILITIES SEQUNCE OF WORKS QA/QC REQUIREMENTS HSE REQUIMENTS EMERANCY CONTACTS Purpose: The purpose of this methodology is to provide a systematic control and direction for the activity for the installation of piping at a construction site. This method statement provides the expectation to execute work in safe,… Read More »

Underground Drainage Pipe Installation Method Statement

The purpose of this plumbing method statement is to describe the methodology for underground laying of UPVC pipes as per the contract specifications and approved drawings, including the backfilling for the site facilities and to detail the steps to be taken to meet the quality and HSE requirements of the project. Method statement is applicable… Read More »

Method Statement for Hydrostatic Testing of Metallic Pipework

The purpose of this method statement is to make sure that hydrostatic pressure testing of chilled water piping system is done safely as per client requirements and applicable mechanical standards. Method statement covers the hydrostatic testing of chilled water steel pipework at the project and to be followed for all piping works at site. Prior… Read More »

Method Statement for Condensate Drain Piping Installation & Testing (UPVC + GI)

This method statement covers on site installation of all condensate UPVC pipes for fan coils drains and galvanized pipework for AHU drains, including supports, expansion and anchor points for the condensate drainage system and insulation of the galvanized steel and upvc pipework. The mechanical method statement defines the method that will be used to ensure… Read More »

Water Leak Detection System Testing & Commissioning Method of Statement

This testing and commissioning method statement defines the nature and method of Pre-Commissioning & Commissioning of Water Leak Detection System, which has been already installed and approved in the project. However, contractual terms and conditions shall be applied and enforced in case of any contradictory matters that may arise. Purpose of this method is to… Read More »