2025
Jun
21

Hot Water Calorifier Testing and Commissioning Method Statement

Hot Water Calorifier Testing and Commissioning Method Statement

This method statement is applicable for the testing and commissioning of hot water calorifier or water heater for any kind of building or projects. Arrange below tools before start of the work: Electrical Toolbox Box spanner set Pipe wrench Pre Commissioning Requirements

2025
Jun
20

Underground Coated Carbon Steel Piping Excavation, Installation, Jointing and Backfilling Method Statement

Underground Coated Carbon Steel Piping Excavation, Installation, Jointing and Backfilling Method of Statement

This mechanical method statement covers the excavation, installation, jointing and backfilling of underground coated carbon steel piping. The pressure testing of all steel piping system will be conducted in accordance with applicable Hydrostatic Test Procedure. Roles and Responsibilities Project Manager is responsible

2025
Jun
13

Aluminum Sliding Doors Installation Method of Statement

Method Statement For Installation Of Automatic Aluminium Sliding Door

Below is the procedure for performing the sliding door/ aluminum door installation for any kind of building project. Before start of the sliding doors installation work, make sure the approval of material submittal and subcontractor / supplier. Ensure that shop drawings is

2025
Jun
3

Occupational Health and Safety Procedure for Mobile Elevated Work Platform

Below is a precise procedure that provides instructions for the safe use of Mobile Elevated Work Platforms (EWP), applicable for all kind and size of projects. Overall project director and project HSE team is having responsibilities for the implementation of this occupational

2025
May
20

Method of Statement for Formwork, Rebar Installation and Concreting

Method Statement for Scaffolding, Formwork, Rebar Installation and Concreting

Below is a precise civil work method of statement that covers the detailed procedure for the scaffolding / formwork, rebar installation and concreting operation applicable for footing, pedestals and pile caps etc. Also to explain how footing, pile caps, trenches, grade beam

2025
May
3

Construction Methodology for Underground Services Protection

Construction Methodology for Underground Services Protection

Purpose of below safety method statement is to provide instructions for ensuring the safe operations involved with ground penetrations so that underground services are not damaged and also to ensure the safety of workers. Overall the project manager is having responsibilities for

2025
Apr
25

Plastering Method Statement

Plastering Method Statement

Below is a precise plastering work method statement that is very useful for civil engineers to understand how best quality plaster work can be done. This procedure covers the methodology to be followed for carrying out plastering in line with the approved

2025
Apr
22

Flooring Installation Method Statement for Marble and Granite Tiles Installation

Flooring Installation Method Statement for Marble and Granite Tiles Installation

This flooring installation method statement covers the detailed procedure to be followed for supply & installation of Marble and Granite tiles on floor, stairs, walls and counters and other areas as per the schedule of finishes for the project. Civil site engineer

error: Content is protected !!