Underground Drainage Pipe Installation Method Statement

Underground Drainage Pipe Installation Method Statement

The purpose of this plumbing method statement is to describe the methodology for underground laying of UPVC pipes as per the contract specifications and approved drawings, including the backfilling for the site facilities and to detail the steps to be taken to

2022
Feb
20

Underground Coated Carbon Steel Piping Excavation, Installation, Jointing and Backfilling Method Statement

Underground Coated Carbon Steel Piping Excavation, Installation, Jointing and Backfilling Method of Statement

This mechanical method statement covers the excavation, installation, jointing and backfilling of underground coated carbon steel piping. The pressure testing of all steel piping system will be conducted in accordance with applicable Hydrostatic Test Procedure. Roles and Responsibilities Project Manager is responsible