Electrical Method Statements

Electrical method statement is used for safe implementation and construction of electrical works.

Before performing any electrical engineering activity one must prepare a method statement for electrical work that will describe scope of work, references, responsibilities, required materials and resources.

The main section of an electrical method statement for construction shall contain steps for installation and construction of the electrical works and components.

We are providing editable method statement swms packages, you can check a sample of  free electrical method statement and after that decide about downloading the full package.

In addition to method statement you shall find inspection and testing plan, inspection/testing checklists and risk assessments for doing the work as part of method statement for electrical works.

Below you can find complete set of electrical method statements and also you can search from the top left section of this page.

In addition you can also find complete set of editable electrical method statement in the form of editable files which are in Word / Excel formats and you only need to insert logo of your company and it is ready for submission and approval.

Click here to download electrical method statements.

Method Statement For Installation Of CCTV Camera Security System

CCTV Camera Installation

Below is a precise method statement for the installation of CCTV camera system on a project. Contractor shall make sure that the installation is done as per project specifications, approved drawings and applicable regulatory requirements. List of necessary Tools Following tools shall be required to perform the installation of CCTV system. MATERIAL HANDLING & STORAGE: […]

CCTV Camera Installation Read More »

Electrical Method Statements
distribution board testing procedure

Main Sub-Main Distribution Boards Testing and Commissioning Procedure

Below is a precise method statement for Testing and Commissioning of Main Sub-Main Distribution Boards (MSMDB) Sub-Main Distribution Boards (SMDB) Distribution Boards (DB) and Consumer Units(CU) TESTING, COMMISSIONING AND START UP PROCEDURES Upon completion of equipment installation and prior to carrying out test runs, the Contractor shall visually inspect the installation and satisfy that the

Main Sub-Main Distribution Boards Testing and Commissioning Procedure Read More »

Electrical Method Statements, Testing & Commissioning
standby diesel generator installation instruction

Standby Diesel Generator Installation Instructions

Before the installation of standby generator the equipment shall be inspected and checked against the relevant general arrangement drawing, approved material submittal. Doors and Panels shall be checked to ensure proper opening and closes. Generator rating, name plate details, Breaker ratings, protection devices, indicators, voltmeter and ammeters shall be checked. The Presence of all identifying

Standby Diesel Generator Installation Instructions Read More »

Electrical Method Statements
PVC Pipe & Conduit Installation

Method Statement for PVC Electrical Conduit – PVC Pipe Installation

Plastic electrical pvc conduits are common item which is useful for electrical wiring using pvc pipe. Since these electrical conduits are not much stronger as compared to metallic GI conduits therefore need proper handling and storage. Plastic electrical conduit pipes while unloading shall be lowered properly, not dropped to the ground. While during the storage,

Method Statement for PVC Electrical Conduit – PVC Pipe Installation Read More »

Electrical Method Statements

Lead Acid Batteries Installation Operation & Maintenance

Before starting the batteries installation begins, inspect for signs of damage or missing components. Store the battery in a dry, clean and preferably cool and frost-free location. Do not expose the cells to direct sunlight as damage to the container and cover may occur. As the batteries are supplied charged, storage time is limited. In

Lead Acid Batteries Installation Operation & Maintenance Read More »

Electrical Method Statements

Procedure for Repairing Damaged Outer Jacketing of Cables by Wraparound Heat Shrinkable Sleeves

SCOPE OF WORK: This Method Statement describes the procedure for repairing the damaged outer jacketing of cables using wrap around heat shrinkable sleeves. TOOLS Cable preparation tools Cable manufacturer approved solvent Clean, lint free clothes Burning Torch Electrician’s tape Installation tools MATERIALS REQUIRED: The wrap around heat shrinkable cable sleeves used shall be as per approved

Procedure for Repairing Damaged Outer Jacketing of Cables by Wraparound Heat Shrinkable Sleeves Read More »