2023
Feb
7

Mobile Heavy Equipment Recovery Standard Procedure

The purpose of this procedure is to safely recover mobile equipment that may have been bogged, overturned, suffering from mechanical/structural failure, slipped over an edge or into a culvert, or similarly immobilized. It provides instruction for recovery operations that require the use

2023
Jan
11

Pedestrian Walkway Concreting – Broom Finish Concrete

Pedestrian Walkway Concreting - Broom Finish Concrete

The purpose of this concreting method statement is to define the guidelines for the preparation of the concreting work for pedestrian walkway (broom finish) and to ensure the safe execution of all the concrete works during construction phases of the project so

2022
Dec
20

Method Statement for Excavation & Backfilling for Open Foundations / Footings

Below is a brief method statement that details general procedures to be followed for excavation & backfilling of foundations, Sub-structures & Trenches for any type of the construction and road project. The method covers survey works, excavation, backfilling, compaction and area cleaning

2022
Nov
17

Standard Requirements for Furnishing, Fabrication, and Placement of Reinforcement Including bars, welded wire fabric, Ties & Supports

Installation Of Reinforcement Steel Bars For Footing, Strap Beam, Raft, Slab & All Structural Concrete - Steel Fixing

Below are standard specifications and quality control requirements for concrete reinforcement including tension, compression, and temperature reinforcing steel, including welded wire fabric, and epoxy coated reinforcing. The scope of work includes furnishing, fabrication, and placement of reinforcement for cast-in-place concrete, including bars, welded wire fabric, ties, and supports. Related

2022
Sep
28

Bored Pile (Cast-in-Situ) Construction Method Statement

Bored Pile (Cast-in-Situ) Construction Method Statement

The purpose of this document is to outline the proposed methodology for the construction of the cast-in-situ bored piles using temporary casings. Aim of the procedure is to detail the sequence and method of pile construction, identify the hazard, assess the associated

2022
Aug
21

Underground Fuel Tank Back Filling and Cathodic Protection Installation Procedure

Cathodic Protection System for Storage Tanks Installation Method Statement

Below is a brief method statement for Fuel Oil System, that covers the backfilling and cathodic protection of underground pressure vessel / fuel storage tank. Overall project manager is responsible for the implementation of project quality and safety requirements and achieving the

2022
Apr
14

General Civil Work Method Statement for Roads & Building Construction

Setting Out the Layout Refer to the final layout drawing prepared with reference to the actual demarcation, set back adjustments, final levels and other development works. Check if the site is cleaned and leveled properly by cutting or filling. Start the layout

error: Content is protected !!