Upon completion of the LV Distribution Board installation including proper terminations into each breaker, the same shall be offered up for inspection from consultants. Earth fault loop impedance test & earth leakage test for LV Distribution Board shall be done & recorded
Read Complete Method
The manufacturing of the busbar system shall comply to the latest edition of BS 158 and BS 159. All busbars and current carrying parts shall be manufactured to carry a current density of not more than 1.55 A/mm² and shall be capable
Read Complete Method
The checklist or test report for mdb, smdb and fdb can be used for testing and commissioning purpose as per the below given template. There is one another page on our website that provides full list of applicable tests and respective method
Read Complete Method