Category Archives: Plumbing Method Statements

Hydrostatic Testing Procedure Including Pigging, Draining, Swabbing and Drying of Pipelines

The purpose of this hydrostatic testing procedure is to list out various steps involved in hydrostatic pressure testing, pigging, draining, swabbing and drying of pipelines for any kind and size of pipeline project in line with the project specifications and applicable standards and regulations. Scope of work covers the water supply quality and treatment, Internal… Read More »

Method Statement for Hydrostatic Testing of Metallic Pipework

The purpose of this method statement is to make sure that hydrostatic pressure testing of chilled water piping system is done safely as per client requirements and applicable mechanical standards. Method statement covers the hydrostatic testing of chilled water steel pipework at the project and to be followed for all piping works at site. Prior… Read More »

Hot Water Calorifier Testing and Commissioning Method Statement

This method statement is applicable for the testing and commissioning of hot water calorifier or water heater for any kind of building or projects. Arrange below tools before start of the work: Electrical Toolbox Box spanner set Pipe wrench Pre Commissioning Requirements Before commencing the testing and commissioning of calorifier the following shall be carried… Read More »

Underground Coated Carbon Steel Piping Excavation, Installation, Jointing and Backfilling Method Statement

This mechanical method statement covers the excavation, installation, jointing and backfilling of underground coated carbon steel piping. The pressure testing of all steel piping system will be conducted in accordance with applicable Hydrostatic Test Procedure. Roles and Responsibilities Project Manager is responsible for overall management including quality and HSE requirements of all construction activities at… Read More »

Fire Protection Pipes and Fittings Installation Method Statement

This method statement covers the detailed procedure for installation of Fire Protection Pipes and Fittings. Procedure also defines the method used to ensure that the pipe work and fittings installation has been carried out as per the contract specification requirements. This method will be applicable for the installation of Fire Pumps, Valves, Zone control valves… Read More »

Disinfection and Flushing of Water Mains

Purpose of this plumbing method statement is to ensure that disinfection and flushing of water mains and related pipe lines are executed safely and in accordance with the contract requirements and that all quality assurance / control activities are conducted in a systematic manner, works are inspected and conformance is verified and documented for the… Read More »

Water Booster Pump Installation Testing and Commissioning Method Statement

Below is a precise method of statement for water pump or booster pump installation including the testing and commissioning steps. Make sure that proper clearance is available from civil side before commencement of water pump installation works. Ensure that the work area is clean and safe for carrying out the activities. Also prior to start… Read More »

Laboratory Gas Piping System Testing & Commissioning Method

This method statement covers all processes related to Testing & Commissioning of Laboratory Gas System, procedure is to be read in conjunction with the relevant ITP, outlining the responsibility and the quality verification to be performed by various parties. Project manager is overall responsible to make sure that all installations and testing activities are done… Read More »