METHOD STATEMENT FOR TESTING OF AUTOMATIC TRANSFER SWITCH

As part of the Field Quality Control as per specification clause, testing and commissioning of the ATS Panel will be carried out as per the enclosed Method Statement under the direct supervision of factory authorized service representative.

SYSTEM COMPONENTS

ATS Panel – covered under this method statement

TECHNICAL SPECIFICATION :

TEST EQUIPMENT EMPLOYED :

a) Insulation Megger (With Valid Calibration Certificate)

b) Digital Multimeter (With Valid Calibration Certificate)

c) High Voltage Test Set (With Valid Calibration Certificate)

VISUAL AND MECHANICAL/ELECTRICAL INSPECTION:

  • Compare equipment nameplate with drawings and specification.
  • Inspect physical and mechanical conditions.
  • Confirm components are as per drawings.
  • Check-up the mechanical on/off operation of all breakers.
  • Check the spring charging mechanism operations for MCCB.
  • Check-up the other additional /parallel operating controls for breakers.
  • Connect the control supply at the correct terminal and polarity.
  • Check the on/off operation of MCCB (in ATS circuit) electrically.
  • Observe external status indication lamp for operation of breakers.
  • Check the spring charging motor operation MCCB.
  • Check the manual operation of MCCB through the extended rotary handle or directly at the MCCB.
  • Check the operation of control circuits as per the drawing.
  • Check all the interlocks and selections as per schematic.

ELECTRICAL TESTS

Insulation Resistance Test

Before starting the tests, the testing area to be identified by surrounding rope/chain so that except testing personnel, nobody else can have access to the panel till completion of all test.

Using 2Kv megger the insulation resistance between

Phase to Phase
Phase to Neutral } To be tested for Power Circuit
Phase to Ground
Neutral to Ground

The maximum insulation resistance should be 0.2 Mega Ohm.

Using 500V megger the insulation resistance between

Phase to Phase
Phase to Ground } To be tested for Power Circuit
Neutral to Ground

The minimum insulation resistance value should be 0.1 Mega Ohm.

testing of ATS Switch

Dielectric  Test

Before starting the test identity, the area for safety purpose as per earliest test. Disconnect the cables connected to electronic components like U/V relays etc.

Using high voltage test equipment 2.5 Kv -to be applied between:

 

Phase to Phase
Phase to Neutral } for 1 minute
Phase to Ground
Neutral to Ground

 

The test withstand capacity to be observed.

 

MANUFACTURER’S RECOMMENDATIONS:

Manufacturer’s recommendations for testing and commissioning is herewith enclosed.

REPORTS

A   written  report   shall   be   furnished   to  certify   the  works   as  recorded  on  the  form attached to this document.

SAFETY

Only competent personnel will be carrying out the tests, and only authorized personnel will be present at the testing area.

TRAINING

Will be provided as per training schedule under the contract conditions, before handing over to the owner.

WORK DURATION

The procedure should not require more than 2 hours.

 

Inspection Checklist:

A. VISUAL MECHANICAL INSPECTION :
1 Compare equipment nameplate with drawings and specification.
2 Inspect physical and mechanical conditions.
3 Confirm components are as per drawings
4 Check-up the mechanical on/off operation of all breakers.
5 Check the spring charging mechanism operations for MCCB.
6 Check-up the other additional /parallel operating controls for breakers.
7 Connect the control supply at the correct terminal and polarity.
8 Check the on/off operation of MCCB (in ATS circuit) electrically.
9 Observe external status indication lamp for operation of breakers.
10 Check the spring charging motor operation MCCB.
11 Check the manual operation of MCCB through the extended rotary handle
12 Check the operation of control circuits as per the drawing.
13 Check all the interlocks and selections as per schematic

 

B. INSULATION RESISTANCE TEST :
IR BETWEEN INSULATION RESISTANCE VALUE M-Ohm
R-Y
Y-B
B-R
R-E
Y-E
B-E
N-E
C. DIELECTRIC TEST :
DIELECTRIC TEST BETWEEN LEAKAGE CURRENT                         VALUE Micro-Amps
R-Y
Y-B
B-R
R-E
Y-E
B-E
N-E

Discover more from Method Statement HQ

Subscribe to get the latest posts sent to your email.

error: Content is protected !!