RCC Precast Boundary Wall Method Statement

Below is a precise method statement for the rcc precast boundary wall construction and installation as per project specifications and approved drawings.

Quality requirements shall be complied during all activities as per project quality plan, specifications and approved method statements.

List of Equipment’s

Below is list of necessary plant and equipment for precast boundary wall related works.

  • Batching Plant / Transit Mixers
  • Concrete Vibrators 3HP
  • Concrete Needles 40/25mm dia.
  • Hydra F-15 Escort 8 ton
  • Welding Machines

Health Safety and Environmental Requirements

RCC Panels casting shall be carried out in designated locations, approved barricading shall be provided.

All site personnel shall wear suitable PPE Personal Protective Equipment.

For other activities such as handling of reinforcement, electrically operated equipment etc., safety devices/ precautions will be taken as per the approved project safety plan.

All precautions will be taken for carrying out the activity.

Precautions:

Caution boards indicating danger will be fixed at proper place.

Safe access should be provided.

During night works floodlight shall be used for lighting up the area.

All the workers and supervisory staff’s shall wear PPE s (Personal Protective Equipment) during the work execution.

The work methodology of the activity will be explained to all the key personnel and workmen involved in that activity and standing instruction will be given.

Daily inspection checklist to be completed by site engineers and safety personnel before starting the work.

The safety manager, through deputing safety personnel at the site, round the clock, will look after all safety aspects of the job.

Tool Box meeting to be conducted before starting the work on daily basis.

All the workmen will follow the safety rules.

All plants and lifting equipment used in work shall be tested by third party competent person wherever required.

Construction Methodology:

Panel Casting Panel Moulds:

10 Moulds for pre-cast panel casting shall be fabricated & erected as per drawing along with necessary supporting assembly for casting of Panels.

Similarly adequate moulds for casting of columns should also be arranged as per the drawing followed.

If required, depending upon the work progress and site requirement, further moulds may be fabricated.

Sequence of Casting Panels:

Clean the bottom shutter of the mould and apply shutter release oil.

Place the reinforcement cage in position for casting of Panel.

Fix the four sides formwork of mould.Safework Method of Statement for Production & Erection of Precast Concrete Boundary Wall Panel

If railing is to be provided, then fix the insert plate of size 2700×75×6 mm for railing as per the approved drawing.

Cast the Panel & column.

De-shutter the Panel by removing the four sides formwork of panel.

Carry out de-moulding operation with the help of Hydra.

Curing the cast panel for a period of 14 days in stacking yard.

Process/steps will be repeated till the total required casting is completed.

Concreting:

The concrete required (M-30) shall be produced as per the approved design mix at the centralized batching plat and transported by transit mixers to the pouring location.

Before pouring, concrete slump of 110+/-30mm shall be checked at pouring location.

Concrete placement will commence from one end to another in the same manner till completion.

Concrete should be poured by the use of chute ensuring that height of fall of Concrete is not more than 1.5 M.

The concrete shall be vibrated using 40mm/25mm diameter needle vibrators.

Concrete cubes shall be taken for testing of compressive strength as per applicable standards at pouring location.

Proper care shall be taken to see that concrete temperature shall not exceed 40 degree C.

De-shuttering:

The de-shuttering shall be commenced after the concrete has attained 7.5 MPA crushing Strength.

Lifting of Panels:

The Precast Panels shall be lifted using 2 number lifting hooks provided for the purpose in the top surface of panel using suitable hydra crane and shall be placed in stacking yard.

RCC Precast Wall Panel Erection:

Erection of pre-Cast Panel and columns shall involve the following steps:

  • Transportation
  • Pre-inspection
  • Lifting & fixing
  • Alignment
  • Reinforcement & shuttering
  • Concreting

Transportation of Panel:

Loading of Panel will be done by Hydra of suitable capacity in casting yard.

It will be tied with the trailer with the help of rope/slings properly.

Panel will be shifted to required location by trailer.

Either Panel may be unloaded directly by hydra crane during lifting or unloaded at site on ground with the help of suitable capacity hydra crane.

Panels will be lifted directly from trailer for launching.

Care shall be taken to ensure that Panels will be unloaded on ground exactly below the Lifting location.

Pre-inspection of Panel:

Panels shall be checked against any damage during transportation.

It should also be checked for status of reinforcement dowel.

Launching of Panel:

Lifting of Panel:

Lifting of Panel will be done with the help of hydra crane either from ground or from trailer.

Crane will be positioned at the suitable location to accesses maximum length.

Sling will be attached with lifting hook for lifting.

Panels lifted will be brought in pre-determined location.

Then it will be rest over deck in position required at respective location followed by fixing the Panels with U-bar.

Lifting & fixing of Panels will be repeated as above procedure.

Panels Alignment:

Panels alignment to be done by using suitable props.

Then for final alignment it shall be checked with respect to centre line.

Reinforcement Preparation:

For fixing of reinforcement for columns, bar bending schedule shall be prepared as per the approved construction drawings.

The re-bars should be rust free, or if required, it may be cleaned with wire brush.

Reinforcement shall be cut using cutting machines or manually as required and bent.

The reinforcement shall be transported to final location in trailer/truck or manually depending upon the lead.

Fixing of reinforcement:

The reinforcement shall be manually fixed into its position as shown in the construction drawing.

Lap length of 50D should be provided.

The reinforcement fixed shall be checked by Engineer in charge or his representative.

Shuttering

Before placing the shuttering, shuttering oil shall be applied on shutter face in contact with the concrete, to ensure easy removal of shuttering & proper concrete finish.

For preventing leakages from joints, rubber strip/foam strip shall be provided at the joints of shuttering plates.

Concreting:

The required grade of concrete, as per approved drawings shall be produced as per the approved design mix at the centralized batching plant and transported by transit mixers to the pouring location.

Before pouring concrete, slump of 90mm to 125 mm shall be checked at pouring location.

The concrete shall be placed by Concrete Bucket.

Concrete placing will commence from one end to another in cascading manner till completion.

The concrete shall be vibrated using 25mm/40mm diameter needle vibrators.

Concrete cubes shall be taken for testing of compressive strength as per applicable standards at pouring location.

Proper care shall be taken to see that concrete temperature shall not exceed 40 degree C.

Special care shall be taken for curing the concrete for 14 Days.