Aluminium Windows & Doors Fabrication Method Statement

Below is a brief method statement that is useful for fabrication of aluminium doors and windows. This method can serve as standard work instruction for aluminium fabrication works. At the end of this page you will find complete work instruction with images in detail.

List of necessary tools:

  • Drilling Machine, screws & drill bits
  • Pen/Pencil
  • Cutting Lists
  • Roller
  • Knife
  • Measuring Tape

Basic Health & Safety Requirements

  • Gloves, safety glasses & shoes must be worn at all times.
  • Step 4 & step 6: – keep the drill straight and keep away the fingers from drill bit.

Aluminium Windows & Doors Fabrication Work Instruction

  1. Receive Profile from cutting machine to Assembly Area
  2. Select appropriate angles for the profiles
  3. Before assembly check whether the height piece of door/Window shutter requires lock
  4. Drill holes in the profiles
  5. Mark the angles as per the holes provided & number the profile & angle
  6. Drill holes in the angles as per the marking
  7. Fit the angles to the profile as per the identification number
  8. Assemble the aluminium frame
  9. Check for the corners, if gap or mismatch is found correct them
  10. Fit the gasket as per the cutting list
  11. Fit the accessories as per the cutting list
  12. Check the dimensions as per the cutting list

Aluminium Windows & Doors Fabrication Method Statement