Below is precise method statement for demolition works that has been prepared to demonstrate the safe working method for the soft strip of internal fixtures/fixings and identified items, asbestos removal and demolition of the existing structure.
This safework method is to be read in conjunction with provided drawings and Hazard surveys.
This method statement is intended to be a live document in accordance with the applicable regulations.
Any amendments to this method statement due to unforeseen circumstances will be agreed in writing by the Project Director, Safety Adviser, Project Supervisor & forwarded to the Principal Designer/Clients Representative as appropriate.
INDEX:
- LOCATION OF THE WORKS
- EXTENT OF THE WORKS
- PROGRAMME OF WORKS
- EXISTING SERVICES
- SAFETY PROCEDURES
- ACCESS AND EGRESS
- SAFETY ARRANGEMENTS
- IDENTIFIED HAZARDS ( MECHANICAL & PHYSICAL)
- OPERATIVES AND TRAINING
- PERSONAL PROTECTIVE EQUIPMENT
- ACCESS
- COSHH AND RISK ASSESSMENT
- WELFARE ARRANGEMENTS
- SPECIAL WORKS
- ARISINGS
- PUBLIC / OTHER / EMPLOYEES SAFETY
- PROJECT MANAGEMENT
- PROJECT RESOURCES
- METHOD
1. LOCATION OF THE WORKS
The works are located at a heavily populated residential area.
2. EXTENT OF THE WORKS
The works, in summary, involves the strip out, including asbestos removal and demolition of existing building.
Demolition works, in summary, involves:-
- Creation and provision of project specific Health & Safety Plan as required by the Regulations – Principal Contractor duties;
- Creation and provision of project specific demolition phase method statements and associated risk/COSHH assessments;
- Registering site with Environment Agency for Hazardous site registration code – applicable when any type of hazardous substance is contained on site;
- The Client is to carry out all service disconnections feeding the site, Including any overhead services. All services are to be terminated outside the footprint of the site for safety purposes and written confirmation provided. Please Note: Start date cannot be confirmed until written confirmation is received.
- Erection of protective 2.4m Heras type fencing to encompass any site boundaries required and those openings created by the works to ensure prevention of unauthorized access;
- Protection at all times of adjacent properties and those accessing same;
- Protection at all times of adjacent roadways and pavements and those accessing same;
- Liaising with neighboring property owners/representative;
- Provision of fully trained NFDC/NDTG Site Supervisor for the duration of the project;
- Provision of suitable and sufficient welfare facilities to meet the CDM 2015 Regulations;
- Provision of fully trained CSCS/CCDO & CPCS workforce;
- Monthly external safety audits for the duration of the project with written reports issued;
- Fortnightly in-house safety audits for the duration of the project with written reports issued;
- Removal of all non-licensed asbestos containing products in line with HSE ACOP L143 – Work with materials containing asbestos;
- Removal of licensed asbestos containing products by specialist appointed contractor as per Control of Asbestos Regs 2012;
- Soft-stripping of structures;
- Demolition of structures in line with BS6187:2011;
- Demolition of sensitive areas by hand working methods;
- Breaking up all concrete floor slabs;
- Break up external concrete DDA ramp and handrails to the main entrance;
- Grubbing up of all footings to a depth of 5m;
- Grubbing up hard standings;
- Make good the ground and level excavated areas of site with suitable topsoil, compacted and graded alongside existing pavings;
- Leave site safe and clear to the clients satisfaction
To Include:
- Protection at all times of adjacent processing areas and those accessing same;
- Protection at all times of adjacent roadways and pavements and those accessing same;
- Protection of Clients employees or other contractors liable to be within the confines of the site;
RETAINING ITEMS
- Areas of hard landscaping retained by the building as per the appended landscape plan
- Any other TBA;
Any items for retention by the Client/CA will be documented, marked and relayed to all site operatives.
Demolition works which fall outside the development boundary covered by Planning Application are to be carried out to slab level only, with the slab/footings and associated hardstandings remaining.
PROGRAMME OF WORKS
Project Commencement Date:
Project Duration:
Working Hours: 07:30–18:00 hours Mondays to Fridays 07:30–13:00 hours on Saturdays
The general program for the works will be as follows:-
| Documentation & Notification |
| Section 80-82 notification from local Council – Subcontractor to issue – copy to be displayed on site; |
| F10 – provided by CDMC |
| ASB5 – to be submitted to HSE by licensed contractor; |
| EA – Hazardous Waste Site Registration – Subcontractor to obtain – site number to inserted on all hazardous waste consignment notes |
| Neighboring property notifications – Subcontractor to issue |
| M&E Disconnection Notices Issued by relevant services authority – Client to issue – copy to be displayed on site; |
| Scaffold Permit – N/A |
| Posting of courtesy notices advising of the impending demolition to all properties situated to the boundary of the site and those adjacent the site (including emergency contact no’s etc.); |
| Obtain service termination confirmation notices from the service providers. |
| Detailed method statement + associated risk assessments and provision of same to
respective parties |
| Site Set-Up | Site Supervisor to install:-
· Site fire plan including fire and assembly points etc.; · Installation – segregation/signing of internal traffic routes, public footpath and access/egress; · Erection of additional site fencing; · Designation of machine over-night secure zone; · Designation of internal vehicle turning points (as required); · Designation of site parking facilities; · Designation of further zones as required. · Safety issues pertaining to adjacent occupied premises ALL OPERATIVES TO ATTEND SITE INDUCTION |
| Service / Hazardous area Investigation & protection | · Careful investigation as to the exact layout of drains etc. feeding the adjacent properties will be carried out and the layout marked. Road plates or similar will be placed over any construction traffic cross-over points to prevent damage;
· Obtain Permit to Dig via Client prior to breaking of any ground to determine exact locations of underground services; · Movement of machinery from low-loader into site will be carried out at a suitable time so as not to cause additional hazard within the surrounding environment. |
| Removal of contaminants/hazardous substances | It is policy that all hazardous materials are removed, wherever possible, at the initial stage of the project to prevent additional exposure / double handling and enable safe, uninterrupted execution of the soft-strip & demolition stage of works. To include:- MMMF (man made mineral fibre) ACM’s – asbestos containing materials as identified in the demolition and refurbishment asbestos survey. Section 62 & Duty of Care consignment notes will be issued to the CDM Co-Ordinator for later inclusion within the H&S File if appropriate. |
4. EXISTING SERVICES
- OBTAIN PERMIT TO DIG PRIOR TO BREAKING OF ANY GROUND TO DETERMINE EXACT LOCATIONS OF UNDERGROUND SERVICES;
- OBTAIN WRITTEN CONFIRMATION OF DISCONNECTION OF SERVICES PRIOR TO COMMENCEMENT OF ANY SOFT-STRIP OPERATIONS;
- CLIENT INSTRUCTION:-
Prior to any works commencing, full investigation will take place to ensure that all isolation / disconnection works to relevant services have been completed and there are no remaining live services and that all pipes and cables have been isolated.
Written confirmation will be received from the Client;
IF YOU DO NOT HAVE COPY OF DISCONNECTION CONFIRMATION DO NOT START – SPEAK DIRECTLY WITH SUBCONTRACTORS PROJECT CO-ORDINATOR.
All service items which are to be retained will be suitably marked and brought to the attention of all operatives through on site tool box talks to ensure all persons are aware of the exact location of same.
All work carried out to or which affects new or existing services will be in accordance with the bye laws or regulations of the relevant statutory authority.
Internal temporary electricity will be supplied by use of generators. These will be sited to prevent disturbance to neighboring properties through noise/fumes etc. and will be effectively earthed.
All cables off will be suitably marked and placed so as to prevent tripping and damage.
Portable & hand held electric tools shall not exceed 110v and shall be inspected as per the established maintenance system:-
User Check: Weekly
Visual Inspection: Monthly
Combined inspection and test before use and thereafter 3 monthly.
Central & task lighting will be installed as appropriate and conform to BS & IEE standards.
5. SAFETY PROCEDURES
All operatives will be made aware of the extent and location of the works, informed of any restricted areas and possible areas where interaction with operatives or others is liable to be hazardous.
DANGER DEMOLITION signs and exclusion zone barriers will be erected to all areas as required. Any additional signage will be erected as required.
Edge protection, installed by a specialist contractor, will be erected to all areas where there is a risk of falls. Signage will be affixed to each barrier advising ‘remove this = lose your job’.
All areas referred to in the Location and Description of the works are closely surrounded by a residential environment, therefore extreme caution will be implemented when access and egress to the site is required.
Exclusion zone fencing is to be erected to encompass all site boundaries and internal exclusion fencing is to be erected where needed to prohibit access by site operatives into danger zones i.e. within the working radius of the excavator / drop zones etc.
All employees will ensure that the site is maintained in a clean and tidy manner. Removing scrap metals and debris from the work area progressively. (Good housekeeping).
NOTE: No fires are to be set on site, and no burning of any arisings will be carried out at any point.
Special Care will be taken to eliminate the risk of FIRE where hot cutting works are required. All hot works will be under Permit to Work Systems to be implemented by the Site Manager.
Fire extinguishers of a suitable type will be on hand, as will a banksman assigned to fire watch. Cold cutting to be employed where highly flammable materials are present or there is a risk of lead coatings.
6. ACCESS AND EGRESS
Existing traffic use & restrictions:
- The access route is via residential streets, which are narrow in part with park cars and traffic calming measures. Planning conditions are in place restricting working hours and the hours during which deliveries to and removals from site can be undertaken.
- Any large deliveries are to be carried out under banksman control due to continuity of surrounding environment – this is to be pre-planned with local residents due to parking cars on roadways etc., Subcontractor to make contact (either by speaking directly or letter drop for those who are no in) to advise of delivery time/area etc.
- The site is contained within a highly populated residential environment – and as such surrounding roads will be heavily congested throughout the works – ensure these are maintained clear and free of obstructions throughout the works;
- Access to site will be off Townroe Drive via the existing school entrance. This will be the point of entry to site for deliveries and disposal. Restrictions apply to the timing of vehicular access. No demolition traffic will arrive or leave site between 08.00 and 09.15.
- The neighboring properties consist of private dwellings, therefore it should be noted that others will be using these facilities and due care attention and courtesy is to be shown throughout – particularly when access/egress by construction plant is used, contractor to liaise direct with the neighboring representatives prior to commencement of works.
- Be aware that pedestrian/other vehicular traffic will ALWAYS have the right-of-way.
- Due to the site locality access by waste carriers is required to be pre-planned to prevent interaction with vehicles / personnel etc. employed within further buildings.
- There are main pedestrian crossing points to all surrounding roadways– ensure that these areas are kept clear at all times to ensure the safety of pedestrians etc.
- Surrounding properties are occupied and as such all safety requirements are to be advised to all operatives and unimpeded access provided throughout the works;
- Occupants of all neighbouring /surrounding properties will require unrestricted access to their places of work, therefore due care, attention and courtesy is to be afforded at all times.
- Care must be taken to prevent dust, pollution and debris from causing potential danger for both adults and children;
- In all cases due care, attention and safety is to be afforded to those persons/vehicles accessing the surrounding environment;
ENSURE THAT A BANKSMAN OVERSEES ALL MOVEMENT OF SITE VEHICLES INTO THE SITE TO PROTECT THE SURROUNDING ENVIRONMENT
Access/Egress:-
The main entry point will be the point of entry to site for deliveries and disposal. Restrictions apply to the timing of vehicular access. No demolition traffic will arrive or leave site between 08.00 and 09.15 and 14.30-15.45.
The following controls will be initiated at the access/egress point to the carpark.
- This route will be manned THROUGHOUT THE WORKS to control traffic flow and aid others accessing the surrounding areas;
- The banksman will oversee all movement of plant/vehicles requiring access to the site;
- Signage will be erected to advise all persons accessing the site to ‘sign in’ at the site office;
- Signage will be erected depicting the internal designated transit / parking route and site office with site contact telephone number;
- Signage will be erected at suitable points warning of site access point;
- The insitu gate will be locked at ‘quiet’
Particular care is to be afforded by all operatives and operators of plant when accessing / leaving site due to the continuity of the footpath which crosses this cross-over point.
Due to the nature of demolition and the waste produced, vehicles removing the waste will be of large nature – 20T tipper wagons, skip wagons or roll-on-roll-off container transports.
The frequency of these will vary throughout the demolition, but at the peak may reach 6 wagons per hour loading excavated debris.
These will be coordinated to avoid queuing on the highway.
A copy of the access / egress route and site contact telephone number will be held within the main office of contractor and faxed/emailed to any contractor engaged for the removal of materials or the supply of plant and machinery prior to movement taking place. This will ensure suitable warning is given to site and enable traffic movements to be pre-planned.
A banksman will be employed for movements of construction plant / vehicles across any cross over point and all drivers of construction traffic will adhere to the existing applicable speed restrictions.
These access gates will be kept closed with an operative assigned to oversee all movements. All other access gates will be locked and secured against trespass.
7. SAFETY ARRANGEMENTS
Safety, health & environmental advice and auditing is carried out by in-house SHE department. Their role is to make periodic site visits to advise on Health & Safety matters, to assess hazards and risks, ensure adequate controls are implemented and monitored and to assist in the on-going training of company operatives.
8. IDENTIFIED HAZARDS ( MECHANICAL & PHYSICAL)
The surrounding public walkways, residential environment and occupied business premises/car parks.
Noise and Dust are environmental hazards affecting both operatives and people in the immediate vicinity during demolition and loading procedures.
The nature of intended work at height creates an on going hazard during the removal process.
Falls from height, falling materials and tools, slips, trips, cuts and scrapes.
Fire – Ensure all preparatory safety works are installed;
Asbestos – ensure all works are carried out as per the written method
RISK ASSESSMENTS FOR SITE SPECIFIC HAZARDS ARE INCLUDED.
9. OPERATIVES AND TRAINING
There will be one fully trained NFDC/NDTG site supervisor involved in the project.
All operatives to be employed on site will have completed the Safety Awareness Course for Demolition Operatives.
Operatives are bonafied ‘CSCS – CCDO Ticket’ holders or have applied under the scheme and awaiting their cards (evidence of this will be held on site within the main site file).
All personnel will adhere strictly to the Codes of Practice for Demolition BS 6187:2011.
Site operatives are to attend Site Induction prior to commencement of the project. The Project Supervisor/s will ensure Tool box talks are given on assignment of work tasks and additional talks given on a weekly basis.
All further training deemed necessary to carry out the safe conclusion of the works will be appropriated. Specialist training courses e.g.; MEWP, Abrasive Wheels, will be carried out to suit requirements.
10. PERSONAL PROTECTIVE EQUIPMENT
The following items of Personal Protective Equipment will be worn on site by all operatives.
i. ALL SITE PERSONNEL: Gloves, Goggles, Respiratory Protection, Safety Boots, Hard Hats, Reflective Jackets/vests, Dust masks (EN149FFP2S)
ii. HOT-CUTTING OPERATIVES: As i above plus gauntlets, flame retardant overalls, tinted visor.
iii. OPERATIVES WORKING AT HEIGHT: As i above plus full body safety harness, safety line.
iv. ASBESTOS REMOVAL (non-licensed):
Disposable coveralls (elasticized ankles, hood and wrists); Safety Boots; Hard Hats; Goggles; Gloves; Half Face Masks (EN149 FFP3)
All PPE will be issued to operatives as and when conditions of work and or when deterioration of existing issue is noted.
Each operative is responsible for ensuring the good condition of his PPE. (Regulation 11. PPE Regs’ 1992 )
The Site Supervisor will monitor all PPE on a daily basis as part of the on going Health & Safety program.
A register of all PPE issued is kept on site.
11. ACCESS
Access to any above ground work areas will be achieved using one or more of the following safe means of access, as appropriate.
Approved Tower/podium scaffolding erected in accordance with manufacturers recommendations;
LADDERS OR STEP LADDERS ARE NOT PERMITTED ON SITES – SUPERVISOR CARRY OUT AN ASSESSMENT FOR EACH AREA REQUIRING ‘WORKING AT HEIGHT’
12. COSHH AND RISK ASSESSMENT
All work covered by this Method Statement will be undertaken with due regard for the Control of Substances Hazardous to Health Regulations 2002.
Contractor has prepared a series of COSHH assessments to cover substances to be introduced by them during the works, these typically are;
- Propane ( Including cutting flame )
- Mineral oils and greases
- Concrete and brick dust
- Hygiene materials
Additional assessments will be prepared for any residual materials contained within the building and encountered during the works.
Risk Assessments have been carried out as required by the Management of Health & Safety at Work Regulations 1999 to document all perceived risks in respect of operations carried out on site.
These will be conveyed to all operatives during site induction and made available for the duration of the works.
Further assessments will be carried out as the works progress and the necessary controls implemented.
13. WELFARE ARRANGEMENTS
Contractor will provide adequate facilities to meet the requirements of CDM 2015, these are to include:-
- Site accommodation with sufficient space and seating arrangements for the number of operatives employed on site, to allow them to take meal breaks with the facility for hot water and food
- Drinking water
- Washing facilities with a supply of hot running water, including a supply of soap and towels.
- Suitable and sufficient plumbed in toilet
- Clothes drying
Arrangements will be made for all toilets and welfare facilities to be cleaned and restocked on a regular basis.
Should the number of operatives on site increase, additional sufficient welfare facilities will be, if required, placed on site.
14. SPECIAL WORKS
- Refer to Access/Egress restrictions item 6;
- Refer to Clients rules contained within your site file – all conditions set are to be abided by throughout the works.
- There is no smoking in any area (apart from specific designated area), due to high risk to others / building. Where hot-cutting is required all works are to be under hot-works permit system with fire watchers appointed. The site supervisor is to inform all site personnel of this rule during site induction and post signage throughout the structure;
- On arrival on site ALL delivery drivers/visitors and personnel must report to the site reception to obtain instruction. UNDER NO CIRCUMSTANCES SHOULD ANYONE VENTURE ONTO THE SITE BEFORE REPORTING TO THE SITE OFFICE, SIGNING IN AND OBTAINING INSTRUCTIONS.
- Full public protection measures are to be installed and maintained around the site boundaries due to the high number of pedestrian/cycle/vehicular traffic;
- There are hazardous substances on site:-
- Asbestos – this is a carcinogenic resulting in lung cancers / mesothelioma; Ensure that reference to the refurbishment and demolition survey is made. All works relating to the removal of asbestos are to be carried out by licensed operatives (whether stripping licensed or non-licensed asbestos) in fully isolated conditions. Asbestos to be sealed and segregated and disposed of to a licensed
- There are likely to be others within the site confines during the soft-strip/demolition works i.e. asbestos strippers etc. Ensure that all parties are aware of their designated working areas and any restricted / hazardous areas. All contractors will be under subcontractors control – ensure site rules are complied with and all attend site induction & tool box talk training throughout their duration on site. Report any non-conformities immediately to subcontractors safety rep for further investigation;

- Ensure that all necessary safety precautions relating to each required phase of works, including access and ejection of materials, are addressed and installed/available prior to commencement – this will include, but not limited to, erection of ply sheeting to windows to each working area etc.;
- It will be mandatory for ALL operatives to wear their correct PPE/RPE and those working at height to wear safety harness’s on this project. Anyone found not wearing PPE/RPE will be removed from site and wages donated to LOROS – Supervisor to issue all persons with site notice advising of this fact;
- Demolition works will disturb the established fire exit routes in place throughout the structures – ensure that suitable exit routes are available from each work area at all times. These routes must be signed and re-located as work dictates;
- Waste removal is to be pre-planned due to the locality of the site. A drop-zone is to be installed and controlled to permit easier removal of waste materials directly into a waste skip wherever practical.
- Each section to be removed is to be size reduced so as to reduce risk of manual handling issues.
- There is asbestos containing materials on site – refer to survey and associated method found within the site file and relay localities to all site personnel to prevent damage etc. A licensed contractor are to remove the licensed materials – Subcontractor is to remove all non-licensed items as detailed within the report – refer to method;
15. ARISINGS
All arisings from these works will fall into four main categories;
Clean Material of Commercial e.g.; Scrap metals, reclaimed building materials.
These will be handled with the necessary care and transported from site by road transport for commercial disposal/recycling in full conformance with the Waste (England & Wales) Regulations 2011.
Duty of care ticket to be produced for each consignment off site.
Concrete and Brick Rubble:
This will be handled by mechanical methods and removed from site in full conformance with the Waste Regulations.
Paper, Wood and other:
Will be removed from site via road transport and where applicable will be in full conformance with the Waste Regulations 2011. Duty of care ticket to be produced for each consignment off site.
Asbestos & Hazardous Waste Materials:
Care to be taken that all ACMs are sealed within the confines of hazardous areas, and kept segregated from other waste streams.
This and any other hazardous waste discovered in the course of the demolition is to be disposed of via licensed carriers to a licensed tip in a manner appropriate to the waste material encountered.
16. PUBLIC / OTHER / EMPLOYEES SAFETY
The safety of the General Public is of paramount importance to the operation in particular to those accessing the public footpaths and surrounding town centre environment, and employees accessing their place of work.
Banksmen will be employed and movements of waste programmed to reduce risk to the lowest level practicable.
Danger Demolition signs will be erected in prominent locations around the boundary of the site to warn of the dangers of access to the working area.
In addition Heras type fencing panels will be mounted to create exclusion zones around hazardous areas (i.e. openings to floors etc.) and the working areas as work dictates.
17. PROJECT MANAGEMENT
COMMUNICATION
On a daily basis communication will be relayed from the site supervisor to the Project Director.
Should it be deemed necessary the Project Director will relay findings to other members of the project team, which will include the Principal Designer, SO, Safety Advisor and / or sub- contractor.
Any exchange of design information as required will be advised to the Principal Designer.
A ‘Daily Hazards Board’ will be displayed in the site canteen/messroom (or other prominent position) detailing specific hazards to be noted and morning briefing carried out to remind all persons working on the site to bring to the attention of the Site Supervisor any matters relating to health and safety which they think require remedial action.
Operatives are encouraged to raise issues they see or foresee on site. The Site Management will consider their comments and take appropriate action. They will inform the person who raised the issue of the action taken or the reason why no action has been taken.
They will inform the person who raised the issue of the action taken or the reason why no action has been taken.
If the Site Management raises any health issues with Contractor’s Supervisors or employees, they will record an entry in the site diary, outlining the problem and action taken.
An internal weekly progress meeting will be held with all project management personnel.
18. PROJECT RESOURCES
Mechanical & Loading operations:
1 No. 360 deg. Wheeled Excavator with grab /shear attachment – 18 Tonne – External noise 104dB (A) /cab noise 74 dB (A);
RORO Lorries
Rubbish Skips
Crew Vans
Access Equipment:
Tower/podium Scaffold Unit/s – of varying sizes dependent on space available;
LADDERS OR STEP LADDERS ARE NOT PERMITTED ON SITES – SUPERVISOR CARRY OUT AN ASSESSMENT FOR EACH AREA REQUIRING ‘WORKING AT HEIGHT’
Flame Cutting Equipment (if required)
Oxygen & Propane Cylinder (stored safely in secure site cage);
Hoses;
Cutting Heads;
Flashback Arresters;
Fire Fighting Equipment
Electric Tools (if required)
Hilti (low vibration) breakers
Angle Grinders
Tile lifter
Hand Tools / Misc.
Sledge Hammers
Mattocks
Shovels
Wheel Barrows etc.
Back-pack spray units
Asbestos waste sacks;
Cloth adhesive tape 1000 gauge polythene
Mobile water bowser + spray attachment
19. DEMOLITION METHODS
19.1 SITE SET UP METHODOLOGY
SITE MANAGER/SUPERVISOR DUTIES:
- Inspect site fencing and ensure sufficient designation of areas for waste skips / storage etc.
- Liaise with any adjacent properties to ensure all are aware of the works.
- Collate all applicable information relating to requirements of adjacent properties regarding access, movement etc.
- Liase with main office / Local Authority to ensure all applicable licenses etc. are in place for the specific works area.
- Site all applicable signs (all visitors report to site office / danger demolition / hard hat signs etc), including main Contract sign, as depicted within tender documentation.
- Erect additional fencing as required.
- Carry out inspection of all fencing etc. to ensure security is maintained and put in appropriate additional measures where required.
SITE COMPOUND:
First task will to designate and position the following:-
- Fuel storage area;
- Oxy/Propane storage area (vented cage showing empty & full);
- Equipment / Plant storage
DOCUMENTS:
Site supervisor / designated person:
- To post F10, H&S Poster, Site Rules, Method Statements, Risk Assessments, First Aid requirements Section 80 building control etc. within provided site cabin.
| ASSOCIATED RISK ASSESSMENT No.’s | 22, 44 |
| ASSOCIATED | s.2 of the Health Safety at Work Act 1974 |
| LEGISLATION | CDM2015
Manual Handling Regs Control of Noise at Work 05 PUWER 98 COSHH 2002 PPE Regs. 92 |
19.2 SERVICE INVESTIGATION / INSTATEMENT
- ALL SERVICES ON THIS PROJECT ARE TO BE DISCONNECTED/ISOLATED BY ARRANGMENT OF THE
- PERMIT TO DIG TO BE OBTAINED FROM KIER PRIOR TO BREAKING OF GROUND;
- DUE TO CONTINUATION OF ADJACENT PROPERTIES THROUGHOUT THE WORKS A CAT SCAN IS TO BE CARRIED OUT & ALL SERVICES NOTED MARKED UP AND PROTECTED THROUGHOUT THE WORKS – WHERE NECESSARY THIS WILL INCLUDE ERECTION OF INTERNAL HERAS FENCING TO SEGREGATE THE SERVICE RUN TO PREVENT ACCESS BY PLANT/MACHINERY ETC.
19.2.1 INVESTIGATION:
Information concerning existing services within the site and surrounding area has been obtained from the client.
Supervisor Note: No certificate – No start
All isolation / diversion / purging of M&E supplies are to be carried out by others therefore written confirmation will be received from the Client by site supervisor before commencement of demolition works.
Any retained services will be marked with suitable high visibility materials and road plates positioned over all cross over points required
19.2.2 DISCONNECTION / CAPPING OFF OF SERVICES & (where required) INSTATEMENT OF 110V FEED TO EACH FLOOR
A competent external contractor will be engaged to carry out these works where required (these works will be instructed and be under the control of contractor).
19.2.3 INSTATEMENT OF CENTRAL AND TASK LIGHTING
Where necessary central and task lighting will be installed by a competent electrical contractor. Particular attention will be paid to all emergency exit routes and hazardous areas (these works will be instructed and be under the control of the subcontractor).
RECORDS
The site supervisor will ensure that all information relating to location of all capped services is relayed to the CDM Co-Ordinator for inclusion in the File.
| ASSOCIATED RISK ASSESSMENT No.’s | 71, 74 |
| ASSOCIATED LEGISLATION | s.2 of the Health Safety at Work Act 1974 Working at Height Regs 2005
The Electricity at Work Regulations 1989 Institution of Electrical Engineers Wiring Regulations Road & Street works Act 1991 CDM2015 |
I have read this method statement specific to the work tasks which I am to carry out. I have brought to the attention of the supervisor any areas of the method which I do not understand and have had them explained. I understand it is my duty to ensure the safety of myself and others around me and will bring to the attention of the supervisor any unsafe work practices or conditions which come to my attention. I will wear all necessary PPE/RPE.
| NAME | SIGNATURE | DATE |
19.3 SET UP OF EMERGENCY PROCEDURES
Site Supervisor to:
Position First Aid equipment within site cabin;
Designate Fire Marshall/s – whose duties will include:-
- Pre-planning and positioning of fire extinguishers and airhorns
- Removal of fire extinguishers and air horns at day end to secure unit
- Reinstatement of same at start of day prior to works commencing
- Inspection of stairwell lighting daily
- Inspection of emergency exit route daily (particularly stairwell) to ensure clear
- Oversee any ‘hot’ works via permit system
- Direct emergency vehicles into the site.
Designate Muster Point
Organize instatement of fire extinguishers with site supervisor.
Post emergency exit signs and Emergency Layout Fire Plan to all floors;
Post emergency procedures within site welfare unit;
EMERGENCY PROCEDURES
First Aid
The requirements for first aid provision are contained in the Health and Safety (First Aid) Regulations and the Approved Code of Practice to the Regulations.
A first aid box is provided in the [Site Supervisor’s Office]. The contents are as indicated in the Company Safety Policy.
The Site First Aider will be responsible for ensuring that the contents are replaced as necessary.
A trained First Aider is available on site. The name of that person and the location of the first aid box is posted in the messroom/canteen.
Medical Assistance
The phone number of the nearest hospital and route is displayed on the site notice board.
A copy of the A-Z map for the area with the route to the nearest hospital accident and emergency unit clearly highlighted will be pinned to the wall of the site office with the note
Remove and use in the Case of Emergency.
The following notice will be pinned within the site welfare facility and where necessary due to work locations, distributed to all personnel on site.
– Nearest Accident & Emergency Hospital:
– MINOR INJURIES & URGENT CARE CENTRE – such as suspected broken bones, infections and non-traumatic joint
The site telephone is:
Emergency services to enter via Access Point (or other as instructed – dependent on position of fire).
EMERGENCY PLAN
The Management of Health and Safety at Work Regulations require every employer to prepare a plan which sets out the action to be taken in the event of any emergency.
a. Introduction
The aim of this plan is to highlight any situation, which will require the evacuation of all, or part of the site and to outline the procedure to be followed. This will help to identify quickly whether any personnel are missing and set in motion the rescue procedures.
Possible hazardous situations which may occur are:
Fire in cabins or vehicles, explosion or fire in the site area or compound caused by LPG, accidents in confined spaces or scaffold collapses.
b. Control
Control over any incident will be exercised by the Site Supervisor who will remain at the main assembly point throughout.
They will detail one person to act as a guide for the emergency services. The guide should be positioned at the main entrance to the site.
c. Communication
A representative from the contractor will manage the site mobile telephone throughout the emergency and will be responsible for alerting the emergency services.
d. Assembly Point
The assembly point(s) will be at – SITE ACCESS POINT.
e. Action on Fire
Person discovering the fire will alert other personnel by shouting “FIRE; FIRE; FIRE” or operate the alarm (in the situation where the fire alarm has been disconnected due to the works operate the Air Horn provided).
If the fire is a small one, attempt to put it out using the appropriate fire extinguisher. DO NOT PUT YOURSELF IN DANGER.
Go to the assembly point.
All Contractors:
- Isolate any gas appliances.
- Go directly to the assembly point and report to the Site Supervisor.
- The Senior Person from each Contractor must check if anyone is missing. At the assembly point, Contractors are to report to their supervisors and all other persons are to report to Site Management.
Site Supervisor:
- On being alerted of an incident, sound the alarm (if appropriate).
- Obtain outline details of the emergency and alert the emergency services.
- Detail a guide to direct the emergency services onto the site.
- Detail a member of the management team to man the telephone.
- Go to the assembly point and assess the situation.
- Check with Contractors if any operatives are missing.
- Standby the Fire Fighting Team (if appropriate).
- Receive and brief the emergency services, giving the location of the emergency water supplies/hydrants (as appropriate).
f. Action on Explosion or LPG Escape
As above, except that no attempt should be made to fight the fire. The Site Supervisor will select a suitable assembly point which is upwind of the gas.
g. Action on Confined Space Accidents
At the first instance of an incident, alert the nearest person who should in turn alert the Site Supervisor.
The banksman must remain in position. They must not under any circumstances enter the confined space. They should, with the assistance of others, attempt to pull out any incapacitated person (if they are attached to a safety line and are wearing a safety harness).
Site Supervisor must ensure that nobody enters the confined space. Rescue procedures will be undertaken by the Fire Brigade on their arrival.
h. First Aid
A first aid kit must be taken to the assembly point. The trained First Aider must report to the Assembly Point.
i. Emergency Services
- The Fire Service should be summoned to all the above incidents (f; g or h). The Ambulance Service must be summoned to any confined space incident, LPG explosion or drowning incident. They should be summoned to any fire or other incident if it is thought that there has been an
- The Site Supervisor at the assembly point will receive and brief the emergency services, giving details of any missing
FOLLOWING SITE AND EMERGENCY PROCEDURES SET-UP THE SITE SUPERVISOR OR COMPANY SAFETY ADVISOR WILL CARRY OUT THE SITE SPECIFIC INDUCTION TALK.
THIS WILL INCLUDE INTERACTION WITH OTHER TRADES / SITE RESTRICTIONS / SITE RULES / EMERGENCY PROCEDURES / SITE COMMUNICATION ETC.
19.4 Erection of Heras Type Security Fencing
Scope of works:
- Erection of internal fencing to designate internal zones; protect operatives from hazardous areas (i.e. drop-zones; openings to floors; segregate further contractor/s from demolition zones).
- Erection of external boundary security fencing to all elevations required (i.e. internal roadways / car-park etc. to form exclusion zone).
Site Supervisor to refer to site layout plan showing exact layout of fencing and access points;
Calculate required number of panels / blocks to each area and designate ‘drop off’ area for required number of panels at each elevation;
Instruct delivery driver to position required amount at each designated point to reduce manual handling risk;
Phase works to ensure unimpeded access for further deliveries (welfare / storage units etc);
Site supervisor to appoint ‘gang’ to erect same ensuring all are issued with correct PPE: Safety Boots to protect crushing of feet; Rigger gloves to prevent cuts, grazes etc. and high visibility jacket/vest to ensure visible to all others on site particularly vehicle drivers.
Two operatives will be assigned to position bases – these operatives will be instructed in the correct lifting procedures to prevent manual handling problems – and two further operatives will follow through with the fencing panels and fixings.
On completion the operatives will affix warning notices to all elevations.
The site supervisor to assign one operative to inspect boundary fencing at start and end of shift to ensure all panels / clips in place etc. Any non-conformities to be reported to supervisor immediately.
| ASSOCIATED RISK ASSESSMENT No.’s | 22, 44; 75 |
| ASSOCIATED LEGISLATION | CDM 2015
The Manual Handling Regulations |
19.5 SOFT STRIP METHODLOGY
NOTE #1: – PRIOR TO ANY WORKS COMMENCING SPEAK TO THE SITE SUPERVISOR TO ENSURE ALL LOCATIONS OF ASBESTOS CONTAINING MATERIAL ARE KNOWN – DO NOT REMOVE ANY ITEMS WHICH WILL CREATE DISTURBANCE OF THIS MATERIAL.
NOTE #2:- IF YOU LOCATE ANY SUSPECT MATERIAL STOP WORK AND REPORT IT IMMEDIATELY TO THE SITE SUPERVISOR & INFORM OTHERS AROUND YOU.
NOTE #3:- CARRY OUT AN ASSESSMENT OF THE WORKS/AREA BEFORE COMMENCEMENT OF TASK – – IF THERE IS TO BE HOT CUTTING ENSURE HOT- WORK PERMIT IN PLACE – IF WORKS WILL CREATE AN OPEN EDGE ENSURE SUITABLE PRECAUTIONS ARE TAKEN AGAINST FALLS (BE IT DURING OR AFTER THE WORKS) – CARRY OUT A NOISE ASSESSMENT AND INSTALL MANDATORY HEARING PROTECTION ZONES AS REQUIRED;
NOTE #4:- SOFT-STRIP WORKS WILL GENERATE A LARGE QUANTITY OF COMBUSTIBLE MATERIALS. ENSURE THAT MATERIALS ARE REMOVED FROM THE WORKFACE IN A PROGRESSIVE AND SAFE MANNER.
NOTE #5:- THERE IS TO BE NO SMOKING WITHIN ANY PART OF THE STRUCTURE THROUGHOUT THE WORKS. IF YOU ARE FOUND TO DISOBEY THIS RULE YOU WILL BE DISMISSED.
NOTE #6:- ENSURE THAT THERE IS ADEQUATE MEANS OF ESCAPE FROM YOUR WORKING AREA AND FIRE FIGHTING EQUIPMENT AVAILABLE AT THE WORK-FACE. ADVISE THE SITE SUPERVISOR OF ANY CHANGES TO ESTABLISHED FIRE EXIT ROUTES THAT ARE CREATED BY YOUR WORKS.
NOTE #7: ENSURE OPTIMUM CARE IS TAKEN TO PREVENT DAMAGE TO THE STRUCTURE TO ENSURE THE SAFETY OF OTHERS ADJACENT TO THE WORKING AREA;
NOTE #8:- ENSURE GLOVES ARE WORN THROUGHOUT ALL WORKS
NOTE #9:- ENSURE A WORKING AT HEIGHT ASSESSMENT IS CARRIED OUT WHERE ANY WORKS AT HEIGHT ARE REQUIRED;
The works involves the removal (soft strip) of all internal fittings – to include:-
Strip out of internal items to include removal of all redundant services, fixtures, fittings, partitioning, floor coverings etc.
PRIOR TO COMMENCEMENT:-
All operatives will receive on site induction and additional tool box talks to ensure they are aware of hazardous areas, any drop-zones and exact location of the works, emergency routes etc. specific to the work zone.
Ensure appropriate disconnection certificates are available for services feeding the area.
Suitable signage and exclusion zones will be erected to prevent/alert persons of the risk of entering the working area during soft-strip operations. Where removal of items is carried out at height no persons will be allowed to enter the area below the working zone.
All access equipment required for the works will be assessed and installed prior to commencement.
All works will be carried out by the use of hand tools in a controlled manner. Where necessary barrows/trolleys etc. will be utilized to prevent manual handling problems.
All soft strip materials will be removed from site progressively to prevent a build up of combustible materials via the insitu rear fire escape. Priority will be given, at all times, to others within the structure and assistance offered where required.
Loose fixtures & fittings i.e. cupboards; shelving;
These items will be removed by hand and removed systematically from the work area to the designated waste area for loading into skips for removal from the site. This will be carried out following the generation of a suitable amount of waste materials to prevent a build-up of combustible materials.
Care will be taken when removing abandoned waste to ensure sharp’s or chemical residues are not present. Suitable PPE will be worn for all works.
A manual handling assessment will be carried out before lifting larger items and where the risk cannot be adequately controlled the item will be broken up to aid movement/prevent injury etc.
Redundant heating units (overhead & wall mounted) and associated pipework; Electrical cabling & lighting units;
Prior to commencement of any of these removal works an assessment of the surrounding environment will be carried out. The following safety precautions will be carried out:-
Where items are at height:-
- the area below will be demarcated as a NO-GO area for all operatives not involved with the works.
- A safe work platform will be erected – tower scaffold or staging unit will be employed (dependent on space available). This will be erected by competent operatives in accordance with manufacturers recommendations. Toe boards will be
Where cast iron materials are involved:-
- the area below and immediate surrounding area will be demarcated as a NO-GO area for all operatives not involved with the
- Plyboard sheets (or similar) will be positioned at adjacent windows;
- Goggles (high impact) will be provided and worn;
- Carry out a manual handling assessment;
Where items are adjacent to asbestos products:-
- If possible do not remove the item until the asbestos contractor has carried out his works;
- If removal required to aid asbestos contractor, cut off below fixing brackets to prevent damage to material;
Where flammable materials are sited within the vicinity
- Appoint fire-watcher to oversee all works and check following completion;
- Damp down area;
- Position fire blankets to floor areas;
- Position fire fighting equipment immediately adjacent work area;
- Carry out cold-cut techniques wherever
- Work in accordance with Hot-Work
SAFE WORKING:
All works will be carried out in a methodical manner working back towards the main fire exit stairwell at all times. Pipework will be cut out using either quick-cut or hot cut methods or where risk of fire pipe cutters will be employed.
Cables to overhead heater units will be severed using cable cutters and the hanging brackets unbolted wherever possible or severed using Stihl saws.
Wall mounted heaters/radiators will be prised/dismantled from their fixings and carted from the work area. Associated pipework/cables will be removed in a methodical manner using cable cutters / Stihl Saws.
Lighting units will be have their cables severed and the units prized free from their fixings. All waste steelwork/pipework will be removed to the designated storage area.
Ceiling lining boards
Prior to commencement
- the area below will be demarcated as a NO-GO area for all operatives not involved with the works.
- A safe work platform will be erected in the form of tower scaffold units, the space available will dictate on the size of the unit. This will be erected by competent operatives in accordance with manufacturers recommendations. Toe boards will be
- Operatives to be issued with safety glasses/gloves;
Plasterboard ceiling panels will be prised from their fixings employing hand tools, any nail heads hammered into the timber frame and timber frame supports removed to provide a neat finish;
At no time will a section of plasterboard or gridwork be left partially removed / hanging as this can cause injury to operatives – make sure that the area is safe during the works and before shift end. Always bar off boards working from one end.
– do not work from the middle as the board can split and swing down causing injury.
Removal of Sanitary Ware
Confirmation of isolation of water supply to be obtained before commencement of these works.
These units will be removed carefully by either unscrewing fixings or where this is unsuitable, carefully breaking into surrounding brickwork to release. The individual units will be removed and placed within a designated storage area.
A temporary cement bung will be installed to drainage points to seal over to prevent cross contamination.
Associated pipework will be cut back (following confirmation of disconnection of supply via the Client) employing disc cutting equipment.
Remove Kitchen Fittings
Where items are at height:-
- the area below will be demarcated as a NO-GO area for all operatives not involved with the works.
- A safe work platform will be erected – tower scaffold or podiums will be employed (dependant on space available). This will be erected by competent operatives in accordance with manufacturers recommendations. Toe boards will be
These items will be removed by hand and removed systematically from the work area to the designated waste storage area via either barrow or trolley transfer.
A manual handling assessment will be carried out before lifting larger items and where the risk cannot be adequately controlled the item will be broken up to aid movement/prevent injury etc.
Suitable PPE will be worn for all works. A temporary cement bung will be installed to drainage points to seal over to prevent cross contamination. Associated pipework will be cut back (following confirmation of disconnection of supply via the Client) employing disc cutting equipment.
Removal Of Doors/Skirting/Frames
Doors: Operatives will work in pairs for these works. The doors will be unscrewed from their fixings and carefully lowered to floor level before being moved to a designated skip.
Skirtings & Door Frames: Skirting will be removed first, followed by frames. All works to be carried out in a controlled manner – fixings will be carefully removed or prised using small tools. Two operatives are to be employed per frame to ensure full control is achieved.
Dismantling of Internal partitioning
All works will commence from the upper section employing hand tools. Prior to commencement suitable and sufficient PPE/RPE will be issued to include ½ face masks to P3 standard, disposable coveralls, goggles, gloves etc. See specific method for removal of MMMF materials.
Employing hand tools the operatives will commence with removing the plasterboard covering from the uppermost section to expose the MMMF materials behind – See specific method for removal of MMMF materials. To control dust release localized sprays of water will be applied as required and a polythene covering will be placed to the floor area to enable easier clearance of the waste and prevent double handling of the plaster which could lead to excessive dust within the atmosphere.
The timber support grid will be removed following removal of the partition covering by use of hand tools and size reduced for easier transportation. All protruding nails will be hammered over.
Removal Of Carpets / Linoleum
Operatives will, using hand tools, carefully prise carpets from their initial gripper strip. To minimize manual handling issues the section of carpet will be cut, employing Stanley knife, into manageable sections. The carpet will then be rolled as it is lifted and a further operative will remove all associated gripper strips to ensure safety of others within the area.
Removal of vinyl floor tiles (non-asbestos)
Where fungal deposits are noted these will be sprayed a minimum of 24 hr previously, with an application of fungicidal liquid.
One gang of operatives will be appointed to carry out these works.
The tiles will be lifted using suitable hand tools in as whole a section as possible.
Lifted tiles will immediately be placed within a wheel barrow and transported to the designated waste area to prevent tripping hazards for the further soft-strip works.
Removal of Ceramic floor tiles
NOTE: Ceramic materials are very sharp and can cause serious injury – ensure that the work area is controlled and only those allocated to the task are within the area;
One gang of operatives will be appointed to carry out these works and be issued with high impact goggles, gloves and instructed to untuck trousers from their boots (to prevent ceramic shards from entering their boots and causing injury).
The tiles will be removed employing a Kango breaker (under vibration permit system) with spade head with only one operator working to the area at a time to prevent ejection of shards causing injury to others. Once works are ceased or completed to the area a clearance operative will load the tiles/shards into a wheel barrow and transport to the designated waste area.
Removal of waste
All resultant arisings will be sorted, where necessary, removed from the work area and positioned either:-
Scrap – within designated waste skips for later removal;
Waste – combustible – within designated area to be loaded into either waste skips/rollon/off containers or flat-bed transport for removal to a suitable disposal point under Waste Management ‘Duty of Care’ procedures.
Environmental Monitoring
This will be carried out throughout the duration of the works.
When activities of a noisy nature or with high vibration potential are being carried out, monitoring will be carried out in line with BS:5228 Part 1 (Code of Practice for Noise and Vibration Control on Construction and Open Sites), to ensure that this stays within the prescribed parameters.
The site supervisor will carry out continuous monitoring with regard to dust and other disturbances.
Should works dictate, damping down procedures will be carried out during the demolition and loading operations to ensure migration of dust within the surrounding area is minimized.
| ASSOCIATED RISK ASSESSMENT No.’s | 03; 05; 06; 10, 13, 14, 17, 22, 27; 32; 40, 53, 70; 105; 110 |
| ASSOCIATED | s.2 of the Health Safety at Work Act 1974 |
| LEGISLATION | Working at Height Regs 05; |
| CDM2015 | |
| Manual Handling Regs | |
| Control of Noise at Work 2005 | |
| PUWER 98 | |
| COSHH 2002 | |
| PPE Regs. 92 |
19.6 REMOVAL OF M.M.M.F. MATERIALS
Material located:
- Within partitioning
- Above suspended ceilings
- Lagging
PREPARATORY WORKS:
All operatives involved with these works are to be instructed on the need to adopt a high hygiene standard i.e. wash at shift end, no smoking etc.
Due to the risk of inhalation of fibers, all operatives involved will be issued with and instructed to wear the following RPE/PPE:-
Disposable coveralls;
½ face P3 (high filtration) masks;
gloves;
goggles;
safety footwear.
REMOVAL PROCEDURE
To suppress fibre release the respective materials will be damped down by the use of an airless spray unit or similar. Once damped the materials will be placed immediately into waste sacks to prevent double handling and sealed with cloth adhesive tape. Further operatives will then remove the sealed bags directly to the waste skip provided so as to maintain good housekeeping standards and prevent damage to the bags etc.
| ASSOCIATED RISK ASSESSMENT No.’s | 76 |
| ASSOCIATED | s.2 of the Health Safety at Work Act 1974 |
| LEGISLATION | PPE Regs 92 |
| Work at Height Regs 2005 | |
| CDM2015 | |
| COSHH 2002 |
19.7 HOT WORKS
NOTE: Post fire watcher internal to the structure wherever hot-cutting is required to prevent risk of ignition.
This method has been produced to control hot cutting activities on the project and should be followed for all works which produce heat/sparks etc.
Prior to commencement:
Site Supervisors Duties:-
- Carry out Burning & Welding Insurance Conditions Toolbox Talk;
- Obtain Hot Work Permit – either our internal form 59 or Principal Contractors own (whichever is applicable);
- Carry out all preparatory safety inspections/works and position fire fighting equipment as detailed on Toolbox Talk and Hot Work Permit and sign;
- Where cutting of pipework/vessels is required ensure former contents are known and where applicable purging of pipework is carried out by a competent contractor and certificates issued;
- Ensure guns, regulators, spark arrestors and pipes are fitted correctly;
- Issue correct PPE/RPE;
- Ensure operatives are competent and are aware of their required duties;
- Erect internal exclusion zones as
Safe Working; Operatives duties:-
- Carry out full inspection of the work equipment and PPE and report any defects immediately to the site supervisor;
- Ensure hoses etc. do not pose a tripping hazard to others within the work area;
- Check that all preparatory safety works as detailed in Item 2 above have been carried out;
- Don PPE/RPE;
- Carry out the works in a safe and methodical manner;
- Report any new findings immediately to the site supervisor;
Completion of Works; Operatives duties:-
- Dismantle and store equipment correctly;
- Carry out inspection of the work area – report any findings to Site Supervisor;
Site Supervisors Duties:-
- Carry out inspection of the work area and sign off Hot Work Permit
19.8 ENVIRONMENTAL ISSUES
Abandoned COSHH items throughout structures
Subcontractor to carry out a ‘sweep’ of all structures as part of site set-up.
Any items which are located are to be collected and placed within a secure area for removal from site via a specialist contractor.
Suitable PPE is to be worn during all collection activities – this will include as a minimum – impervious gloves; safety visor; overalls.
Where maneuvering onto pallets is required operatives will wear impervious gloves and coveralls ensuring that, before movement, each drum is inspected and tops secure.
Once placed onto a pallet the drums will be wrapped and banded to make secure.
The specialist contractor will collect and remove to the licensed disposal point under Section 62 Hazardous waste consignment note. A copy of this note will be provided to the site supervisor, as producer of the waste, prior to leaving site.
Consignment notes for all waste removal off site are to be provided for evidence as part of the SWMP;
Spillage Control
Spill kits are to be placed at sensitive zones i.e. adjacent to bunded fuel tank and drip trays used for any equipment/plant or COSHH items on site.
All spillages are to be controlled following TRD’s spillage procedure and any use of spill kits reported directly to the site supervisor for logging as per ISO internal requirements.
Previous Ground contamination issues
Subcontractor to adopt caution when breaking ground.
Continuous inspection of excavations is to be carried out and any signs of contamination relayed directly to the client for further investigation.
Consultation with the client will also be required to enable advise to be obtained as to how best to rectify the issue.
Works:
To be adopted where areas have determined the presence of hydro-carbon contamination – either within the ground investigation report or to new areas discovered as floor slabs are extracted.
Following excavation of highlighted areas contact with the clients representative is required to allow them to inspect the excavation prior to backfill therefore ensure that the engineer is aware of the works program to enable him to visit site and inspect.
The site supervisor will:
- Ensure the area is pre-marked to ensure that all materials containing contaminants are removed;
- Advise the Client/Engineer of the program of works;
- Designate the working zone and where materials to be removed from site – position the lorry to a safe point immediately adjacent the excavation point to enable the material to be deposited directly into the skip to prevent distribution of the material outside of the controlled zone. Where items are required to be further investigated/tested an impervious sheeting will be positioned to a designated area and the excavated materials deposited on this until instruction received as to the required treatment/removal from the client;
- Designate the area as a `flame-free zone` and no smoking zone
- Carry out specific Tool Box talks to all operatives on site.
- Ensure that the excavation is made safe until such time as the Client/ engineer has inspected and OK’d for backfill with clean inert materials;
Once all preparatory works are in place and the machine & lorry are within their designated locations, works will commence with the careful extraction of contaminated soil from each highlighted area.
Care will be taken not to overfill the bucket attachment due to the risk of transferal of contaminated matter outside of the working zone.
Each bucket load will be lifted and deposited directly within the lined body of the lorry or onto the impervious liner– this will be repeated to designated depths as detailed by the client/report.
Once complete each excavation will be barriered off for safety until the Client/ engineer has inspected and confirmed that it may be backfilled. Clean inert arisings generated from the demolition works will be used as backfill back to surrounding levels.
Bats
The Bat presence/absence survey has found no evidence of roosting bats, hence no further survey or licence will be obtained. Measures will be taken to safeguard bats as identified in the Bat Method Statement.
Leptospirosis (Weil’s disease)
The leaflet from the HSE called “LEPTOSPIROSIS” – are you at risk! will be issued to each operative working on the project as will an employee handout detailing the symptoms etc. of coming into contact with Rat’s urine etc. Any flu-like symptoms must be reported to S Wright on on-set.
Hypodermic needle
Hypodermic needles and glue cans/bags may be contained within the site. A designated gang will be assigned to carry out these works prior to commencement of any further activities within the structure. Following completion of works a final inspection will be carried out by a competent person.
NOTE #1: BE AWARE THAT IT IS A KNOWN FACT THAT NEEDLES CAN BE TAPED TO BANISTERS, FURNITURE (WITHIN DRAWS AND TO BACKS) SO THAT WHEN YOU TOUCH/GO TO MOVE THEM YOU GET STICK INJURIES AND TO TOPS OF DOORS SO THAT THEY FALL WHEN YOU ENTER. IT HAS ALSO BEEN KNOWN THAT THEY ARE PLACED INTO SOFA CUSHIONS/MATTRESSES AS WELL AS BEING WITHIN ABANDONED WASTE / BED LINEN ETC. BE VERY AWARE – DO NOT TOUCH ITEMS WITH YOUR HANDS – USE LONG HANDLED TOOLS UNTIL YOU ARE SATISFIED THAT THERE IS NO DANGER AND ALWAYS WEAR PPE, EVEN WHERE YOU ARE SATISFIED THAT THE ITEM IS SAFE TO HANDLE;
NOTE #2: ENSURE THAT CORRECT PPE IS WORN AT ALL TIMES. DO NOT TUCK YOUR TROUSERS INTO YOUR BOOTS, WEAR THEM OVER TO PREVENT RISK OF ENTRY BY NEEDLES;
Works:
All operatives will be made aware of the above facts during specific on-site induction/toolbox talk and instructed in the need to maintain vigilance and adopt caution when handling abandoned waste.
Each operative will be issued with ‘Anti-sharp’ gloves; ‘Anti-sharp’ leggings; safety boots; safety helmet and instructed to wear same. ‘Litter picking’ hand tools will also be issued to ensure that no contact is necessary with the operatives person.
The operatives will then systematically go through each area of the structure (including external landings/stores/garages etc.) moving abandoned waste/bedding, furniture etc. to inspect same.
All hypodermic needles will be picked up via the ‘litter picking’ equipment – pick up by the blunt end (or the syringe if still attached) and placed directly into a Sharp Bin as provided to each operative. All bags/cans etc. will be picked up, again using the ‘litter picking’ equipment as before.
At the end of shift all contaminated material packaging will be suitably sealed and placed within a secure area as instructed by the Site supervisor. All full sharp bins will be returned to the local drug rehabilitation office / local authority or via Wards (as appropriate – liaise with environmental manager) for disposal by incineration.
All glue-associated items will be disposed of at the appropriate site.
ACTION IN THE EVENT OF AN INJURY:
Hepatitis and the virus HIV can be contracted by a puncture wound from a blood contaminated ‘sharp’.
Needles carrying the greater risk and blood contaminated razors and broken glass to a lesser degree.
If a cut or puncture wound is received encourage free bleeding immediately. This is done by squeezing the area around the wound to force out a flow of blood;
wash the area;
– report immediately to your site supervisor who will ensure that you attend the A&E dept. of the local hospital
– Any injury of this type MUST be recorded in the site accident book;
– the safety officer is to be informed immediately
Prevention of contamination & sealing of drains
- First task will be to identify all drain runs on the site – Foul & Surface Water;
- Carry out site survey to identify location/condition of all man-holes;
- Open up each manhole and check the direction of flow – mark on site drawing;
- For those manholes located adjacent to the site boundary/ feeding retained areas – insert temporary plug at drain outlet;
- Following commencement of demolition works on site each drain run will be severed at the site of the manhole;
- A permanent cement mortar plug will then be forced within each manhole, consisting of a 3 to 1 mortar
- Each sealed manhole will be clearly marked on the site plan for inclusion in the site safety file;
- Operatives gaining access to any manhole shall be trained in the correct entry / rescue procedures for confined spaces and be supervised at all times – a permit to enter system will be in operation;
- Once manholes are suitably sealed then manhole covers will be paint marked for identification
Protection of surface water courses
Surface water courses will be suitably protected against runoff and associated particulate materials or dissolved materials. Protection will be provided in the form of cut off trenches, pumped bunds or interceptors sand bags or similar precautions.
In protection of water course, due attention will be paid to the “Pollution Prevention Guidelines” published by the Environment Agency. PPG5 (Works near or liable to affect water courses) and PPG6 Working at Construction and Demolition Sites are especially relevant.
Odour dust and nuisance (not including noise)
All works will be undertaken in accordance with the contract specification.
No special precautions against inhalation or contact of site personnel with ground materials will be taken on the site other than those normally undertaken in accordance with good site practice.
This should include as a minimum use of overalls, boots and gloves with a change facility for clothes for travel to and from the site. Obvious signs of visual contamination will be assessed if they occur.
It is considered that the ground materials to be encountered will be sufficiently coherent not to pose a significant dust generation hazard. In the event of dust becoming a problem, suitable damping down will be carried out to contain the hazard.
Dust generation from operations related to demolition of buildings or removal of hardstandings may be a greater potential hazard. This will be handled by suitable damping down procedures which in turn will be continually monitored.
Protection of other site users and off site personnel.
The site is currently unoccupied and no special measures are required to protect on-site users.
However, adjacent sites are operational and there are public access routes immediately adjacent all site elevations. Measures will be taken to protect such off site personnel against hazards associated with the works.
These will include, but not necessarily confined to:-
- correct fencing off of the site and all appropriate security measures,
- avoidance of wind borne dust,
- reduction to the lowest level of noise (including that from site traffic and other machines)- this will be monitored in line with BS:5228 Part 1 (Code of Practice for Noise and Vibration Control on Construction and Open Sites) to ensure that this stays within the prescribed parameters.
- use of wheel washes and wash down of vehicles prior to leaving site whenever practical,
- correct sheeting of containers or vehicles containing contaminated materials before leaving site,
- erection of full public protection measures to all elevations which impede on surrounding pavements / car parks
- Installation of suitable and sufficient traffic / pedestrian signage in line with the Road & Street works Act 1991
| ASSOCIATED RISK ASSESSMENT No.’s | 11; 57 |
| ASSOCIATED | s.2 of the Health Safety at Work Act 1974 |
| LEGISLATION | CDM 2015 |
| Control of Noise at Work 05 | |
| PUWER 98 | |
| COSHH 2002 | |
| PPE Regs. 92 |
19.9 ASBESTOS REMOVAL – NON LICENSED. SPECIFIC SITE NOTES:
- REFER TO TYPE 3 SURVEY CARRIED WITHIN YOUR SITE FILE PRIOR TO ENTRY INTO EACH STRUCTURE TO DETERMINE ITEMS/LOCATIONS OF ACM’s
- OPEN ASBESTOS CEMENT SKIPS MUST BE LINED USING 1000 GAUGE POLYTHENE – LINE THE BASE AND SIDES LEAVING A FLAP OVER THE EXTERNAL SIDES SO THAT ONCE FILLED THESE CAN BE FOLDED OVER THE TOP TO SEALWITH CLOTH ADHESIVE TAPE ATTACHED TO EACH SEAL LINE TO FULLY ENCLOSE THE LOAD + SHEET OVER BEFORE TRANSPORTING;
- CHECK THAT THE NON-FIBROUS SKIP IS MARKED WITH AN ASBESTOS SIGN;
- IF USING A WORK PLATFORM i.e. MEWP / TOWER OR PODIUM SCAFFOLD REMEMBER TO SEAL THE WORKING PLATFORM WITH TWO LAYERS OF 1000 GAUGE POLYTENE AND CLOTH ADHESIVE TAPE TO PREVENT RISK OF CROSS- CONTAMINATION;
- IF YOU ARE UNSURE ON ANY ITEM – RING STELLA ON 07967 101 987 BEFORE YOU COMMENCE
- PRIOR TO COMMENCEMENT SUPERVISOR TO CARRY OUT A WALK ROUND INSPECTION WITH LICENSED CONTRACTOR SUPERVISOR TO CONFIRM AREAS FROM THE SURVEY;
- FOLLOWING COMPLETION SITE SUPERVISOR TO CARRY OUT WALK ROUND INSPECTION WITH LICENSED CONTRACTOR SUPERVISOR – RECEIVE EACH CLEARANCE CERTIFICATE FOR EACH AREA AND GET THEIR SUPERVISOR TO SIGN OFF EACH SPECIFIC SECTION OF THE METHOD; SUPERVISOR TO DO THE SAME FOR YOUR NON-LICENSED WORKS;
- KEEP ALL CLEARANCES ON SITE FOR FUTURE REFERENCE;
The following are all items identified as containing asbestos from the survey
NOTE: First task will be to designate the work team and carry out a Tool Box talk detailing the work task involved and the risk of working with asbestos containing materials. HSE guidance leaflet ‘Asbestos & You’ will be issued.
All work equipment will be inspected by the user and any defects reported directly to the site supervisor. The site form relating to work equipment will be completed.
An exclusion zone will be erected around the area – hazard tape and warning notices will be positioned to all access/egress points to prevent access by unauthorized personnel.
Fire fighting equipment will be positioned as per the site fire plan.
Works:
First task will be for the removal of ACM’s as identified within the refurbishment survey report.
The supervisor will carry out a final inspection of the area with the appointed gang and highlight hazards and controls via toolbox talk training – a record of this will be kept.
The asbestos areas will be classed as a mandatory respiratory protection zone for the duration of the work tasks and addressed by the issue of appropriate PPE.
WASTE REMOVAL:
All asbestos waste sacks will be wiped down, swan-neck tied, and double bagged.
All bagged/sealed waste will be transportation to the lockable asbestos skip.
Once the skip is full it will be disposed of at a licensed waste disposal point under a Section 62 consignment note.
PROCEDURES FOR DEALING WITH EMERGENCIES
The on site fire plan will be in operation for the works.
Should a bag of waste split the following procedure will be adopted:-
The spillage will be immediately sprayed with water a further bag will be obtained and all materials placed directly into the bag employing a shovel.
The split bag will also be placed into this replacement bag and the bag swan neck tied to contain.
CLEAN DOWN OF WORK AREA:
All surfaces will be cleaned down with a damp cloth / tac-rag and type ‘H’ vacuum to ensure fibre residues are not present.
All PPE/RPE/ cleaning materials will be bagged and classed as contaminated waste also.
INDIVIDUAL DECONTAMINATION:
As per HSE guidance – Asbestos Essentials – Personal Decontamination as found within your site file.
NOTE:
Asbestos Fibers can cause lung cancer & lung diseases;
You must be trained to work safely with asbestos materials;
You must be trained to use PPE & RPE properly;
Remove your face mask last;
You need to decontaminate yourself properly, otherwise you could take asbestos fibers home on your clothing and expose your family and friends;
Procedure:
- Clean your boots with a damp rag – soak the rag (cotton but those that do not shed fluff or impregnated rags (eg ‘Tak’ rags)) in water; fold in half or quarters; wring it out; wipe your boots; refold the rag to give a clean surface; repeat until you have used all of the clean surfaces of the rag; put the used rag in the asbestos waste sack; if required use another rag as before; REMEMBER – do not re-soak the same rag as this will create contaminated
- Where available, clean your overalls with a brush attachment on a Type ‘H’ vacuum and once complete vacuum off the brush head;
- Otherwise, use damp rags by a ‘patting’ action. Remember rubbing can disturb fibers;
- Always work in pairs – one person decontaminating the other;
- Peel off disposable coveralls making sure they go inside out and place them immediately in an asbestos waste sack;
- Finally remove your face mask and place immediately in an asbestos waste sack;
Personal decontamination:-
- Can you use the site washing facilities? If so they must be for your use only;
- Keep other people out during personal decontamination and until you have cleaned down the facilities;
- Wash every time you leave the work area
- Use damp rags to clean down the washing facilities at the end of the task;
- Clean the facilities daily if the work lasts more than one day;
- Inspect the facilities visually once the work has finished;
- Clearance sampling is not normally required for washing facilities;
Any other information relevant to safe working.
- All works will be carried out in a methodical manner working in from a designated
- All works will be carried out in line with
- HSE ‘Working with Asbestos Cement’ booklet HSG189/2;
- Asbestos Essentials A14 – Removing asbestos cement sheets;
- Asbestos Essentials EM5 – wetting asbestos materials
- Asbestos Essentials EM8 – Personal Decontamination
19.9.1 REMOVAL OF THERMOPLASTIC FLOOR TILES AND/OR BITUMEN BENEATH
No. of operatives: Max. 4
Expected duration: 4 days per man
Expected exposure: Below control limit
RPE: ½ face respirator –EN149FFP3
PPE: Disposable coveralls – elasticated ankles/hood/wrist; goggles;
safety wellington boots;
EQUIPMENT/MATERIALS
Floor Tile Scrapers Hand Tools
Hand Held spray unit
Wetting Agent
Asbestos Waste Sacks
Assessment: The work consists of the removal of an asbestos based product known to contain chrysotile asbestos. The floor tiles are thermoplastic therefore it is anticipated that the control limit will not be exceeded. For this reason FFP3 half-face respirators will be used along with disposable coveralls.
In some areas the tiles are non-asbestos but the bitumen adhesive contains Chrysotile asbestos.
Work Method:
Access will be restricted to operatives involved in the work by means of warning tape and notices.
Having donned their correct PPE/RPE the operatives will commence with the stripping operations.
Utilizing the tile scrapers the operatives will carry out lifting of the tiles whilst a further operative carries out localized spray of wetting agent to the disturbed area to contain any fibre release.
The lifted tiles will, where identified as containing asbestos, then be bagged and swan- neck tied with cloth adhesive tape before being removed to the designated special waste skip.
Hand tools will be utilized to scrape up the fixing glue residue or specialist environmental solvent type liquid applied to dissolve the adhesive.
This residue will be placed into asbestos waste sacks for disposal.
Each sack will be swan neck tied to seal and double bagged and sealed once more with cloth adhesive tape before transportation off site under Section 62 hazardous waste consignment note.
19.9.2 REMOVAL OF SINK PADS
No. of operatives: Max. 2
Expected duration: ½ hr per man
Expected exposure: Below control limit
RPE: ½ face respirator – EN149FFP3
PPE: Disposable coveralls – elasticated ankles/hoods/wrists; Safety Boots; Hard hat;
First task will be release the sink from it’s surroundings.
Once released the unit will be turned over for easier access and the base pad sprayed with a PVA solution.
Employing a hand-held scraper the pad will be removed, including any residue to a clean finish and all materials placed immediately into an asbestos waste sack.
The area will be cleaned down finally with a damp cloth which will also be placed within the asbestos waste sack.
Once all works are completed the sack will be swan neck tied with cloth adhesive tape to seal.
19.9.3 REMOVAL OF CEMENT DEBRIS
No. of operatives: Max. 2
Expected duration: 2 hour per man
Expected exposure: Below control limit
RPE: ½ face respirator –EN149FFP3
PPE: Disposable coveralls – elasticated ankles/hoods/wrists; Wellington Boots; Hard hat;
To suppress fibre release one operative, employing a spray unit will damp down the a/c material at source and once wetted further operative/s will hand-pick the a/c debris and immediately place within an asbestos waste sack.
Care will be taken not to over-wet the sheeting as this will create contaminated waste water.
Care will be taken not to overfill the asbestos waste sack to prevent splitting/spillage etc. Once suitably filled the sack will be swan-neck tied with cloth adhesive tape and removed from site under Section 62 consignment notice.
19.9.4 REMOVAL OF FUSE PADS
No. of operatives: Max. 2
Expected duration: 2 hour per man
Expected exposure: Below control limit
RPE: ½ face respirator –EN149FFP3
PPE: Disposable coveralls – elasticated ankles/hoods/wrists; Wellington Boots; Hard hat;
Access: MEWP – Scissor Lift – work platform/open ends sealed with 1000gauge polythene and cloth adhesive tape
Or
Podium/Tower Scaffold (as appropriate) – work platform/open ends sealed with 1000gauge polythene and cloth adhesive tape
HAS THE ITEM BEEN TESTED TO PROVE THAT IT IS DEAD!!! IF UNSURE ASK YOUR SUPERVISOR.
Operatives to post warning signs at all approach points to alert others of the works and don their correct PPE/RPE.
A bucket of water and hand held spray will be positioned immediately adjacent the work area to wash down following the works.
The cable to the fuse box will be severed using a cable cutter.
The complete unit will then be removed from it’s fixing by either unbolting or fixing and placed immediately into an asbestos waste sack.
All asbestos waste sacks will be wiped down, swan-neck tied, and double bagged.
Where the item is noted as loose only the flash-pad will be removed following damping down of the item to contain fibre release.
Again this will be bagged as before.
Following removal all surfaces will be cleaned down with a damp cloth / tac-rag. All PPE/RPE/ cleaning materials will be bagged and classed as contaminated waste also.
19.9.5 REMOVAL OF CEMENT CILLS
No. of operatives: Max. 2
Expected duration: 2 day per man
Expected exposure: Below control limit
RPE: ½ face respirator – EN149FFP3
PPE: Disposable coveralls – elasticated ankles/hoods/wrists; Safety Wellington Boots; Hard hat; Full body harness.
Access: Podium/Tower Scaffold (as appropriate) – work platform/open ends sealed with 1000gauge polythene and cloth adhesive tape
MEWP – Scissor Lift – work platform/open ends sealed with 1000gauge polythene and cloth adhesive tape
All operatives engaged in these works will be issued with appropriate PPE/RPE – as described above.
A working at height assessment will be carried out and appropriate safe work platform provided.
Inspection of the ground on which the work platform is to be positioned is to be carried out and any soft-ground either suitably compacted and dressed with hardcore/stone or covered with suitable road plates (or similar) to provide a safe area.
Following removal of the windows (damping down procedures to be carried out during this procedure) the cill will be sprayed with a low pressure application of wetting agent to contain fibre release and carefully prised from it’s fixings using hand tools only.
Each cill will be placed immediately within an asbestos waste sack which, once at ground level, will be cleaned down, sealed and removed to the contaminated waste skip.
19.9.6 REMOVAL OF CEMENT UDERCLOAKING
No. of operatives: Max. 2
Expected duration: 1 day per man
Expected exposure: Below control limit
RPE: ½ face respirator – EN149FFP3
PPE: Disposable coveralls – elasticated ankles/hoods/wrists; Safety Wellington Boots; Hard hat; Full body harness.
Access: Podium/Tower Scaffold (as appropriate) – work platform/open ends sealed with 1000gauge polythene and cloth adhesive tape
MEWP – Scissor Lift – work platform/open ends sealed with 1000gauge polythene and cloth adhesive tape
All operatives engaged in these works will be issued with appropriate PPE/RPE – as described above. A working at height assessment will be carried out and appropriate safe work platform provided. Inspection of the ground on which the work platform is to be positioned is to be carried out and any soft-ground either suitably compacted and dressed with hardcore/stone or covered with suitable road plates (or similar) to provide a safe area.
Gable infill: Following removal of the roof tiles the exposed ‘gobbo’ will be removed and the undercloak will be sprayed with a low pressure application of wetting agent to contain fibre release and carefully prised from it’s fixings using hand tools only.
Each strip will be placed immediately within an asbestos waste sack which, once at ground level, will be cleaned down, sealed and removed to the contaminated waste skip.
| ASSOCIATED RISK
ASSESSMENT No.’s |
104; 105; 204 |
| ASSOCIATED LEGISLATION | s.2 of the Health Safety at Work Act 1974 Working at Height Regs 2005
The Control of Asbestos Regs 2012 PUWER 98 PPE Regs 92 CDM 2015 HSG189/2 – Work with Asbestos Cement L143 – Work with materials containing asbestos |
19.10 DEMOLITION PROCEDURE
Background info:
NOTE #1: THERE ARE NUMEROUS RESIDENTIAL DWELLINGS IN CLOSE PROXIMITY TO THE SITE, WHICH WILL BE OCCUPIED, LOCATED ADJACENT TO THE SITE BOUNDARIES – A DIRECT LINE OF COMMUNICATION WILL BE MADE AVAILABLE DIRECT WITH THE OCCUPANTS AND SUITABLE TIMES AGREED IN WHICH TO CARRY OUT DEMOLITION OF THE SENSITIVE AREA – THE SUPERVISOR WILL SPEAK WITH EACH OCCUPANT AND PROVIDE HIS CONTACT TELEPHONE NUMBER ETC. AND AGREE WHAT PREPARATORY WORKS ARE REQUIRED WITH REGARDS TO ADDITIONAL SAFETY MEASURES ETC.
NOTE #2: WHERE CONTROLLED DEMOLITION WORKS ARE REQUIRED WHERE THERE IS RISK OF INTERACTION WITH OTHERS THE SITE SUPERVISOR WILL APPOINT BANKSMEN AT DESIGNATED POINTS. WORKING FROM WITHIN THE FOOTPRINT OF THE BUILDING THE ELEVATIONS WILL BE DEMOLISHED IN A CONTROLLED MANNER WITH ALL BRICKWORK BROUGHT INTO THE FOOTPRINT AT ALL TIMES AWAY FROM THE HIGH RISK AREA. SUCH AREAS WILL BE CARRIED OUT AT ‘QUIET TIMES’ FOLLOWING CONSULTATION WITH THE APPROPRIATE AFFECTED PARTIES.
PREPARATORY WORKS:-
Careful inspection of each structure will be carried out by the site supervisor and the appointed machine operator. All sensitive areas will be highlighted to the operatives and Toolbox talk given to ensure the correct safety measures to be incorporated are known by all persons.
The site supervisor will make contact with all neighboring representatives who will be affected by the works to ensure they are aware.
During all works the surrounding area will be classed as an exclusion zone. Works will be programmed so as not to coincide with peak-times.
Once the designated section of structure is ready for demolition and the site supervisor gives the instruction, all operatives not involved with the works will position themselves at the designated safety zone unless appointed as banksman whereby they will position themselves within their designated view point.
On completion of all preparatory works i.e. hypodermic needle clearance / soft-strip and asbestos removal operations demolition works will be carried out.
Demolition Works:
Mechanical:
The mechanical reduction works will be from top down with the demolition machine with PD19 attachment reaching in to its furthest point at the top level and staggering the cut lower down to produce a natural run off of materials, so far as is reasonably practical. In this way overloading of each floor level shall be reduced to its lowest expectation.
The reduction of the structure shall be progressive working a bay at a time. As each section is demolished, the debris shall be pulled off to prevent any possibility of a build up of materials.
This reduction process shall be continuous in a progressive and systematic manner. During all reduction operations, the machine operator, together with his supervisor, shall continuously asses the integrity of each section of the structure being reduced at that time. Where any ambiguity exists as to the continued integrity of any adjacent section the works are to suspended and an action plan formulated to deal with any potential problem.
During all structural reduction operations, the operator of the demolition rig will leave sufficient bracing to maintain stability allowing him to carefully reduce the building elements in a piecemeal manner.
Throughout the duration of the works, all operatives shall be aware of and shall carry out any instructions regarding the safety and integrity of the surrounding environment. Works considered to have a significant impact on the environment shall not be implemented until such time as suitable and sufficient control measures have been put into place to reduce such impacts.
Noise and dust levels are to be kept to the lowest expectancy. Operations shall be carried out using power fork or grapple wherever possible.
All resultant arisings will be sorted and removed from the work area and all deleterious materials loaded into either rollon/off containers or tipper transport for removal to a licensed disposal point under Waste Management ‘Duty of Care’ procedures.
Completion Works:
Once at slab level and arisings removed an inspection will be carried out.
The excavator will initially break along predetermined lines employing concrete breaker then, to reduce noise issues utilize the bucket attachment to lift the slab in sections – an assessment will then take place to ascertain whether these slab sections can be loaded direct or further size reduction is required.
At no time will works be carried out which may affect the adjacent pavings etc.
All materials will be sorted and arisings removed from site.
Once removed the exposed footings will be grubbed up and once all arisings cleared the ground will be made good – compacted and graded to existing paving levels with suitable topsoil.
Environmental Monitoring
This will be carried out throughout the duration of the works. When activities of a noisy nature or with high vibration potential are being carried out, monitoring will be carried out in line with BS:5228 Part 1 (Code of Practice for Noise and Vibration Control on Construction and Open Sites), to ensure that this stays within the prescribed parameters.
The site supervisor will carry out continuous monitoring with regard to dust and other disturbances.
Should works dictate, damping down procedures will be carried out during the demolition and loading operations to ensure migration of dust within the surrounding area is minimized.
| ASSOCIATED RISK ASSESSMENT No.’s | 07; 11; 13; 14; 22; 33; 53; 70; 75; 80; 84; 85; 102; 105; 107; 110; |
| ASSOCIATED | Health & Safety at Work Act 1974 |
| LEGISLATION | WAH Regs 05 |
| PUWER 98 | |
| PPE Regs 92 | |
| The Construction (Design & Management) Regs 07 | |
| The Control of Noise at Work Regulations 05 | |
| BS6187:2011 |
