2025
Aug
15

Chilled Water Pumps Testing & Commissioning

Below is a precise testing and commissioning method statement for chilled water pumps on a project site. The purpose of this method of statement or standard operating procedure is to define the step by step method to implement the correct practices for

2025
Aug
14

Method Statement for Drainage Pipe Installation – PVC uPVC Drainage Piping Under / Above Ground

This method statement is applicable for all drainage pipe works underground, above ground, horizontal and vertical drainage piping for any kind of the project as specified in project specification. It is responsibility of project manager and project plumbing engineer to ensure the

2025
Aug
14

Nitrogen Flushing of Air Conditioning and Refrigeration Systems

Below is the standard procedure for the proper flushing of air-conditioning and refrigeration system with the use of dry nitrogen, and refrigeration equipment which require flushing of the system after exposing it to the atmosphere or during replacement of the refrigerant compressor. Responsibilities: 

2025
Aug
12

Concrete Formwork Method Statement

Concrete Formwork Method Statement

The purpose of this document is to lay down the systematic procedures for the various activities required for concrete formwork to ensure that all works are carried out in accordance with the approved shop drawings and contract specifications. This civil method statement

2025
Aug
11

Chilled Water Pressurization Unit Testing & Commissioning Method Statement

Chilled Water Pressurization Unit Testing & Commissioning Method Statement

Purpose of this procedure is to define the step by step method to implement the correct practices for the pre-commissioning & commissioning of chilled water pressurization unit through the guidelines contained herein so as to ensure that the job execution complies with

2025
Aug
10

Method Statement For Cable Pulling and Final Electrical Connections To MV & LV Equipment

cable connections and termination method statement

1. Purpose This Method statement covers the installation and final electrical connections to the MV and LV equipment at any electrical project site. All the electrical installation work will be in accordance with the project electrical specifications. 2. Scope of Work This procedure

2025
Aug
10

Permit to Work PTW System General Requirements and Improvement Plan

This document is prepared to provide a clear explanation about PTW issuance and to exemplify the PTW required activities at a construction or any other kind of project, the process involves detailed risk assessments on site activities conducted by main contractor in

error: Content is protected !!