Below electrical method statement explains and covers the transformer installation procedure for any kind and size of the project.
By following this method of statement the electrical installation team shall ensure that installation of transformer is done as per the applicable specifications, codes and standards also ensuring the compliance with the manufacturer installation manuals/instructions.
Necessary Tools & Equipment
- Indoor Dry Type Transformer & Accessories (complying with specifications)
- Fork Lift or Crane, pallet mover with capacity and arrangement in line with the Manufacturer’s recommendations and as required at site.
- Portable Hand Tools / Tool Box.
- Portable Drilling Machine
- Grinding Machine
- Angle Cutter
- Spirit Level
- Level Threads
- Digital Multimeter
- Earth Resistance Tester
- Personal protective equipment’s such as safety shoes, safety helmet, safety glasses, fluorescent vest, safety gloves and dust masks.
Material Handling & Storage
On arrival at project site, transformer shall be inspected and checked against the relevant general arrangement drawing, approved material submittals etc.
Transformer will be off loaded to the place nearest to the future installation and protected properly from dust and adverse environmental impacts.
The transformer shall be stored in sheltered, clean and dry ambient temperature.
Transformer shall be checked for any signs of damage occurred probably during the transport. If any damage is found shall be notified to suppliers or relevant parties.
The characteristics of the Transformer detailed on the rating plate shall be checked to those of the shipping documents and with those of the test report, which is attached to the transformer.
Each transformer shall be checked for the accessories, rating, name plate details, protection devices, indicators & terminal boxes.
Compliance of comments raised during factory inspection shall be checked if any.
The Presence of all identifying and warning levels shall be checked.
All material required at site shall be inspected, handled and store properly.
Any discrepancies, damage etc., shall be notified and reported for corrective action.
Material found not suitable as per approved material submittal shall be removed from site.
Proper storage shall be provided as per manufacturer recommendation.
An inspection request shall be raised for consultant approval upon receipt of the material at site.
Transformer Pre-Installation Requirements
Arrange all the necessary tools and equipment for the installation of transformer.
Supervisor and foreman will orient and familiarize all the technicians and labors involved in the installations regarding relevant approved shop drawings, technical submittals, installation procedures and details, acceptance criteria and health and safety requirements.
Ensure all civil works are completed, unit base must be properly cured and its foundations must be strong enough to withstand the unit weight, including floor paint and clearance is obtained from respective authorities to proceed further.
Method for Transformer Installation
The area or transformer room to be verified to ensure that the civil work has been completed and transformers placement/installation work can commence.
Also check that the area is clean for the positioning of lifting crane and transformers.
Extra precaution to be taken before lifting the transformer, manufacturers’ recommended special lifting eyes shall be used to lift the transformer.
Transformer shall be lifted with maximum sling angle of 60 degree as per manufacturer’s recommendation.
If the transformer is complete with protection enclosure, roof shall be taken off to attach the slings.
Points of attachment shall be checked for cracked welds or loose nuts and bolts before lifting.
Guide ropes shall be used to prevent twisting or swinging of the transformer once it has been lifted clear of the ground.
Don’t perform lifting of transformer in high winds.
Transformer shall be placed down on the level surface capable of supporting its weight.
Place the transformer on removable GI U channel at the place of its final installation.
For locating the transformer in the final location, suitable lever on the special points foreseen on the lower frames shall be used to act only and not on the magnetic core and/ or on the winding.
Make sure that during the movement of transformer no one is pushing the coils and the connections.
Secure the transformer to the foundation after assuring the correct positioning, by fixing bolts and blocking the transformer wheels.
Cable support, cabling and terminations shall be completed as per approved drawings and manufacturer’s recommendation.
Installation of current transformer shall be offered for inspection and approval from the consultant/client.
After the transformer installation and approval, substation is securely locked up and the room placed under the permit system and only workers/employees having suitable permits may enter the room.
Once installation is completed contractor can plan the next activity of transformer testing and commissioning.
Transformer Installation Checklist
Check transformers are of correct size, type and capacity in accordance with schedules & specifications.
Make sure that the installation is as per approved shop drawings, manufacturer’s instruction and specification requirement.
Check mounting, alignment and orientation are correct and sufficient space is available for maintenance purposes.
Make sure that the transformer rail and pulley hook been installed properly.
Inspect for physical, electrical and mechanical condition of the transformer. No damage evident.
Verify that all manufacturer control wiring between shipping splits is properly connected as per manufacturer’s drawings and specifications.
Equipment identification labels permanently affixed.
Verify transformer connections are correct as per the single line diagram.
Inspect insulators, barriers and shields for damage or contamination.
Inspect transformer cables and connections for defects or physical damage
Equipment identification labels permanently affixed.
Discover more from Method Statement HQ
Subscribe to get the latest posts sent to your email.
One thought on “Transformer Installation Method of Statement for any type of Project”
Comments are closed.