2018
Feb
16

Design of Reaction System for 1500 mm diameter Test Pile

The following are the main elements in the design of reaction system for 1500 mm diameter test pile.     Design of Reaction Anchor.     Design of Dywidag Bars.     Design of cross beam.   Anchor Design The test load

2018
Feb
9

Method Statement for Temporary Retaining Wall Installation

Temporary-Retaining-Wall-Installation-Method-Statement

The existing ground level varies between + 3.52 m DMD to + 4.29 m DMD. The working platform level for Double U wall is considered at the average ground level. A Double U channel beam wall with one layer of tie-back anchors

2018
Jan
29

Method Statement For Vibro Compaction Works

Vibro-Compaction-Works-method-statement

Vibro compaction technique is applicable and effective for the improvement of loose natural fine sands as well as the compaction of Fills.  Relative density is improved, potential for liquefaction from a seismic event is reduced, improvement depth up to 20.0 m or

2018
Jan
15

Method Statement for Pile Reinforcement and Concrete Casting

Piling Cage Installation

Subsequent to the completion of the pile drilling, the borehole depth will be checked and verified versus the depth given on daily piling sequence and pile data.  Only after borehole depth check can the cage be lowered into the borehole.  A reference

2018
Jan
7

Method Statement for Piling Works Constructions – Drilling

Below is a brief method statement of piling work that can be used for any kind of project piling works. A crawler mounted piling rig will be used to install bored cast in situ piles of dia 1200 mm. The procedure for

error: Content is protected !!