Civil Engineering Methods

Civil engineering is the core business of any construction company that works as a civil contractor. Our website provides best resources for civil engineering profession.
Civil construction engineers can download construction methodology , method statements covering ITP, check lists and risk assessments.
All our civil engineering documents are editable hence fulfilling the construction industry requirements, and helping engineers to grow in their engineering career.

Temporary-Retaining-Wall-Installation-Method-Statement

Method Statement for Temporary Retaining Wall Installation

The existing ground level varies between + 3.52 m DMD to + 4.29 m DMD. The working platform level for Double U wall is considered at the average ground level. A Double U channel beam wall with one layer of tie-back anchors shoring system is proposed along the four sides of the plot for a […]

Method Statement for Temporary Retaining Wall Installation Read More »

Civil Engineering Methods, Construction Method Statements, Method Statement for Civil Works
Collapse-of-bore-hole

Piling Problems and Risks During Execution Works

The following possible risks or problems are identified with the activities involved with pile execution. Survey – Out of Positioning of the Pile The pile position shall be cross-checked by the Engineer, Contractor and Sub Contractor before the installation of pile. If any out of position of the pile (more than the allowable tolerance) has

Piling Problems and Risks During Execution Works Read More »

Civil Engineering Methods
Piling Cage Installation

Method Statement for Pile Reinforcement and Concrete Casting

Subsequent to the completion of the pile drilling, the borehole depth will be checked and verified versus the depth given on daily piling sequence and pile data.  Only after borehole depth check can the cage be lowered into the borehole.  A reference site datum level will be given to ensure the correct positioning of the

Method Statement for Pile Reinforcement and Concrete Casting Read More »

Civil Engineering Methods, Method Statement for Civil Works

Method Statement for Piling Works Constructions – Drilling

Below is a brief method statement of piling work that can be used for any kind of project piling works. A crawler mounted piling rig will be used to install bored cast in situ piles of dia 1200 mm. The procedure for the construction of bored piles, with temporary casing under bentonite / water  support

Method Statement for Piling Works Constructions – Drilling Read More »