Sequence of Installation for the Chiller Plant Manager CPM Field Devices

Sequence of Installation for the Chiller Plant Manager Field Devices

Safety

  • All site safety rules & regulations shall be complied with.
  • Supervisors will deliver tool box talks, relevant to these activities to all operatives involved in the installation and shall be recorded.
  • All operatives will be equipped with minimum personnel protective equipment; hard hat, coveralls, safety boots, safety glasses.
  • Ensure only qualified personnel shall install the Chiller Plant Manager Field devices.
  • During Installation display warning sign boards to be provided and barricade the area whenever necessary.
  • Only competent, experienced & trained personnel shall perform all the required activities stated in this method statement.
  • Ensure that all operatives fully understand the method of these activities.

Pre- Installation Procedure

  • Before commencement of installation activity, the supervisor must ensure that:
  • Delivered Chiller Plant manager field devices have been inspected & approved via MIR by the consultant prior to installation at site.
  • All Installations & Pressure Testing of Pipe works/ Ductworks (if applicable) have been completed & approved by the consultant.
  • Determine whether the field devices are to be installed at the right location as shown in the approved drawing
  • Permission to start or Civil Clearances prior to installation has been given by the main contractor.
  • All applicable relevant Shop drawings for the installation of the Chiller Plant Manager Field devices shall be available & approved by the consultant. No installation shall be done without Approved Shop Drawings.
  • Installation activities shall only commence when all associated works by the Civil has been completed.
  • Safe access shall be provided by the Main Contractor thru Work Permit in coordination with the Safety in charge at site.
  • Check for other services, making sure that there is no interference between each service & adequate access to work and for future maintenance can be maintained.

 Installation Procedure for Water Differential Pressure Sensor (WPD)

  • PVC tubing with ferrule nut connections or steel pipe with male threads will be used as a connection of WPD.
  • Ensure proper location of the units as per the approved shop drawings.
  • The transmitter mounts on a vertical surface with the pressure ports and cable entrance on the bottom using the two screw holes on the base of the unit.
  • Ensure there is enough space around the unit to make the pressure and electrical connections.
  • Avoid locations with severe vibrations or excessive moisture.
  • The enclosure has a standard ½” conduit opening and may be installed with either a conduit coupler or a cable gland type fitting.
  • The two pressure ports are labelled High and Low.
  • The output signal indicates a positive value when the pressure is higher on the High port than the Low port so ensure these ports are connected correctly.
  • Use appropriately rated pressure tubing and arranges it to minimize stress on the connections.
  • Do not allow material to fall into the pressure ports as contamination could damage the sensors.
  • Use 22 AWG shielded wiring for all connections and do not locate the device wires in the same conduit with wiring used to supply inductive loads such as motors.
  • Disconnect the power supply before making any connections to prevent electrical shock or equipment damage.
  • Make all connections in accordance with national and local electrical codes.
  • This device is a 3-wire sourcing type transmitter. Connect the positive DC voltage or the hot side of the AC voltage to the terminal marked PWR.
  • The power supply common is connected to the terminal marked COM.
  • The device is reverse voltage protected and will not operate if connected backwards.
  • The analogue output signal is available on the OUT terminal. This signal is jumper select-able for either voltage or 4-20 mA output.

CPM Field Devices

Installation Procedure of Differential Pressure Switch Across Pumps (AX-LDPS)

  • Ensure proper location of the units as per the approved shop drawings.
  • The AX-LDPS is for use in systems under pressure and should be installed in accordance with practices relevant to the intended use only by persons qualified to do so.
  • The AX-LDPS is suitable for use with mains voltage and power must be isolated before opening the cover.
  • The AX-LDPS should be mounted on a wall or other suitable surface using the bracket provided.
  • Pipework should then be installed to the unit and terminated at the high and low ports using the 1/4”BSP fittings.
  • Ensure that the pipework is suitable for the system pressure
  • Cable connection- 1.5sqmm cable should be connected to PIN1 (Normally Open)and PIN3 (Common).

Download Complete Method Statement With ITP, Checklist and Risk Assessment


Discover more from Method Statement HQ

Subscribe to get the latest posts sent to your email.

error: Content is protected !!