2014
Jan
20

Method Statement For Final Sub Circuit Wiring

Installation of sub circuit wiring Check the installation & approval of distribution board / back box either recessed or surface and termination of all conduits & trunking completed. Confirm DB reference with load schedule detail. Check all conduits as per circuits are

2013
Nov
4

Testing & Commissioning Of Fire Pumps

Fire Pump Testing and Commissioning Procedure SWMS

Fire Pump Testing and Commissioning Procedure The purpose of this procedure is to define the step by step method to implement the correct practices for the pre-commissioning & commissioning of “Fire Pumps” through the guidelines contained herein so as to ensure that

2013
Sep
7

Sample Checklist for Pre Commissioning Of Chilled Water Pump

The pump operation is controlled as per the chilled water or cooling requirements and sequence of operation is automated via field control devices i.e. valves, thermometers and pressure switches etc. Pump sets are supplied mounted on a substantial fabricated base plate; the

2013
Sep
2

Method Statement For Fire Alarm System Installation & Testing

Below is the method statement for the installation of fire alarm system which can be modified for different type of systems like HSSD or Vesda etc. The steps are very general and should be customized depending upon the project specific requirements, specifications

2013
Aug
20

Testing & Commissioning Of Fire Suppression System

The scope of method statements covers the planning, preparation, and conduct of fire suppression systems cable laying, Installation testing and commissioning. Preparation & Pre Testing & Commissioning Work Before start of testing & commissioning the completeness of the system shall be ensured

2013
Jul
31

Chilled Water Balancing For HVAC System Method Statement

The aim of chilled water balancing is to apply a disciplined procedure of adjustment to water flow rates throughout the chw system to meet the particular requirements of the design. The balancing of chilled water flow rates should be carried out to specified

2013
Jul
31

Air Balancing Procedure for HVAC System FCU AHU Exhaust Fans & Pressurization Unit

Air Balancing Procedure for HVAC System FCU AHU Exhaust Fans & Pressurization Unit

Below is a precise air balancing procedure that covers the HVAC system equipment and ducting system.  Air Balancing For Fan Coil Units Check that all automatic controls are fully commissioned and operating properly All pre-commissioning checks have been carried out Select the

error: Content is protected !!