Civil engineering is the core business of any construction company that works as a civil contractor. Our website provides best resources for civil engineering profession.
Civil construction engineers can download construction methodology , method statements covering ITP, check lists and risk assessments.
All our civil engineering documents are editable hence fulfilling the construction industry requirements, and helping engineers to grow in their engineering career.

Pile Cutting & Trimming Method Statement

The purpose of this Method Statement is to define the procedure for the cutting of piles to the approved cut off level. General sequence of work may include: Auger fitted with appropriate head Auger drilled into ground to required depth. Steel reinforcement cage lowered in the bore hole, with the upper lap length enclosed in… Read More »

General Sequence of Works in Preparation of Building Foundation Up To The Level Of Blinding Concrete

The purpose of this article is to define the procedure for sequence of works in preparation for the foundation up to the level of blinding concrete, considering all safety and quality requirements. Preparation of foundation works at site involves water proofing, screed and casting of foundations including column and lift pit footings. Prior to commencement… Read More »

Possible Causes of Road Crack and Defect – Road Maintenance Inspection Guide

Below you can find some major causes of road crack and road defects. The page also provides what are the effects if these road defects are not properly addressed. Alligator Cracking Alligator cracking is a series of interconnecting cracks creating interconnected patterns on the road. The cracks start at the bottom of asphalt surface and… Read More »

Method Statement for an EPC Construction Project

This method statement for construction project consists of the following sections. 1. General Execution Strategy 2. Details of Design and Engineering Plan 3. Material Management Planning and List of Long Delivery Material 4. Construction and Installation Activity 5. Safety and Environmental Plan 6. Quality Assurance Planning Section 1. General Execution Strategy Contractor will be responsible… Read More »

Pipe Jacking Method Statement Using Automatic Tunneling Machine

The objective of this method statement is to define the installation sequence of casing pipe by means of Pipe Jacking using Herrenknecht Automatic Tunneling Machine with Slurry Material Removal (AVN machines). Table of Content Soil investigation. Identification and location of existing utilities. Responsibilities Labor, equipment’s and material required to complete the work. Handling and disposal… Read More »

Method of Soil Backfill of Trenches

This method statement describes a proper work procedure shall be carried out during the backfill Work of soil. Earthwork forms a part of the installation procedures of box culverts, retaining walls, foundations, and substructures. In order to ensure an adequate foundation for such structures, backfill material must meet certain specifications and be compacted by acceptable methods… Read More »

Method Statement & Risk Assessment for Demolishing and Removal of Fence and Shelters

The purpose of this method statement is to illustrate how the existing fence and shelters will be removed from site in proper and safe way. The scope of this method of statement is to cover the demolishing methodology of the following: Chain link fence (internal & external) Shelters Toilet Tents Water station Lighting pole Road… Read More »

Formwork Scaffolding Definitions and Terminologies

Below is list of very informative terms and definitions which are related to the formwork scaffolding. Every health and safety person must get familiar about these terminologies. ALIGNER Lumber or metal members used to align vertical formwork. (plumbing strut or alignment device) ANCHOR BRACKET A projecting member designed in combination with a specified anchor to… Read More »