Method Statement for Earthwork Related to Track Work

Before start of work, following equipment and machinery shall be arranged for earthwork and monitoring. Excavators Dump Trucks Bull Dozers Compactor Rollers Settlement Gauges/Settlement Markers Survey Equipment To begin with, licensed surveyor is required to establish the boundary and the temporary bench mark and existing ground level (EGL) all these have to be confirmed by… Read More »

Construction Project Site Mobilization Method Statement

Project starts from project mobilization. Once you win the project and client asks you to move your team you need certain documents for submission and approval. Site mobilization method statement is one of such requirement. Now a days most of the government entities require that all contractors must submit a plan which details how mobilization… Read More »

Sequence of Operation for Variable Volume Type FAHU with Plate Heat Recovery

Below sequence of operation is for Variable Volume Type FAHU with Plate Heat Recovery system. The system shall be variable volume package Fresh Air Handling Unit. The scope of the unit shall consist of: Supply Side accessories Intake motorized damper Panel (Pleated) Filter Bag Filter Cooling Coil Supply Fan (with VFD) Plate Heat Exchanger Intake and discharge… Read More »

Drainage Pipe Installation & Hydrostatic Testing Method of Statement

When off loading, the drainage pipe shall be lowered to the ground either manually or with crane. Timber supports of at least 3” wide shall be placed beneath the pipes with spacing not greater than 2 mtrs. Closer supports will be required for sizes below 160mm. Drainage pipes shall not be stored under direct sunlight… Read More »

Method Statement for PVC Electrical Conduit – PVC Pipe Installation

Plastic electrical pvc conduits are common item which is useful for electrical wiring using pvc pipe. Since these electrical conduits are not much stronger as compared to metallic GI conduits therefore need proper handling and storage. Plastic electrical conduit pipes while unloading shall be lowered properly, not dropped to the ground. While during the storage,… Read More »

Method Statement for Testing and Commissioning of Fire Alarm System

Before starting the commissioning of Fire Alarm System, make sure that system installation is complete and approval is available. Verify the absence of unwanted voltage between circuit conductors and ground. Test all conductors for short circuits using an insulating testing device. With each circuit pair, short circuit at the far end of the circuit and… Read More »

Method Statement for Installation of GI Ducts for HVAC System

This mechanical hvac method statement covers the installation of GI ductwork. Procedure defines the method used to ensure GI ducting installation has been carried out as per contract requirements and best practices. The method statement gives details of how the work will be carried out and what health and safety issues and controls are involved.… Read More »

Method Statement for Installation of Sump Pump

Pump shall be stored on a flat surface in well ventilated storage area. Inlet and outlet flange blanks shall not be removed until ready for connection to pipe work. Manufacturer’s instructions shall be strictly followed as applicable. If the pumps are stored for longer periods the shaft shall be periodically rotated and lubricated, if required. The… Read More »