Testing & Commissioning

SOA of AHU

Sequence of Operation for Single Zone Variable Volume Type Recirculating Air Handling Units AHU

Below sequence of operation is for single zone Variable Volume type recirculating Air Handling Units AHU’s. The system shall be variable volume package Fresh Air Handling Unit. The covering of the sequence shall consist of: Supply Side coverage of scope Exhaust Side coverage of equipment’s Sequence of Operation The Variable Volume re-circulating type AHUs for single zone […]

Sequence of Operation for Single Zone Variable Volume Type Recirculating Air Handling Units AHU Read More »

Building Management System, Testing & Commissioning

Ring Main Unit Testing and Commissioning Method Statement

In a ring main unit distribution system feeder covers the whole area of supply in the ring fashion and finally terminates at the substation from where it is started. The unit forms a closed loop and looks like a ring. The advantages of RMU is that less conductor material is required as each part of

Ring Main Unit Testing and Commissioning Method Statement Read More »

Electrical Method Statements, Method Statements, Testing & Commissioning

UV Sterilization System Testing and Commissioning Method Statement

Ultraviolet UV Sterilization System are useful in many water purification systems to disinfect and control bacteria. Ultraviolet or UV energy is found in the electromagnetic spectrum between visible light and x-rays and can best be described as invisible radiation. UV light occurs with a wavelength ranging from 200 to 390 nanometers (nm). The most effective

UV Sterilization System Testing and Commissioning Method Statement Read More »

Method Statements, Plumbing Method Statements, Testing & Commissioning

Car Parking Management System Testing Commissioning Procedure

Electric installation and maintenance work may be carried out only by appropriately qualified licensed electricians. Mains connections must be hard-wired. Please ensure full compliance with all applicable national and international rules and regulations concerning electric connections, as well as all applicable safety rules. System units may be used only for their intended purpose, as specified

Car Parking Management System Testing Commissioning Procedure Read More »

Construction Method Statements, Electrical Method Statements, Method Statements, Testing & Commissioning
main-distribution-board MDB Testing Procedure

Main Distribution Board MDB Testing & Commissioning Procedure

Upon completion of the LV Distribution Board installation including proper terminations into each breaker, the same shall be offered up for inspection from consultants. Earth fault loop impedance test & earth leakage test for LV Distribution Board shall be done & recorded in prescribed format. There are 3 cases to be considered. Case 1 is

Main Distribution Board MDB Testing & Commissioning Procedure Read More »

Electrical Method Statements, Method Statements, Testing & Commissioning