HVAC Method Statements

Method statement for building construction is very important for successful completion of the construction projects. HVAC is a major discipline of any project and MEP engineers are using method statements for air conditioning works. Method statements include the ducting works, sleeves, chilled water piping, pipe welding, flushing of pipes and installation of HVAC equipment’s. In addition to installation method statements the requirements is also for testing and commissioning method statements. As part of method statement there are always, risk assessments, inspection and test plans ITP and inspection checklists.

Below you can browse our collection of method statement for HVAC building construction works free of cost. If you are looking for editable files in Word format that you can also use for submission then you may need to visit our method statement download center.
HVAC Building Construction Method Statements

Bypass Terminal Reheat Units Testing & Commissioning Method

Pre-Commissioning Procedure Before starting the commissioning activities check and ensure that bypass Terminal Reheat units are installed as per the approved shop drawings and manufacturer’s instructions and approved. Check that sensing grids tubing connection from the grids to the transducers are correct & secure. Check for proper mounting of the actuator on the body of […]

Bypass Terminal Reheat Units Testing & Commissioning Method Read More »

Construction Method Statements, Duct Works, HVAC Method Statements, Method Statements
General Instructions and Method Statement for Chemical Cleaning of Carbon Steel Pipelines

General Instructions and Method Statement for Chemical Cleaning of Carbon Steel Pipelines

Following is a precise chemical cleaning procedure that will ensure the internal and external cleanliness and protection of the pipes before the piping process unit is put into service. Scope of work covers all the horizontal and vertical pipelines through all the areas in the project and buried underground lines in the infrastructure area as

General Instructions and Method Statement for Chemical Cleaning of Carbon Steel Pipelines Read More »

HVAC Method Statements
tig-welding-procedure

Types of Welding WPS, CWB Arc Welding Tig Welding

Before going to the welding procedure in full detail let’s first understand what is welding? The term welding is used in mechanical engineering when we are joining two or more pieces of any material typically metal by application of heat, pressure or combination of both. This is simplest definition for welding. Mostly the term is

Types of Welding WPS, CWB Arc Welding Tig Welding Read More »

HVAC Method Statements, Stainless Steel Fabrication

Welding Procedure | Arc Welding Machine

This welding procedure or Method statement describes in detail the welding process for pipe work and the welder’s qualification test procedures. This includes addressing programs for implementing commitments regarding the quality of welding works. Scope and Purpose This document outlines the method for executing welding procedure for pipe work and welding procedure qualification test for ARC Welder. This

Welding Procedure | Arc Welding Machine Read More »

HVAC Method Statements, Stainless Steel Fabrication
AC Duct Cleaning Method Statement for HVAC Ducts & Accessories

AC Duct Cleaning Method Statement Best for HVAC Ducts & Accessories

The purpose of this ac duct cleaning method is to remove the inert suspended matter such as foreign objects, moulds etc. HVAC duct cleaning will be done until all suspended matter and loose debris are fully removed from the ducting system. Following tools shall be arranged before starting the ac duct cleaning works of HVAC

AC Duct Cleaning Method Statement Best for HVAC Ducts & Accessories Read More »

Construction Method Statements, Duct Works, HVAC Method Statements, Method Statements

Testing & Commissioning Procedure for Ventilation and General Exhaust Fans

Mechanical Pre-commissioning checks for Exhaust Fans Carefully inspect the unit and check the installation with anti vibration materials is complete. Check and ensure the shipping bolts / clamps are removed. Check tightness of all nuts / bolts, screws, fasteners etc. as applicable. Check the alignment of belts and adjust the tension (where applicable). Check the ductwork connections

Testing & Commissioning Procedure for Ventilation and General Exhaust Fans Read More »

HVAC Method Statements, Method Statements, Testing & Commissioning
SOA of AHU

Sequence Of Operation For Variable Volume Type Fresh Air Handling Units

Sequence of operation is very important part of testing and commissioning of equipment’s. This becomes more important when matter of mechanical systems is considered. SOA is technical document that is developed based upon the mechanical systems performance and operation requirements. Sequence of operation is part of building management system BMS submission documents. BMS covers the

Sequence Of Operation For Variable Volume Type Fresh Air Handling Units Read More »

HVAC Method Statements, Testing & Commissioning

Sequence of Installation for the Chiller Plant Manager CPM Field Devices

Sequence of Installation for the Chiller Plant Manager Field Devices Safety All site safety rules & regulations shall be complied with. Supervisors will deliver tool box talks, relevant to these activities to all operatives involved in the installation and shall be recorded. All operatives will be equipped with minimum personnel protective equipment; hard hat, coveralls,

Sequence of Installation for the Chiller Plant Manager CPM Field Devices Read More »

Construction Method Statements, HVAC Method Statements, Method Statements