Scope of Work This method statement is applicable for Installation, Testing & Commissioning of BMS building management system in accordance with the specified standards and regulations in project specifications. The Scope of works includes the delivery to site, installation, testing & commissioning of
Read Complete Method
VAV Pre-Commissioning Checking & Start up procedure Visual inspection to ensure that all DDC panels, sensors, actuators and other system devices are installed as per the approved point list, schematic drawings and specifications. Check the wiring of field devices with DDC panel
Read Complete Method
Below method statement is for testing and commissioning of DDC panels and FCU (fan coil units) with respect to building management system BMS. Pre-Commissioning Checks for field Instruments Check installation of all field instruments for correct location and position as instructed in
Read Complete Method