Method Of Statement For Structural Excavation & Backfilling

Excavation and Backfilling for Culverts, Storm Sewers and Ducts Precast concrete and steel pipe culverts and pipe ducts will be installed in trenches cut into previously constructed and compacted embankment either from the subgrade or from an embankment height at least twice the nominal diameter of the pipe. Unless otherwise noted on the drawings, trenches […]

Method Of Statement For Structural Excavation & Backfilling Read More »

Civil Engineering Methods, Method Statement for Civil Works, Method Statements
excavation measurement procedure

Method of Measurement for Structural Excavations

Measurement of Structural excavation will be limited to excavation for foundation for bridges, retaining walls, box culverts or cross sectional area exceeding 1 sq. mtr, box culvert wing walls, head walls, toe walls and aprons, manholes, pump houses and sub-stations. For box culverts 1 sq. mtr or less, pipe culverts, storm sewers and ducts, measurement

Method of Measurement for Structural Excavations Read More »

Civil Engineering Methods

Method Statement for Earthwork Related to Track Work

Before start of work, following equipment and machinery shall be arranged for earthwork and monitoring. Excavators Dump Trucks Bull Dozers Compactor Rollers Settlement Gauges/Settlement Markers Survey Equipment To begin with, licensed surveyor is required to establish the boundary and the temporary bench mark and existing ground level (EGL) all these have to be confirmed by

Method Statement for Earthwork Related to Track Work Read More »

Civil Engineering Methods, Construction Method Statements, Method Statement for Civil Works, Method Statements
Construction site mobilization

Construction Project Site Mobilization Method Statement

Project starts from project mobilization. Once you win the project and client asks you to move your team you need certain documents for submission and approval. Site mobilization method statement is one of such requirement. Now a days most of the government entities require that all contractors must submit a plan which details how mobilization

Construction Project Site Mobilization Method Statement Read More »

Civil Engineering Methods, Construction Method Statements, Method Statement for Civil Works, Method Statements
BMS System Control devices

Electrical & Mechanical BMS Control Devices

Chilled Water Automatic control valves 2″ and smaller shall be screwed type, of red brass material and valves 2½” and larger shall be cast iron type and flanged. Valves shall be ANSI- rated to withstand the pressures and temperatures encountered. Valves shall have stainless-steel stems and spring loaded Teflon packaging with replaceable discs. All valves

Electrical & Mechanical BMS Control Devices Read More »

Building Management System

BMS Energy Management Software Control Functions

Generally any energy management control software shall provide as a minimum the following functions. Each function is detailed separately. Time Control Modes There shall be no limit to the number of time schedules each of which can have any point or number of points assigned. Each time programme shall operate over a seven-day week and allow

BMS Energy Management Software Control Functions Read More »

Building Management System

BMS Alarms Reporting and Functions

The BMS provides a vehicle for the visibility of plant failure, patterns, annunciation of alarms and the reporting function. In particular it shall provide the standard functions stated below: Alarms shall be generated under the following conditions: Digital input contact change from normal to alarm condition (either open or closed). Digital input condition either matches

BMS Alarms Reporting and Functions Read More »