Plumbing Method Statements

jointing procedure using solvent cement

Installation Method Statement for Water Feature Piping Equipment and Accessories

Below is a brief method statement that covers installation of water feature equipment’s and accessories, in accordance with project specifications and manufacturer’s installations. MEP project manager, engineers site supervisors shall have overall responsibility for adherence to the approved method statement, project quality and site safety plan. They shall ensure that adequate resources and personnel are […]

Installation Method Statement for Water Feature Piping Equipment and Accessories Read More »

Plumbing Method Statements
Method Statement For Installation Of Stainless Steel Shower Gullies and Drain Outlets

Method Statement For Installation Of Stainless Steel Shower Gullies and Drain Outlets

This plumbing method statement covers the nature and type of work for drainage outlets stainless steel shower gullies for the project as per site requirements. Method statement also covers frequency of which inspections are to be carried out. All documentary requirements for the installation works will be submitted for approval of consultant and this will

Method Statement For Installation Of Stainless Steel Shower Gullies and Drain Outlets Read More »

Plumbing Method Statements
Process Pipe Pneumatic Testing Manifold Connection Diagram

Method of Statement for Pneumatic Testing of Distribution and Process Piping System

The scope of this method of statement is to define the methodology for pneumatic pressure testing of any kind of distribution or process piping system. During the activity and works, there will be continuous communication arrangement among all parties i.e. Project Management Team, hydro/pneumatic pressure testing engineer and all personnel working on site. Below is

Method of Statement for Pneumatic Testing of Distribution and Process Piping System Read More »

Plumbing Method Statements, Testing & Commissioning
45° Elbow to Pipe Fit Up

Pipe Welding Work and the Welder’s Qualification Test Procedure

Below method statement describes in detail the welding process for pipe work and the welder’s qualification test procedures. This includes implementing the company commitments for achieving the best quality of welding works. The document outlines the method for executing welding process for pipe work and welding procedure qualification test for welders. This method statement covers

Pipe Welding Work and the Welder’s Qualification Test Procedure Read More »

HVAC Method Statements, Plumbing Method Statements, Steel Structure & Fabrication

Butterfly Valve Installation and Maintenance Procedure

This method is for installation and maintenance of wafer type butterfly valve or lug style butterfly valve with a cast iron body construction, SS stem and disc and either EPDM, BUNA-N or Viton liners. Although the procedure is specifically provided for bi-Torq butterfly valves but is useful for any other such type of valves. General

Butterfly Valve Installation and Maintenance Procedure Read More »

Plumbing Method Statements, Preventive Maintenance
strainer installation method statement

Method Statement for Installation and Maintenance of Strainer

Strainers are installed to prevent foreign matter e.g. scale and dirt causing damage to pipeline equipment. Service temperature and pressure indicated on the identification plate or body marking should not be exceeded. Crane strainers have not been designed as fire safe pressure equipment. Strainers must be installed into a well-designed system and it is recommended

Method Statement for Installation and Maintenance of Strainer Read More »

Plumbing Method Statements
irrigation-system-piping

Method Statement Irrigation Systems Piping

Only approved material shall be used. Delivered material shall be stored at stores and shall always be subject to client’s representative inspection. Special shaded pipe racks shall be constructed to store pipes. Fittings and irrigation materials shall be stored inside containers that will be kept closed at all times. Transportation: All materials will be transported to

Method Statement Irrigation Systems Piping Read More »

Plumbing Method Statements