Testing and Commissioning Method Statement For Drainage System
Below is the step wise procedure for Testing and Commissioning Method Statement For Drainage System Instruments & Tools required: Valve operating keys. Measuring Stick Plumbing Toolkit Work Sequence / Commissioning Phases Pre-Commissioning: System Pre-Commissioning Checks Before commissioning the system the following shall be ensured. The Installation and Leak testing of the pipes are completed. The installations sanitary… Read More »