Tag Archives: Air balancing of FCU

Procedure for Air Balancing of HVAC Ducting System

The purpose of this procedure is to define the step by step method to implement the correct practices for the “Air Balancing “through the guidelines contained herein so as to ensure that the job execution complies with the project requirements and serves the intended function to satisfactory level. Below is list of equipment and tools necessary for performing… Read More »

Air Balancing Procedure for HVAC System FCU AHU Exhaust Fans & Pressurization Unit

Below is a precise air balancing procedure that covers the HVAC system equipment and ducting system.  Air Balancing For Fan Coil Units Check that all automatic controls are fully commissioned and operating properly All pre-commissioning checks have been carried out Select the specified speed of the Fan Coil Set all the dampers in the grill… Read More »