Lifting Work Safety Method Statement

This document covers the procedure to establish a method statement for all lifting activities for any kind of project especially laying of large transmission pipelines.

The purpose of this document is to follow proper methodology and to carry out the activities and sequence of lifting works for laying of transmission pipelines at any kind of project.

This safe works method details the followings,

References & Standards

Roles and Responsibilities

All personnel delegated to the work would have undergone the relevant mandatory and project specific in-house training, and all personnel would be competent for the tasks that they will be carrying out.

Supervisory personnel will act as “lead person” by following and guiding the team.

Project Manager

Project Engineers

HSE Coordinator

Lifting Supervisors

Crane Operators

Riggers

Signalmen

Banksmen

Foremen/ Supervisor

Workers

Necessary Equipment’s Tools and Resources

Equipment’s

Tools

Man Power

LIFTING METHODOLOGY

Preparatory Work

Ensure that the document received bear the stamp “Issued for Construction” and are of latest revision.

The documents submitted/referred with this method statement shall be considered as an integral part of this method statement and shall be read in conjunction with the same.

The crane operator will be required to attend the in-house safety Induction at site.

Lifting Supervisor & crane operator will check & plan the travel routes prior to mobilization. Ensure travel routes & access to the jobsite is in good condition and free from obstruction.

Check and confirm crane set-up positioning.

The engineering drawings and documents received shall be clearly understood to find out the service, material specification, size, thickness, pipe routing quantity etc. line wise and area wise.

Make sure that all the Pre-Construction formalities, approvals, and preparations are done sufficiently in advance to start the lifting activity as per the schedule.

A checklist of all requirements shall be made internally to avoid any omission of them.

All equipment to be used in the work should be initially checked and approved by power gas’s authorized personnel.

Working area shall be barricaded with proper devices & warning signs to display.

Unauthorized person are not allowed in the area barricaded off.

Workers shall wear appropriate PPE for the task.

Safety Coordinator & supervisor shall be present at all time during work activity.

Work Execution Method

Lifting:

All lifting tools, equipment’s and ropes used for lifting shall be inspected and certified by WSH regulations. Activities shall be done according to the proper method statement for lifting.

Submit method statement and RA for review and approval by the client before commencing the mentioned work.

Upon mobilization of crane in to the site, the copies of crane operator’s license, LM certificate and test certificate of lifting gears will be obtained from the crane operator, verified and kept for records.

Lifting Supervisor must verify that the strength / condition of the lifting gears and equipment’s are adequate and they are certified with the safe working load. No lifting operation shall be performed when the load exceeds the safe working load.

Only authorized persons and personnel involved in the lifting are allowed in the lifting operation area. Critical lifting operation area and other areas with potential hazard/danger must be cordoned off to prevent access for all unauthorized personnel.

Positioned the Crane near the designated area and steel plate should be place over the landed of the crane out-rigger.

Lifting plan shall be filled up and attached with load chart and LM certificate shall be submitted during application for permit.

Apply the lifting permit before work commence. Lifting supervisor will conduct tool box and brief the safe lifting operation before work start.

Prior to Lifting Works, it must have an approved Lifting permit and Lifting Plan. Which indicate the type of cranes & lifting gears accessories indicated. The lifting plan must be attached with the lifting permit and display in the lifting area.

Lifting supervisor shall conduct tool-box meeting / pre-work briefing about the risks, hazards and available control measures, using the risk assessment.

Positioned the trailer near the designated area and proper and adequate clearance should be maintained between the fence and the trailer.

Trailer must be secured with hand brake.

Before starting the lifting work, the assigned people must wear proper PPE and adequate safety procedure must be implemented.

All employee and worker involved in the work should first undergo training or safety induction.

Contractor shall employ an experienced, competent and responsible Lifting supervisor to plan and execute lifting operations.

Barricade the marked location scheduled for lifting operation with safety signages.

Use the crane operator’s and lifting supervisor’s checklist before lifting operation.

Special care shall be taken when a crane has to operate on soft or sloping ground or close to the sides of trenches. Outriggers and sufficient heavy timber blocks or plates must be used and carefully placed to ensure stability.

To Provide safe work during lifting of pipes, there are consideration which take according to weight of the pipe.

The site supervisor should prepare the site area to be clean and clear from obstruction.

Rigging work shall be performed under the direction of the lifting supervisor.

The load shall be controlled by means of tag lines to prevent the load from turning or swinging.

For hoisting or lowering of loose materials such as stones, bricks, tiles, slates and bolts & nuts, safety nets or sand bucket or other suitable containers will be used to contain any drops.

Wire rope shall be replaced when the following critical condition is observed:

The communication between crane operator and the signalman will be established by using hand signals / walkie-talkie in the case of remote places where the operator has no visibility.

Suspended loads are not to be left unattended.

When the crane is not in use the hook will be raised up to a safe height away from any moving vehicles, machines or person.

Safety equipment must be always present and ready for immediate use.

HEALTH, SAFETY AND ENVIRONMENT

HSE Manager shall ensure that the work is performed in accordance with the approved health and safety manual and precautions specified in the work permit. He shall ensure that barricades, warning tapes, warning signs, firefighting equipment’s and first aid kits are readily available at the working area.

Tool box talk shall be conducted on a daily basis to inform the workers of the recent safety issues and incidents and to get feedback of any unreported unsafe acts. Feedback will then be processed and resolved.

Safety Procedures

Area shall be barricaded adequately with warning signs.

All Equipment’s and tools shall be checked for good conditions before commencing the work.

Unauthorized persons shall be excluded from the area.

Adequate caution boards and warning signs shall be provided.

On completion of job, the area shall be cleared of any materials and keep clean and tidy.

Hazard analysis for hazardous operation shall be carried out prior to commencing the works.