Method Statement For Final Sub Circuit Wiring

Installation of sub circuit wiring

Check the installation & approval of distribution board / back box either recessed or surface and termination of all conduits & trunking completed. Confirm DB reference with load schedule detail. Check all conduits as per circuits are installed.

Clean distribution boards and make sure all conduits are free from blockage. Use of air blowers to clean conduits is helpful.

All wiring of multi-point circuits shall be carried out in a ‘looping-in’ system and no joints and connections other than those required for the final connection at the DB, ceiling rose, switches, fuses, socket outlets, motors, etc.

Wires shall be drawn-in carefully and professionally to avoid damage to insulation. Wires shall be ‘combed’ as drawing-in operation proceeds.  The Neutral and Earth Continuity Conductor of each circuit shall be drawn along with the Phase conductors of that circuit in individual conduits.

Two circuits of different phase colours cannot be drawn into one conduit.  When drawing groups of circuits in a common trunking, ensure that individual circuit wires are bunched together with approved cable ties and segregated. Tape shall not be used to bunch circuit wires. Sufficient termination length of wires is to be left for the purpose of DB dressing works. Individual circuits should be marked at the DB end as per the Final Approved Load Schedule.

All wire sizes and phase colour should be checked against Final Approved Load Schedules prior to drawing in operations. (Ensure All load schedules are signed and approved by the Project Engineer prior to proceeding with any wiring works)

9. Inspection & Testing  Initial insulation testing is done prior to start of DB dressing works as mentioned above. Final insulation tests, polarity tests, and continuity tests is to be done prior to Consultant’s inspection.

Earth Resistance tests should be conducted utilizing the standard procedures and with Calibrated and tested professional equipment. All earth resistances should comply with regulations and Project specs.

Other tests are to be done as per Consultants requirements and Project Specifications.

In-Process works shall be monitored daily by the Supervisor, Project Engineer and Consultant Engineer for quality of workmanship and installation method against approved layout/shop drawings, approved submittals, project specifications, and prevalent applicable regulations

All works shall be inspected for conformance to specifications and applicable legal requirements.