Site icon Method Statement HQ

Clean Agent Fire Suppression System Best Installation Method Statement

This procedure covers installation and inspection of clean agent fire suppression system, the procedure is for FM 200 but can be useful for many other systems like novec, ansul etc.

Quality of clean agent fire suppression system installation and materials at site will be ensured by project team consisting of a Project Manager, Project Engineers, QA / QC Engineer and the site Foremen. All will be according to the Specification, NFPA standards and /or local civil Defense authority requirements. All materials to be used are as per the approved material submittals.

CLEAN AGENT SYSTEM DESCRIPTION

The Clean Agent system consists of a Central banking system with main cylinders and manifolds. The total No. of cylinders is selected based on the requirement of the largest room. The No. of cylinders triggered will depend on the quantity of Clean Agent gas required for that particular area and will be directed to that area by an electrically operated Directional Valve.

The system shall provide a Clean Agent minimum design concentration of 7 %, by volume, in all areas and/or protected spaces at the minimum anticipated temperature within the protected volume.

The fm 200 or any other system shall be complete in all perspectives. It shall include all mechanical and electrical installation, all detection and control equipment, agent storage containers, Clean Agent, nozzles, pipe and fittings, manual release and abort stations, audible and visual alarm devices, auxiliary devices and controls, shut downs and testing, training and all other operations necessary for a functional, Clean Agent suppression system.

The system shall be actuated by a combination of ionization and /or photoelectric detectors installed within the protected spaces.

Automatic Operation of each protected area shall be as follows:

After completion of the time-delay sequence, the clean agent fire suppression system shall discharge and the following shall occur:

  1. Shutdown all power to high / voltage equipment.
  2. Energize a visual indicator outside the hazard in which the discharge occurred.

The system shall be capable of being actuated by manual discharge devices located at each hazard exit. Operation of a manual device shall duplicate the “Verified Detection” sequence description above except that the time delays and abort functions shall be bypassed. The manual discharge station shall be of the electrical actuation type and shall be supervised at the main control panel.

Design Data for Clean Agent Fire Suppression System

Clean Agent is an electrically non-conducting, volatile or gaseous fire extinguisher that does not leave a residue upon evaporation.

System Component

Clean Agent: The amount of clean agent in the system shall be at least sufficient for the largest single hazard or group of hazard that are to be protected simultaneously.

Storage container:  The clean agent is stored in container to hold that specific agent at ambient temperature.

Storage container and accessories shall be so located and arranged that inspection, testing, recharging and other maintenance activities are facilitated and interruption of protection is held to a minimum.

It can be located as close as possible to or within the hazard or hazards they protect.

Where it is manifold, check valve will be provided to prevent agent loss if the system is operated when any containers are removed for maintenance.

Networking of pipes Detectors, actuator & control system

Automatic detector shall be any listed method or device capable of detecting and indicating heats flame, smoke, combustible vapors or an abnormal condition in the hazard such as process trouble that is likely to produce fire.

Operating Devices

Electric control equipment. A fire alarm control panel shall supervise the actuating devices and associated wiring and as required, cause Actuation.

Time Selections: It is used only for personal evacuator or to prepare the hazard area for discharge.

Storage and Handling for Clean Agent Fire Suppression System

Using suitable means of transportation carefully transport packaged/crated components to their place of installation.

Ensure cylinders are not installed where they could be exposed to fire or an explosion hazard.

They should be installed in such a way to ensure ease of removal after use or for weighing and inspection.

Each container has a nameplate with an identifying part number. The part numbers should be checked against the parts listed on the system plans to verify that the correct equipment was received.

Cylinder containers should be located according to system plans in clean, dry, relatively vibration free areas.

Cylinders should never be mounted in any area which the cylinders could potentially be submerged in liquid.

Ensure cylinders are not exposed to direct sunlight.

Cylinder brackets shall be mounted securely to rigid surfaces which will support the container load.

Work Sequence and Methodology for Clean Agent System

The erection/installation work area/s should be cordoned or taped off and safety notices displayed.

Cylinder and piping to be securely bracketed especially at the fittings and nozzles

Clean and blow out all pipes before installing

All dead end pipes lines to be provided with a capped nipple.

After assembly, blow out entire pipe system before installing discharge nozzles

Methodology of Work

Starting with the cylinder manifold, securely mount the manifold at the appropriate height.

Continue piping remainder of the distribution piping, following appropriate approved for construction drawing

All piping must be rigidly supported by a combination network comprised of pipe hangers and rigid support brackets. Pipe hangers are used to support the “dead load” of the pipe system. Pipe hangers shall be space at intervals not exceeding 12 feet.

Rigid supports are required to support the “live load” of the pipe system during discharge. Rigid bracing is required at each directional change fitting, tee and nozzle. All drops to 180 degrees nozzles require back-bracing in the opposite direction of the discharge.

Before installing nozzles, blow air through complete piping system to determine there is no blockage.

Note: All piping shall be laid out to reduce friction losses to a reasonable minimum and care shall be taken to avoid possible restrictions due to foreign matter or faulty fabrication.

Installation of Conduits and Cables For Fire Suppression System

GI Conduits Installation

Installation of open clip cables

As an alternative you can install the fire suppression system electrical cabling as under:

Installation of Fire Suppression System Devices

Installation of Clean Agent System Panels

Installation Of Clean Agent Fire Suppression System Mechanical Components

Cylinder Installation

Identify the actual location of the cylinder based on the approved shop drawings.

Install the supports: 

Mark the drill hole location on the wall corresponding to the mounting bracket supplied with the cylinder.

Drill the holes as per drop-in anchor size and install the mounting bracket on the wall using drop-in anchor bolts.

Install the Cylinders:

Mount the fire suppression system gas cylinder on the mounting bracket and tighten the cylinder on the mounting bracket with the supplied strap using bolts.

Painting of Pipes: 

Clean the black pipe with cotton rag to remove any dust or grease on the pipes.

After cleaning, paint the black pipes with 1 layer undercoat of wash primer. Ensure all sides (top & bottom) are painted evenly.

Put the painted pipes in a good ventilation condition for 24 hours for the paint to dry.

After the paint is dried, then paint the pipes with 2 layer of finish coat. Ensure all sides (top & bottom) are painted evenly.

After the finish coat is dry, install the pipes as per approved shop drawings of clean agent fire suppression system.

Installation of Pipe Support for fire suppression system

Identify the actual location of the hanger based on the approved shop drawing. Mark the position for installing the drop in anchor after coordination with Structural Engineer.

Cut the required length of the GI angle as per the site condition.

Fabricate the support by welding the angles as per the approved shop drawing.

Drill holes on the fabricated support for fixing the GI angle to the wall/slab and also for installation the pipes using U bolt as per require pipe sizes.

Locate the required support locations as per the approved shop drawing and marks the holes to be drilled on the wall/slab.

Drill the hole on the marked position as per the anchor bolt sizes.

Insert the drop in anchor in the hole.

Tighten the GI angles on drop in anchor using bolts.

Rigid bracing is required at each directional change fitting, tee and nozzle.

Grooving Procedure for fire suppression system piping

Cut the required length of the pipe to be grooved.

Check that the cut ends of the pipe are square.

Install the correct die on the grooving machine for the corresponding pipe size.

Threading Procedure for fire suppression system piping

Pipe Cutting

Cut the required length of the pipe to be threads.

Check that the cut ends of the pipe are square.

Install the Threading Dies

Install the correct die head with threading teethes on the threading machine for the corresponding pipe size.

Thread the Pipe

Insert the end of the pipe to be threaded in-between the die head and tighten the chuck to hold the pipes properly.

Support the other end of the pipe using the pipe stand.

Start the machine and engage the die head into threading position.

Thread the pipe until the required length of the thread is achieved.

After the threading, loosen the chuck and remove the pipe.

Drain the residual threading oil from the pipe into the oil tray of the threading machine.

 Fire Suppression System Coupling Installation

Groove the pipe ends according to the manufacturer’s specification, project specification and consultant’s approval.

Pipe must be free from indentation, projection or roll marks on exterior from the end to the groove, to assure a leak tight seat for the gasket.

Pipe must be free from indentation, projection or roll marks on exterior from the end to the groove, to assure a leak tight seat for the gasket. Refer to figure 1 next page.

Place gasket over pipe ends, being sure gasket lip does not overhang pipe end.

Align and bring 2 pipe ends together and slide gasket into position centered between the grooves on each pipe. No portion of the gasket should extend into the grove on either pipe.

Loosely assemble all segment leaving on nut and bolt off to allow for “swing-over” feature.

With 1 nut and 1 bolt removed, use the “swing-over” feature to position housing over gasket and into the grooves on both pipes.

Insert the remaining bolt to allow easy tightening of the nut. Be sure track head engages into housing recess.

Tighten nuts alternately and equally maintaining metal-to-metal contact at the angle bolt pads. Tighten securely to assure a rigid joint.

Mechanical-T Installation

Drill the hole according to the manufacturer’s specification, project specification and consultant approval.

Remove 1 nut and bolt from housing. Loosen the other nut until it is flush with the end of the bolt. Remove the tape and lift the gasket from Mechanical-T outlet.

Check gasket supplied to be certain it is suited for intended service. Apply a thin coat of silicone lubricant to gasket lips and outside of gasket.

Reposition gasket into housing using alignment tabs on slides for proper positioning.

Rotate the lower housing approximately 90° away from the upper housing in the hole.

Make sure that the locating collar is in the outlet hole by rocking the upper housing in the hole.

Insert bolts in his hole and finger tighten both nuts. Be certain oval-neck of bolt engages recess in housing. Make sure that the locating collar is in the outlet hole and the positioning lugs are properly aligned.

Tighten bolt nut uniformly until the upper housing is in complete surface contact in the gasket pocket area and the assembly is rigid.

 Screw Fitting Installation

 Check the pipe length required based on the approved shop drawing.

Mark the desired length on the pipe and cut it. Make sure the pipe ends are square.

Place the pipe in the threading machine and thread it accordingly. Make sure the thread of the pipe is in good condition.

Remove the oil from the pipe end after the threading procedure and wrap it with Jute and Boss White or Teflon tape.

Install the pipe to the screw fitting.

Fire Suppression System Nozzle Installation

Install the pipe as per approved shop drawings with provision to install the nozzles at location as indicated on the approved shop drawing.

Install support near to the last bend of each nozzle location.

All drops to 180 degrees nozzles require back-bracing in the opposite direction of the discharge.

Ensure that there is no residuals present inside the pipe before installing the nozzles.

Install the nozzles by tightening the nozzles at the last end of the pipe at location as identified on the approved shop drawings.

Testing & Commissioning of Fire Suppression Clean Agent System

Pressure testing documentation for fire suppression system shall be submitted along with inspection request for consultant /client approval.

Click Here To Download Inspection Check List For Installation Of Clean Agent Fire Suppression System

Exit mobile version