Category Archives: HVAC Method Statements

Method statement for building construction is very important for successful completion of the construction projects. HVAC is a major discipline of any project and MEP engineers are using method statements for air conditioning works. Method statements include the ducting works, sleeves, chilled water piping, pipe welding, flushing of pipes and installation of HVAC equipment’s. In addition to installation method statements the requirements is also for testing and commissioning method statements. As part of method statement there are always, risk assessments, inspection and test plans ITP and inspection checklists.

Below you can browse our collection of method statement for HVAC building construction works free of cost. If you are looking for editable files in Word format that you can also use for submission then you may need to visit our method statement download center.
HVAC Building Construction Method Statements

Aluminium HVAC Duct Installation Method Statement

Below is a brief method statement that covers the duct installation of aluminium ductwork on a construction project. This procedure defines the method used to ensure hvac aluminium ducting installation has been carried out as per contract requirements and best industry practices. The procedure gives details of how the work will be carried out and… Read More »

Preventive Maintenance & Breakdown Maintenance Plans and Procedures [Download]

If you are looking for preventive maintenance & breakdown maintenance program, plans, schedules and procedures then this is right place. We are providing editable method statements and procedures that can help you for conducting the planned maintenance of electrical and mechanical equipment’s and systems. Preventive maintenance is an essential part of any facility management works.… Read More »

Pipe Welding Work and the Welder’s Qualification Test Procedure

Below method statement describes in detail the welding process for pipe work and the welder’s qualification test procedures. This includes implementing the company commitments for achieving the best quality of welding works. The document outlines the method for executing welding process for pipe work and welding procedure qualification test for welders. This method statement covers… Read More »

Ventilation Fan Installation Method Statement

This document applies to the inward site inspection, installation and inspection methods to be adopted for the ventilation fan installation. After receiving on the project site, ventilation fans shall be stored in a clean / dry place and adequate covering by tarpaulin sheets to be provided to protect the equipment from deposition of construction dust… Read More »

Method Statement for Installation of Fan Powered Box Units

Unless otherwise specified, all installation shall be in accordance to approved shop drawings and contract specifications. Drawing plans, schematics, and diagrams indicate general location and arrangement of Fan Powered Box units. Install Fan Powered Box as indicated unless deviations to layout are approved on coordination drawings. Transfer the Fan Powered Box units from the stores… Read More »

Method Statement For Testing & Commissioning Of Cooling Towers

The scope of this method statement is to determine the thermal capability of water cooling towers. Its main purpose is to describe instrumentation and procedures for the testing and performance evaluation of water cooling towers. It is recognized that the data limitations specified throughout this Testing & Commissioning Procedure represent desired conditions which may not… Read More »

Method Statement for Installation and Maintenance of Strainer

Strainers are installed to prevent foreign matter e.g. scale and dirt causing damage to pipeline equipment. Service temperature and pressure indicated on the identification plate or body marking should not be exceeded. Crane strainers have not been designed as fire safe pressure equipment. Strainers must be installed into a well-designed system and it is recommended… Read More »

Sequence of Operation for Variable Volume Type FAHU with Plate Heat Recovery

Below sequence of operation is for Variable Volume Type FAHU with Plate Heat Recovery system. The system shall be variable volume package Fresh Air Handling Unit. The scope of the unit shall consist of: Supply Side accessories Intake motorized damper Panel (Pleated) Filter Bag Filter Cooling Coil Supply Fan (with VFD) Plate Heat Exchanger Intake and discharge… Read More »