Wall Panels Fabrication and Installation Method Statement

1.0 PURPOSE: The purpose of this procedure is to define how the Wall Panels Fabrication and Installation shall be carried out under the controlled condition.

2.0 SCOPE: This method statement covers the detailed procedure to be followed for Supply & Installation of wall panels as per approved shop drawings and schedule of finishes for the project. This procedure shall be read in conjunction with contract specification where applicable.

3.0 REFERENCES

4.0 DEFINITIONS& ABBREVIATIONS

 5.0 RESPONSIBILITIES

Project Manager is responsible for overall project execution, quality and safety. Adopt a leading role with respect to Contractor’s quality and safety procedures. The PM is responsible for the overall implementation of this method statement. The Project Manager shall ensure that the key personnel are well aware of the specifications and method statement.

6.0 MATERIALS

As per approved material submittals.

7.0 EQUIPMENTS & TOOLS

Below is the equipment involved in at the Site works:

The capacity / size of the above equipment shall be judged in accordance with site conditions, requirements, and availability at the time of execution.

8.0 SAFETY & HEALTH

SECURITY – HEALTH AND SAFETY CHECKLIST AT PLACE OF WORK:

9.0 PROCEDURE

9.1 Wall Panel:

Before Commencement of Manufacture in compliance with approved Shop Drawing, Cross check the Measurement at Site. If in case of any major variation at the site it must be report to the PE saying by document. If any variation it should be approved by the PE.

If any changes or rectification at the site it must be brought in to notice of Project Engineer and approval must be taken .After the cross check if any correction on the site Engineer must be report to the QCE for the production. The QCE handover the production department after his approval.

The production manager will cross check the drawing on his side for the each departmental head   f foreman. The foreman will prepare the cutting sizes according to the drawing for his subordinates. Mean while all the approved controlled samples should be hand over to QCE. The production manger will be inspecting him that production doing under the control of the sections foreman by the drawing delivered to site comply with approved samples.

Checks all the Materials are available in good quality and quantity that for execute the production.

Check for scratches, cracks, moisture. Avoid if such materials and return to the store.

Prepare MDF panel as per sizes required through the Circular Saw Machine for the carcass. Run through the base cutter machine.

Prepare the beach wood lipping all around by 10mm thick. The lipping joining to the MDF panel is clamp with industrial glue kept for dry at least two hours to strong enough joint.

Prepare the MDF bracket male and female to hang the panels at the wall.

Prepare temporary installation at the factory to make sure that panels are proper as per the sizes provided in the drawing.

Check any difficulties facing while on install the panel. If so bring up the solution to avoid any inconvenience at site.

Prepare for veneer pressing. Cut Out of the sheet by using veneer guillotine Machine. Once the share ready send for pressing to the hot pressing Machine by the temperature of Between 70-120°C.

Bring in to separate division for storage .All the veneer should be kept in isolated Air conditioned area.

 

Painting

Check the Material if the goods have been manufactured in compliance with Final Approved Shop Drawing. If not the material send back to the concerned section for the rectification. Send for Polishing After the approval of QAQC.

Clean veneer panel and remove the Glue of Joint.

Check for any cracks on veneer, Grains are in proper direction.

Make first sanding and apply the pate for the filling. Remove the over filled pate. The surface should be smooth plain.

The application of primer will take in to place as the first processing of painting. After the first coat primer on one side keep for dry about three to four hours.

After drying one side other side of the panel applied with primer and keep for dry again for three to four hours.

After dried on other side looks for any damage or cracks. Apply with N.C pate fill the gaps and cracks. Go for second sanding.

Again second processing of primer as above statement.

Check again and make sure there is no crack or gaps any more. If any apply the same pate and make even.

The final coat take in to place with the requirement of percentage of glossy or mate according to specified in the drawing.

Keep it for dry about three to four hours.

QA / QC CHECKS

After the completion of painting the QA/QA will inspect the materials for the quality control before dispatch to the packaging. The QA/QC will enter in to check list signed and stamped for the packing. In case of any rectification on painting the materials send back to the painting section with comments provide by the QA/QC.

The Points to be  checked by QA/QC

Check with control sample and make sure the same specification and materials used for painting.

Checks the surfaces of the materials are smooth. No any kind of particle spread on the material. No rough on the surface.

Check all the joint if any. No joint should be visible.

Check for all corner and lipping edges for damage or crack.

Check for all materials are even in finishing. There should not be any differences in finishing.

Segregate panel according to site installation number.

Send for packing.

MATERIALS USED FOR SANDING

Heavy Duty Machine

Second Sealer  Sanding

Final Check up  Sanding

Pate blade

N.C pate

Primer

Top coat

PROTECTION

All the Materials cleaned with pure soft cotton lining to remove all the dust if any.

Arrange the segregated materials by numbers provided in the check list.

Arrange the all hardware and fitting accessories for installation.

Make the protection each corner with thermo sheet in order to avoid any damage while on transport. All the Material packed individually to avoid any Damage. Pack with polyurethane sheet to avoid any Scratches. Pack with corrugated sheet with industrial heavy duty Masking Tape. Mark the top and Bottom. Check again is the packing is proper. Ready for loading.

DISPATCH AND DELIVERY

PROCEDURE

The Materials will be delivered once the ready for installation. The site must be free from Dampness. Check the truck any particles are there that may damage the Material. Keep the protection all around the side thermo sheet. Stack the Material properly. Check the vehicle all Materials kept properly. Hand over the D.O and Inspection report to the delivery section.

STORAGE

Storage must be provided by main contractor. The separate storage should be provided for the joinery contractor. The storage must be clean, empty and free from dampness. Once the Material reach to the site the Site Foreman inspect the dispatch form that the material received according to Receipt. Stack material according to code number. Stack the material by order. Space should be provided for the carry out the materials for easy dispatch.

All the code number should visible to identify.

9.2 Pre-Installation:

Site Condition Checking And Setting Out

9.3 INSTALLATION

Paneling

Check the site & study the drawing.

Cleanliness

Keep the site is cleaned after every duty hours. Do not dump any dust wastage at the working area. It should be cleaned adequately. Do not throw any wastage or unwanted Materials site itself. It should dispose to designed waste container. There should be normally three kind of dust collector will kept by the main contractor. Follow up the contained and dispose accordingly.

QA/QC  Checking

The Site Engineer co-ordinate with site foreman that all cabinets are installed as per the client requirement.

The following points to be taken care

Check for no scratches, damage panels

Check for all panels are aligned properly.

Check all the panels are even and straight.

Check for any gap between the panels.

Check for cleanliness and avoid any dust particle.

PROTECTION OF INSTALLATION

Clean with nice cloth. Make a protection with polyurethane sheet.

10. ATTACHMENTS