Testing Pre-commissioning & Commissioning Of Fan Coil Units

Before commencement of testing & commissioning activity, the supervisor must ensure that pre-commissioning of the FCU is complete and approved. All Installations & Pressure Testing of Pipe/ Duct works have been completed & approved by the consultant. Relevant documents or certificates shall be presented at the time of inspection if required by the Consultant.

Permission to start testing & commissioning or Civil Clearances has been given by the main contractor. All relevant Shop drawings shall be available & approved by the consultant. Safe access shall be provided by the Main Contractor thru Work Permit in coordination with the Safety in charge at site.

Inspect the relevant area for any possible clashes with other services. Check for other services, making sure that there is no interference between each service & adequate access to work and for future maintenance can be maintained.

Pre Commissioning Procedure for Fan Coil Units

Final Preparations Prior to Start-up/ Commissioning

ECM (Electronically Commutated) Blower: The ECM Blower is controlled by one of three control boards, depending on the options ordered with the unit.

 Start-up Procedures/ Commissioning

 Air System Balancing

 Water System Balancing

 FCU Controls Operation

General Test Methods for Fan Coil Units

Air dry-bulb and wet-bulb Measurements Points

It is intended that the specified test temperatures surrounding the unit being tested should simulate as nearly as possible the normal conditions of use of such unit. The point of measurement of specified test temperatures should be such that the following conditions are fulfilled:

 Water Inlet & Outlet Pressure & Temperature Measurement Points

 Condensate Measurements

 Drain Trap (P-Trap)

 Sound/ Noise Level Measurement

 Vibration Test