Steel Structure Building Construction Procedure

This procedure is useful for building construction based upon the steel structure erection work. Based on the design and specification, this document provides a proper step wise procedure and quality and safety management of the steel structure work.

The following items/equipments are basic requirements  for building construction of steel structure works at a large scale project.

Lifting Equipment, Ropes & Lines.

Electrical Equipment’s

Necessary Hand Tools

Health & Safety Requirements

Each workers shall be physically qualified to perform the duties to which he is assigned.

Steel Column Base Treatment Procedure

Cleaning of concrete column top surface.

Marking center line of steel column.

Leveling mortar base (using high grade mortar G150 ) at middle of 4 anchor-bolts with the same level of bottom of column-base-plate.

Checking level of column.

Grouting mortar for column base i.e. Sika- grout 212-11.

Steel Structure Erection Procedure

Phase 1:  Anchor Bolt Setting

Step 1: Marking for boundary line of starting column on footing

Step 2: Check and adjust position of starting column-rebar if necessary.

Step 3: Set form for starting column and support them carefully.

Step 4: Marking for bolt-group-center line on side of form.

Step 5: Set template  with anchor bolts. The template position is higher than concrete surface level. Marking line of bolt-group-center and each bolt must be matched on the template.

Adjust position of the template according to marking line on footing by plum bob.

Step 6: Welding diagonal supporting bar  to column rebar and anchor bolt.

Step 7: Check position of anchor bolt again.

Step 8: Protect bolt heads by masking tape

Step 9: Cast concrete for starting column

Step 10: After casting concrete, re-check anchor bolt position. Adjust the template if necessary.

Phase 2: Steel Structure Erection

Step 1:

Step 2:

Step 3:

Step 4:

Step 5:

Step 6:

Inspection & Quality Control for Metal Building Works 

Inspection is necessary at all steps of erection process, from the times materials are first received until the structure is completely installed. Inspection during the steel erection process shall be continuous in order to prevent the occurrence of possible damage and to require the maintenance of high standard workmanship. Inspection shall include members, painting, connection, alignment, bracings, roofing and wall cladding, equipment and false work.

Inspection of Members

Inspection of Steel Connection

a. Anchor bolts:

Check the tolerance of dimensions between anchor bolts to meet the required tolerance (5mm).

Check the tightness of anchor bolts to meet the require forces.

b. Bolts connection:

– The supervisor has to assure himself that the wrenches used are calibrated properly so that bolts are tightened the proper amount. Also the proper lengths of bolts shall be checked.

– After connecting, all bolts shall be tightened to obtain the required tension values

– Every connection point shall be inspected with the inspection record that is made by the team leader, with the confirmation of responsible engineers and Site Manager. The actual value of tension or torque moment of every bolt in the connection shall be shown on the record.

Bolt Tension Required (Table 1)

Bolt diameter

Minimum Tension

Recommended Torque

D

N

M

mm

KN N.m

12.7

53

136

15.9

84

271

19.0

125

481

22.2 173

773

25.4

226

1153

28.6

249

1437

31.7

317

2027

35.0

378

2658

38.1

459

3526

Alignment Inspection of Steel Structure

Adjustment of bracing

Adjustable diagonal bracing is fixed after all parts of the structure are in place. In bolted structures having diagonal bracing, wall bracings are adjusted after the columns are plumbed, and roof bracing are adjusted when rafters are in straight line.

Inspection of Roofing and Wall cladding

Check sequence of roof panels on roof.

Check correct starting- end position of roof and wall panels.

Check right screws using.

All screws must be perpendicular to panels, and rubber washer thickness must be from 1.00 to 1.20 mm.

Final Inspection of Steel Structure

Additional Resources for Steel Fabrication & Building Construction Works

Below is comprehensive list of additional tools and tackles that you may need for doing the steel structure construction works.

Heavy Duty Machinery

1

Portable Roll former

2

Portable Air Compressor

3

Seamer

4

Electric Hydraulic Engine Unit

5

Diesel Engine Unit

6

Uncoiler

7

Crimper
Tools & Instruments

1

Combination Wrench

2

Allen key Set

3

Strap Wrench 18″

4

Screw Driver

5

Adjustable Wrench 24″

6

Wrench

7

Sweeping Broom

8

Stapler for insulation

9

Mastic Gun (Silicon)

10

Goggles

11

Fire Extinguisher

12

Nibbler

13

Cutting Snip 10″

14

Hack Saw

15

C Clamps various size

16

Electric extension 50M

17

Screw Gun

18

Drill machine

19

Grinder (small)

20

Nylon Rope

21

Riveter (heavy duty)

22

Vernier Caliper (digital)

23

Vice Grip 8″

24

Utility Knife

25

Line Man’s Pliers 8″

26

Long Nose Pliers 6″

27

Side Cutter 8″

28

Digital tester (VOM)

29

First Aid Kit

30

Plastic tarpaulin cover 8mx10m

31

Plastic Gallon 20 litter

32

Feller Gauge mm

33

3 Claw Mechanical Puller small

34

Hydraulic Jack 20 tons

35

Level

36

Scow Bar 1m length

37

Electric soldering Iron 100 watts

38

Oiler

39

Ball Peen Hammer (medium)

40

Torch

41

Tape 8 meters

42

Tape 30 meters

43

Tape 5 meters
Supporting 

1

Scaffolding 1.5 meters

2

Bracing for scaffolding

3

Platform for scaffolding

4

Jack for scaffolding

5

Wheel for scaffolding

6

Spreader bar

7

Stair for scaffolding

8

Extension Cord (Cable 3×16+1×10)

9

Electrical box

10

Stand Conveyor

11

Roof Panel Carriage
Safety Gears

1

Safety Clothes

2

Universal Harness (1008833 size M)

3

Rope Lanyard 2m with G)

4

Safety rope (14mm Polyamide Rope)

5

Helmet

 