Internal Painting Method Statement

This method statement details general procedures to be followed for the internal painting work using paints from Berger at any kind of a project/building.

The procedure covers preparatory works, actual application and area cleaning associated with the painting works.

For Latex Emulsion Paint the sequence will be:

Surface Preparations -> PVA primer 1 Coat -> Stucco 2 Coats -> Durosan Paint 2 Coats

For Enamel Paint the sequence will be:

Surface Preparations -> PVA primer 1 Coat -> Stucco 2 Coats -> Bengalac Matt Paint 2 Coats

Before commencement of work, remove electrical switch and outlet plates, surface hardware, frames of lighting fixtures and all other obstructions. Replace properly at completion of the work.

Remove soiled and used rags, waste and empty containers from the building each night.

Take every precaution to prevent a fire.

Before commencement of the work, also ascertain the nature and location of all existing services on site by visual survey.

If any protection, rerouting, termination or removals of services are required for the smooth progressing of the painting work, it will be discussed and written approval will be obtained from consultant as appropriate.

Necessary Tools, Plant & Equipment

Material Requirements

The material shall be approved and shall be used as per the finishing schedule. The colour of the paint shall match the appropriate approved sample.

All the paint material shall be delivered in an unopened package and containers bearing manufacturer’s name & labels.

The labels shall include information regarding batch/stock no, date of manufacture & expiry date.

Painting materials must be kept in air conditioned place, protected from heat and direct sunlight. Containers must be kept tightly closed.

The paint storage room shall be a designated non-smoking area with sufficient fire extinguishers of the type fit for use on paints.

Preparation Before Painting

Clean floors and adjacent surfaces, as well as surfaces to be painted, before work is commenced. Cut out, as required, defects in drywall and plaster surfaces and openings adjoining trim, and fill with a patching compound or approved patching plaster flush with adjoining surface. When dry, smooth and-seal the patch before application of the priming coat.

Surface Preparation for Primer

The substrate must be sound, clean, dry, free from dust, oil, grease and laitance etc.

All traces of release agents must be removed.

On chalky and dusty surfaces, all loose material must be removed by stiff bristle brushing.

Mixing of ingredients

All Paints shall be thoroughly stirred before use.

No dilution of painting material is allowed unless approved by the consultant/Engineer.

Water can be used as a thinner/cleaner for all specified paints except for Bengalac matt.

For Bengalac matt enamel paint, maximum 5% of Jotun thinner no.2 can be used.

Application Of the Painting Works

Priming Works

Painting of Metal Work

Application of Latex Emulsion Paint

PVA Primer coat is applied with roller and allowed to dry for minimum four hour.

First coat of Stucco is applied after applying filling material and allowed to dry for a minimum period of 8 hours.

Then second coat is applied and allowed to dry for a period of 8 hours.

Average wet film thickness of the stucco shall be 195 µm.

Sanding is done to receive a smooth finish and remove the chalky dust.

First coat of Durosan is applied by roller and allowed to dry for a minimum period of 4 hrs.

Before applying the second coat imperfections will be further rectified with a touch up of Stucco and sanding.

Final coat of Durosan is then applied.

Average wet film thickness of the Durosan shall be 150 µm.

Application of Enamel Paint

PVA Primer coat is applied with roller and allowed to dry for minimum four hour.

First coat of Stucco is applied after applying filling material and allowed to dry for a minimum period of 8 hours.

Then second coat is applied and allowed to dry for a period of 8 hours.

Average wet film thickness of the stucco shall be 150 µm.

Sanding is done to receive a smooth finish and remove the chalky dust.

First coat of Bengalac Matt Paint is applied by roller and allowed to dry for a minimum period of 24 hrs.

Before applying the second coat imperfections will be further rectified with a touch up of Stucco and sanding.

Final coat of Bengalac Matt Paint is then applied.

Average wet film thickness of Bengalac Matt Paint shall be 75 µm.

Paint Drying Time

Drying times are related to air circulation, temperature, film thickness, and number of coats.

The figures given in the table are typical with:

Drying Time for PVA Primer

Substrate Temp

100 C

230 C

400 C

Surface dry

06 hrs

3 hrs

1 hrs

Through dry

10 hrs

5 hrs

3 hrs

Dry to recoat Minimum

08 hrs

4 hrs

2 hrs

Stucco Putty Drying Time

Substrate Temp

100 C

230 C

400 C

Surface dry

6 hrs

3 hrs

1 hrs

Through dry

16 hrs

8 hrs

6 hrs

Dry to recoat Minimum

16 hrs

8 hrs

6 hrs

Drying time for Durosan Paint

Substrate Temp

100 C

230 C

400 C

Surface dry

6 hrs

3 hrs

1 hrs

Through dry

12 hrs

6 hrs

2 hrs

Dry to recoat Minimum

6 hrs

4 hrs

2 hrs

Drying time for Enamel Paint

Substrate Temp

100 C

230 C 400 C
Surface dry

18 hrs

8 hrs

6 hrs

Through dry

48 hrs

24 hrs

18 hrs

Dry to recoat Minimum

48 hrs

24 hrs

18 hrs