MEP Project Execution Strategy & Methodology

Detailed programming of all MEP work activities will be prepared in full coordination with the main contractors programme. Builder’s works drawings will be prepared to show all openings sleeves and cast in items, Wherever necessary back up calculations will be prepared and submitted to Consultant. For specialist equipment a suitably qualified specialist subcontractor will be used.

Working Shop Drawings

Working drawings will be prepared for relevant items and equipment. They will be coordinated with other services and works. Working drawings will be prepared in accordance with the requirements of the contract and the statutory regulations by the local service authorities for electricity, water, drainage, telephone and civil defense. The working shop drawings will be submitted to the consultant for approval and also to the local authorities or service authorities where applicable. Relevant authorities will be kept informed about the methods of construction and their approval shall be obtained as necessary. Working drawings will be prepared well ahead of the related construction work to allow enough time for review and comment by the consultant, or service authority.

Material Submission & Approval

Materials of construction to be incorporated in the works will be submitted for approval in proper format approved by the consultant. Priority will be given to approval of materials. that are required for enabling works as well as chillers and transformers. Special attention will be given to storage of material during the course of the contact Covered areas will be used for products. Which need protection from sunlight and weather conditions. Dedicated construction teams with adequate supervisors will be allocated to the various designated areas based on CPM and available areas.

AIR CONDITIONING CONSTRUCTION STRATEGY 

DUCT FABRICATION

Ductwork work will be fabricated using a computerized design and fully equipped sheet metal manufacturing plant.  The following procedure will be used for the fabrication of the ductwork.

Ductwork Installation:

Ductwork will be delivered from the fabrication area when required in a coordinated manner as follow:

DUCTWORK INSULATION

After ducts have been satisfactorily tested for leakage, insulation work will be carried out.

ALUMINIUM CLADDING OF INSULATED DUCT AND PIPES.

Cut the aluminium sheets of specified thickness to make boxes of the required size.  Between the surfaces of the canvas cloth, wrap on top of the insulation with brush. Fit boxes of aluminum over insulated ducts and pipes. Rivet on longitudinal and transverse blots and further if required with waterproof sealants.

CHILLER WATER PIPE INSULATION

Ensure pipes of correct specified type with appropriate documentation and certification.

PLUMBING

During the foundation and concreting stage of the civil works, suitable approved sleeves will be provided in the beams, slabs and columns. The underground drainage work will be carried out simultaneously with the progress of the civil works. Proper slopes will be maintained and the pipeline will be checked for water tightness by subjecting the pipes to required pressure as given in the contract documents. All the drainage pipe work in the horizontal run will be supported.

 ELECTRICAL WORKS METHODOLOGY

The programme for the sequence and coordination electrical and construction work activity will be based on the main activities shown below

Electrical Activities

The installation of electrical equipment can be briefly summarized as under to be followed by electrical engineering team:

COMMISSIONING STRATEGY