Site icon Method Statement HQ

Method Statement for Installation Of Air Handling Unit AHU & FAHU

Below is the brief method of statement for the installation and testing of air handling units i.e. AHU & FAHU.

On this page you can see three major sections which are:

Other parts should be included for preparation of professional method statements for approval purposes etc.

Other sections may include Purpose, Scope, Responsibilities, Standards, references and attachments etc.

Required Tools For AHU Installation

Preparation & AHU Pre Installation Requirements

Installation of Air Handling Units AHU & FAHU

Shift the AHUs/FAHUs to the place of installation in safe manner using fork lift and crane as applicable.

Ensure that the correct AHU is shifted to the place of installation.

Air inlet, outlet, fresh air connection and chilled water connection orientation are as per approved drawings.

If the Air Handling Units are shipped in multiple sections, the AHUs will be assembled strictly as per the manufacturer’s instructions, and also consider:

The AHUs/FAHUs are placed correctly on foundation with vibration isolator rubber pads at right location.

Identify the correct sections that are to be bolted together.

Position fan section on housekeeping pad.

Install gaskets at all bolted joints that are required to be joined.

Position the next section, to be joined, carefully on housekeeping pad, align the two sections.

Jointing brackets will then be used to externally join the sections together.

Air Handling Unit shall be inspected again for any damage during hoisting/shifting.

Upon satisfactory positioning of AHUs/FAHUs any open air/water outlets of AHUs/FAHUs shall be closed properly and area shall be cleaned, complete protection in areas where other trades are working.

Units will be carefully plumbed and aligned by use of blocks and shims, then fully bolted and securely anchored to “Housekeeping” pad.

After alignment is completed supervisor in charge will ensure that vibration isolators are of the correct deflection.  Final calibration will be made at pre-commissioning stage.

Air, Chilled water, Electrical and Condensate Drain Connections

Inspection Of Air Handling Unit AHU Installation

All construction/inspection/testing works shall be carried out in accordance with specifications. Work shall be carried out by the site MEP staff under the guidance of respective engineer and shall further be checked and approved by quality engineer.

An inspection request for the AHUs/FAHUs installation shall be submitted at least 1-2 days prior to the client/consultant or as agreed.

Heat recovery testing will be done to ensure smooth operation

Check the unit model number and relevant accessories are available. Unit name plate as per order.

Verify the construction of the house keeping base is as per the specification & drawing for floor mounted AHU.

Verify the presence of approved vibration isolators, installed before the installation of AHU. Check anti-vibration mountings are located correctly.

Service space around the unit as per manufacturer requirement.

Check the duct is connected to AHU with proper flexible connections

Check fan moves freely.

Check the level of the AHU and verify the minimum slope as per drawing in the direction of condensate pipe. Check the drain connection with U trap.

Check filters are provided as per specification.

Verify the electrical connection of AHU with control panel as per construction drawing.

Check and verify all Installation as per approved drawings

After installation inspect the AHU for physical internal and external damages.

Verify the absence of any vibration in AHU and its inner like fan, motor and coils etc.

Verify the process pipe connection with AHU along with valves, accessories and flow switch etc.

Confirm the additional adequate support for all fittings and valves near AHU as per construction drawings.

Verify the installation of 2-way modulating & gate valve of approved brand and quality as per approved material submittals.

Verify the presence of identification labels, safety and warning signs at their positions as per approved materials.

Exit mobile version