Method Statement for Installation Of Air Handling Unit AHU & FAHU

Below is the brief method of statement for the installation of air handling unit which is applicable for both AHU & FAHU installation.

On this page we have given in detail only one section of overall method statement that covers mainly installation and inspection part.

Complete method statement shall include other sections as well as per the standard method statement template approved for a project i.e. Purpose, Scope, Responsibilities, Standards, references and attachments etc.

Other parts should be included for preparation of professional method statements for approval purposes etc.

Below is list of necessary tools for AHU installation:

Preparation & AHU Pre Installation Requirements

Equipment schedule must be checked for correct location and reference for the Air Handling Unit.

Check civil completion of AHU foundation and ensure it is as per approved drawings and released by civil contractor.

Check the area around the foundation and ensure sufficient space is available around the AHU / FAHU from all sides as applicable i.e. for maintenance purpose.

Ensure availability of sufficient slope to the drain pipe, for easy draining of condensate drain.

Place anti vibration ribbed rubber pads of correct thickness as per approved drawings/submittals.

In case of multiple rubber pads the pads shall be placed one above the other, with the ribs at right angle to each other.

Prior to the commencement of any works access and installation areas will be inspected to confirm they are in suitable condition for installation works.

Make sure “Housekeeping” pads or pertinent structure are complete and leveled.

Temporary protection must be provided to protect the openings during installation and until the final chilled water pipe, ducts and electrical connections are made to the Air Handling Units

Installation of Air Handling Units AHU & FAHU

Shift the AHU / FAHU to the place of installation in safe manner using fork lift and crane as applicable.

Ensure that the correct AHU is shifted to the place of installation as per schedule of installation.

Make sure that air inlet, outlet, fresh air connection and chilled water connection orientation are as per approved drawings.

If the Air Handling Unit AHU are shipped in multiple sections, the AHU will be assembled strictly as per the manufacturer’s instructions, and also consider following:

Air Handling Unit AHU shall be inspected again for any damage during hoisting/shifting.

Upon satisfactory positioning of AHU / FAHU any open air/water outlets of AHU/FAHU shall be closed properly and area shall be cleaned, complete protection in areas where other trades are working shall be provided.

Units will be carefully plumbed and aligned by use of blocks and shims, then fully bolted and securely anchored to “Housekeeping” pads.

After alignment is completed supervisor in charge will ensure that vibration isolators are having correct deflection.

Final calibration will be made at pre-commissioning stage.

Air, Chilled water, Electrical and Condensate Drain Connections

Ducting connection shall be done as per approved shop drawings.

Provide flexible duct connections as applicable/as approved submittal.

Provide proper supports as per approved drawings.

Chilled water connections shall be made as per approved drawings.

Ensure supply and return connection is made properly.

Provide pipe flexible connection and other piping accessories as per approved drawings and submittals.

The piping shall be free of any strain and shall not exert any load on AHU/FAHU.

Install the control valves, strainer, commissioning set correctly as per direction of flow as per approved drawings and project technical specification.

Ensure proper operation of valve handles and sufficient space for valve installation.

Electrical power connections shall be done as per approved drawings and schematic diagrams.

Condensate drain piping shall be terminated at the nearest floor drain.

Provide the U’ trap in the condensate drain piping and ensure the provision for cleaning ofU’ traps, also ensure proper slope to enable easy drainage of condensate water.

Chilled water piping connections to AHU/FAHU shall be pressure tested to 1.5 times the working pressures. Coils not included in test.

Strainer shall be cleaned after pressure testing and initial flushing of chilled water piping system.

Flow test of the AHUs drain tray should be done for condensate drain pipe and ensure water is drained out completely.

Inspection of Air Handling Unit AHU Installation

All construction/inspection/testing works shall be carried out in accordance with project specifications.

All the ahu installation work shall be carried out by the site MEP staff under the guidance of respective engineer and shall further be checked and approved by quality engineer.

An inspection request for the FAHU / AHU installation shall be submitted at least 1-2 days prior to the client/consultant or as agreed.

Heat recovery testing will be done to ensure smooth operation as per approved procedures.

Check the unit model number and relevant details are available, i.e. unit name plate is as per order.

Verify the construction of the house keeping base is as per the specification & drawing for floor mounted AHU.

Verify the presence of approved vibration isolators, installed before the installation of AHU. Check anti-vibration mountings are located correctly.

Service space around the unit as per manufacturer requirement.

Check the duct is connected to AHU with proper flexible connections

Check fan moves freely.

Check the level of the AHU and verify the minimum slope as per drawing in the direction of condensate pipe. Check the drain connection with U trap.

Check filters are provided as per specification.

Verify the electrical connection of AHU with control panel as per construction drawing.

Check and verify all ahu installation is as per approved drawings

Before and after installation inspect the AHU for physical internal and external damages.

Verify the absence of any vibration in AHU and its inner components like fan, motor and coils etc.

Verify the process pipe connection with AHU along with valves, accessories and flow switch etc.

Confirm the additional adequate support for all fittings and valves near AHU as per construction drawings.

Verify the installation of 2-way modulating & gate valve of approved brand and quality as per approved material submittals.

Verify the presence of identification labels, safety and warning signs at their positions as per approved material submittals.