The aim of this Method Statement is to provide and maintain effective quality control procedures and to execute the work in compliance to standard and good practice at all stages during the execution of Epoxy Painting Works at project site.

The equipment/tools involved in painting works are listed below.

Surface Preparation

The substrate must be sound, clean, dry, free from dust, oil, grease and laitance etc from well cured and dry concrete / plaster surface, manually with rubbing stone, scrapper and sand paper etc.

Grinding:

Disc or stone grinder shall be used. Whichever surface preparation method is employed, ensure that the laitance (powdery material on the on the concrete surface) and loose particles are removed from the concrete surface. Also see that the surface smoothness of the power floated concrete surface is removed and a light surface profile is created to allow proper adhesion of the coating to the concrete surface.

Control Joints:

Saw-cut or hand edged trowel tooled control joints where indicated on drawings shall be provided or as designated by the Company.

The joints shall be cleaned, filled with grout mix and strike off flush with surface of floor.

 Cracks Repairing:

Where cracks occur in substrates and prior to the laying of finish materials the cracks shall rout out, grind level as necessary, and fill flush with approved material/grout.

After the surface preparation is complete, remove all the dust formed on the surface using an industrial vacuum machine. Vacuum cleaning is also recommended before the start of each of the coat.

Application of Primer Coat

Application of Jotafloor Coating

Jotafloor Non Slip Aggregate

Application of Jotafloor Coating:

Cleaning and Protection: