Site icon Method Statement HQ

Method Statement For Scaffolding, Formwork, Rebar Fixing & Concreting Footing / Pedestals / Pile Caps

This method statement covers the detailed procedure to be followed for the scaffolding, formwork, rebar fixing and concreting operation of footing, pedestals and pile caps, also to explain how footing, pile caps, trenches, grade beam and grade slab work shall be carried out under controlled conditions.

Tools Required For the Work

DOWNLOAD METHOD STATEMENT FOR FORM WORK WITH ITP & CHECKLIST

Method Statement For Formwork, Rebar Fixing & Concreting Footing / Pedestals / Pile Caps

Water Proofing Works

Reinforcement Works

Isolation and Expansion Joint Works

DOWNLOAD METHOD STATEMENT FOR FORM WORK WITH ITP & CHECKLIST

Form works

Concrete Placement

Removal of Shuttering

Curing

Concrete have to be cured by sweet water. All the surface of foundations will be covered by wet Hessian cloth to maintain this.

DOWNLOAD METHOD STATEMENT FOR FORM WORK WITH ITP & CHECKLIST