Site icon Method Statement HQ

Method Statement & Risk Assessment for Demolishing and Removal of Fence and Shelters

Demolition-Method-Statement

The purpose of this method statement is to illustrate how the existing fence and shelters will be removed from site in proper and safe way.

The scope of this method of statement is to cover the demolishing methodology of the following:

Plant and Equipment

Following is list of the equipment and tools which will be used while demolishing the items mentioned in BOQ as follow:

Materials

All materials which will be extracted from the demolishing process will be sent to the designated landfill area and here is the summery of some of it:

Site Planning & Preparation

Project Details:

Project Name :
Project No:
Project Location :

 Contact Details of Person Responsible for Project:

Name :
Position:
Contact Details:

Contact Persons in/charge of Site

Name :
Position :
Contact Details:

Construction Stage Works of Demolish:

1. Demolish of the chain link fence:
2. Demolish of the road guard rail
3. Removal of electrical lighting poles
4. Demolish of the over side drain

Work Methodology

Demolish of the chain link fence:

Demolish of the road guard rail:

Removal of electrical lighting poles:

Demolish of the over side drain:

 Organisation, Responsibility & Supervision

Project Manager/Construction Manager it will be the responsibility of the project manager to ensure that all involved personnel are familiar with the requirements and implementation of this procedures as applicable to the construction activates. He shall be coordinating with QA/QC at the required stage of the work by issuing an in-house inspection request to check & inspect the work and to notify Royal Commission by RFI for Witnessing or release of Hold Points.

Quality Control Manager Responsible of the overall discipline of the QA/QC inspection, verification of the Project Specification, Documentation and QC records for final acceptance.

HSE Manager Responsible for Safety implementation and ensuring all safety requirements has been implemented within the construction areas.

Superintendent/Supervisor ensure compliance by all labours and equipment, operators and other associated craftsmen’s during demolition works to the requirement of this procedure, project control procedures and test plan, relevant drawings, safety procedures and Royal Commission Standard Section:02220 Guideline Specification for Site Demolition secure all necessary Demolition/confined space and Permits.

Quality Control Engineer Monitor Daily activates and verify compliance with Royal Commission Specification and IFC drawings, ensure that activities are conducted in accordance with ITP Demolition works.

Safety Officer ensure all permits are available prior to commencement of any work. Ensure that all works are carried out in a very safe manner, they will identify any unsafe working condition and immediately rectify the situation, and issue warning for unsafe act of workers, keep close coordination with Royal Commission HSE Engineer for implementation of Safety Procedures. Report all Incidents to Royal Commission HSE Engineer.

Store Keeper responsibility is to identify the location and maintain preservation of the materials or equipment at the storage area and keeping the record and control all the materials/equipment that released.

HEALTH SAFETY AND ENVIRONMENT RISK ASSESSMENT

ITEM JOB STEPS POTENTIAL HAZARD (s) EXPOSED HARM Initial Risk Level MITIGATION CONTROL Remaining Risk Level Responsible Person
S P RR S P RR
1 Access and egress to the work area Slip, Trip and fall.

Hand and Eye Injury

Personnel Injury 3 3 9 M
  • Maintain Good housekeeping.
  • Always wear proper PPE.
  • Always use designated access point.
  • Avoid Short Cut.
1 2 2 L Site Engineer
2 Communication
  • Lack of communication.
  • Failure to effectively communicate with the operator of the crane or emergency services.
  • Uncontrolled or unplanned movement of the load
  • Striking person or plant.
Property Damage and Personnel Injury 3 3 9 M
  • Only the designated banks man shall be provide signals to the crane operator.
  • Handset radios shall be used for communication to emergency services.
  • Above 85dcb, hearing protection required
1 2 2 L
 

 

 

 

3

WORKING ON UNEVEN SURFACES Tripping, slipping hazard Possibility personnel injury. 3 3 9 M
  • Receive a valid permit before starting the job.
  • Proper footwear. Stay alert to change in terrain.
  • Do not overload yourself with what you carry.
  • Slowdown, ensure proper footing.
  • If climbing staircases to tanks, use 3 pts of contact at all times.
  • Watch footing on surfaces containing animal droppings.
1 2 2 L
 

4

 

 

WORKING FROM AND AROUND VEHICLES Blind spot, hit by equipment. Possibility personnel injury. 3 3 9 M
  • Be careful in entering and exiting in high winds.
  • Proper use of parking brake.
  • Maintain vehicle brakes
  • Do not lean equipment against truck or place equipment.
  • Under wheel line of travel.
  • Do not park near utility appurtenances.
  • Perform safety circle walk around to prevent running over utility.
  • Appurtenances (phone pads, valve sets, and anchors).
1 2 2 L
  5 Transportation of materials and equipment at work site. Traffic accident / incident, Falling objects, Fire hazards

 

 

Personnel injury

Fatality

Property damage

 

4 3 12 H
  • Follow road speed limits
  • Equipment properly secured
  • Fire extinguisher available
  • Operator should possess a valid Saudi driving / operator license
  • Assign banks man to guide/ signal heavy equipment from maneuvering.
  • Hand tools shall be in good condition
  • Vehicle compliance for off-road conditions
1 3 3 L
 

 

 

 

 

 

 

 

 

 

 

 

6

Excavation By Equipment and Hand Tools.
  • Hitting existing underground facilities.
  • Collapse or cave in of soils.
  • Falling of equipment’s or workers inside.
  • Noise.
  • Physical Hazard
  • Soil contamination
  • Ground Disturbance
  • Underground facilities
  • Insufficient side slope
Personnel injury,

Property damage and Fatality

4 4 16 H
  • A Valid work permit on site.
  • Before starting job, conduct Tool Box Talk.
  • Use cable detector to identify existing buried facilities at the beginning of excavation and at the bottom of each slit trench.
  • Area Barricaded with Hard and Deep excavation signboard shall be posted.
  • Excavated pit shall be inspected before the work begins and at start of each shift.
  • Maintain at least 1M wide clear space around the edge of excavation to the barriers, to prevent falling of objects on to the persons digging the pit.
  • Ladder to be installed for access & egress. Proper access to the ladder shall be provided & maintained.
  • A standby vehicle with required first aid kit shall be present near worksite at all times.
  • Strictly need to control any Movement of equipment’s near excavation.
  • The Equipment operator must have a valid third party (TUV) certificate.
  • Reverse alarm and light shall be operative.
  • Provision of inspected, color coded and properly grounded generator, color coded electrical cables and putting fire extinguisher in place.
  • Bobcat shall be inspected by third party (TUV) and the operator shall have a valid third party certificate (TUV), reverse alarm and light shall be operative.
  • The personnel shall use hearing protection equipment when needed.
  • Ensure proper shoring and/or sloping for depths more than 1.8 meters.
  • Appropriate PPE shall  be with  proper hand tools
  • Manual Excavation Use only hand shovels.
  • Excavation Approval shall be attached on the permit.
  • Provide fire extinguishers.
  • Deep excavation sign board shall be posted.
  • Adequate number of sun shelters shall be provided at site During Hot Season.
1 2 2 L
 

 

7

Backfilling
  • Dust
  • Uneven ground
  • Poor house keeping
Personnel Injury,Propert damage 2 3 6 M
  • Maintain Daily Based good housekeeping
  • Spray water to reduce dust & Use of certified equipment only.
  • The equipment (Excavator, jcb, Dump truck) shall  be inspected
1 2 2 L
Compaction
  • Noise.
  • Ground Disturbance.
  • Improper access/ egress.
2 3 6 M
  • The personnel shall use hearing protection equipment when needed.
  • Provide proper Access \Egress
  • Unnecessary material must remove from the ground
1 2 2 L
  8 Dismantling and Re-installation of Fence /Guard rail
  • Trips and fall.
  • Hand and Eye Injury.
  • Pinch Points.
  • Failure of lifting equipment.
  • Equipment may hit or damage existing structure or property during dismantling.
Personnel injury,

Property Damage and Fatality

4 3 12 H
  • Allow only skilled and trained personnel to execute the work.
  • Keep away from line of fire.
  • Use appropriate PPE.
  • Observe correct usage of power tools.
  • Inspect tools regularly.
  • Never stand under the suspended load.
1 2 2 L
  9 Material handling(manual lifting\lowering of material )
  • Back due to manual material handling
  • Individual capability
  • Poor lighting conditions
  • Inadequate space
  • Tripping \slipping
  • Improper lifting load beyond the capacity of the individual
  • Improper lifting techniques
  • Lack of training instruction & supervision
  • Slippery surface\overcrowded place
  • Improper housekeeping
Personnel Injury, Property Damage 3 3 9 M
  • Whenever practicable, mechanical lifting aids eg.crane, forklifts ,trucks etc., shall be used to alleviate the requirement for manual handling
  • Supervision will assess weight, center of gravity etc. and determine the number of persons required to carry out the work safely
  • Personnel shall be trained in manual handling techniques
  • Avoid manual load lifting if possible if not the check and ensure that the load is below the recognized permissible limit
  • Workers fit for the activity shall be engaged
  • Area shall be illuminated with adequate lighting
  • Good housekeeping standards shall be maintained at all times   to avoid slip ,trips and fall
  • Train the staff for good posture
  • Use slip resistance shoe with toe protection and hand gloves with sufficient sip to avoid insecure hold
1 2 2 L
10 Working at Height
  • Lack of adequate lighting
  • Reptile movements
  • Poor concentration
  • Work Pressure
  • Human Error
  • Poor eye vision at night
  • Sleepiness
  • Fatigue
  • Lack of training
Property Damage,  personnel( injury and Fatality) 4 4 16 H
  • Ensure 100% tie off during working at elevated area.
  • Working areas must barricade with warning tape.
  • Reflective vest to be provided for all members of the crew.
  • Ambulance with first aid kit and Doctor/Nurse to be available at all times during the night.
  • Ensure constant supervision.
  • Emergency Contact Numbers posted the entire site Locations.
  • Wear appropriate PPE
  • Proper training
1 2 2 L
 11 Lifting and Rigging Failure of rigging gear and equipment Personnel injury, Property Damage 2 3 6 H Conduct daily inspection of equipment and rigging gear before each use. 1 2 2 L
12 Working at extry Heat stress workers 3 3 9 M Provide rest shelter and cold drinking water for workers 1 2 2 L

 

PROBABILITY  (P) SEVERITY  

 

 

 

 

 

Risk Rating = Probability x Severity SEVERITY
1 Unlikely 1 First Aid or slight injury 1 2 3 4 5
2 Rare 2 Recordable, medical and restricted work Probability (P) 1 1 – Low 2 – Low 3 Low 4 – Low 5 – Med
3 Possible 3 Lost time injury or permanent disability 2 2 – Low 4 – Low 6 – Medium 8 – Medium 10 – High
4 Likely 4 Single fatality or permanent disablity of 3 or more person 3 3 Low 6 – Medium 9 – Medium 12 – High 15 – High
5 Very Likely 5 multiple fatalities 4 4 – Low 8 – Medium 12 – High 16 – High 20- High
5 5 – Medium 10 – High 15 – High 20- High 25 – High

Environmental Safety & Health Contractor Requirements

It is required to provide and designate an area where we can through the extracted and waste materials.

Protective & Safety Equipment

All people who involved in these activities must wear their PPE as per standard such as:

Emergency Procedures

In case of emergency the following procedures should be follow:

Permit requirements

ENVIRONMENTAL ISSUES

ENVIRONMENTAL REGULATIONS

Pollution Control

Fuel Tanks

Spill Response Plan

QUALITY ASSURANCE

Contractual Requirements

Quality Assurance shall be provided to ensure that materials, Construction and Workmanship are in compliance with the plans and specification and applicable requirements of the standard and codes mentioned in Method Statement.  

Critical Works

CONFIRMATION OF INSTRUCTIONS TO OPERATIVES

Those names listed below confirm receipt of the method statement and have had the contents explained to them/understand it and are aware of the site ES&H requirements.
Name Employer Date Signature
       
       
       
       
       
       
       
       
       
       
       
       
       
       
Note to contractor supervisor – Any significant change from this method statement requires it to be revised and resubmitted before work can commence.

 

Exit mobile version