Site icon Method Statement HQ

Method Statement for GI & PVC Conduit Installation Including Accessories

Below is a comprehensive method statement for GI and PVC conduit installation which can be used for purpose of any project and it can be approved easily by consultants because it covers all aspects of a standard conduit installation method.

We have also given the download link for method statement for GI and PVC conduit installation which will help you to easily modify the word and excel files that also include ITP, inspection checklists and risk assessment etc.

1. Purpose

This document describes the method statement for conduit installation which includes GI & PVC conduits and accessories for any kind of the construction project.

Procedure will ensure that all concerned persons are familiar with the sequence of activities, utilization of resources, and execution of the works in compliance with applicable project safety and quality procedural requirements, project legal documents and specifications.

2. Scope of Works for Installation of GI Conduits

This method statement is intended to outline the activities and the methods used for the installation of electrical conduits and accessories.

Installation activities will be carried out in accordance with the contract details and in full compliance to the contract specifications and documents.

All work within the rights-of-way of the standards and specifications will be done in compliance with requirements issued by authorities.

3. Legislation and Code of Practice

All related codes and standards referenced in the project electrical specifications.

4. Reference

5. Definitions

GI: Galvanized Iron

PVC: Polyvinylchloride

ITP: Inspection and Test Plan

6. Resources

6.1. Equipment / Tools: Following tools shall be arranged for the site construction works.

6.2 Safety of Equipment’s

Necessary measures will be taken for the safety of the equipment and any other works affected by the works covered in this document.

Relevant entities which might require protection include any such works in the vicinity of the area of work or on the service access or discharge path.

The construction team will ensure that any such requirements are documented.

 7. Health, Safety & the Environment

The hazards identified in the risk assessment will be controlled under the overall Project Safety Plan which is a separate document communicated to all parties on the project.

Personal Protective Equipment

The works covered under this document require that the PPE must be used as required.

Safety Training and Emergency procedures

Before commencing any conduit installation work, all employees will attend a site safety induction training to ensure all safety measures are understood and implemented and to cover specific procedures in case of emergency.

If necessary, practical training exercises will be conducted on escape routes, signage, evacuation and rescue etc.

First Aid

Prior to the commencement of work, arrangements will be made for medical facilities and medical personnel to be available from prompt attention to the injured person.

The contractor’s vehicle assigned to the job site will be used for transporting the injured person to the first aid station and to the nearest hospital when required.

8. Methods for GI & PVC Conduit Installation

General Procedure for conduit installation is given below after which area wise details are provided like method statement for conduit installation in slab, walls and exposed areas etc.

Steps for exposed GI conduit installation on walls & ceilings etc.

Step 1: Take the following drawings approved for construction.

Step 2: Procedure for GI Conduit Installation

Check the route of GI conduiting to make sure that it is free from debris and obstruction of any other activity.

Arrange scaffolding of sufficient height which is checked by scaffolding inspector/ safety officer before using the same for installation.

Mark the reference points on wall/ column as per civil architectural drawing.

Identify the circuit start point and end points to mark the conduit route as per approved drawings.

Make hole in wall/concrete using drill machine for rawal plug, fix rawal plug inside hole and then fix base of saddle by screw at every 2 meter span.

Use recommended and approved GI conduiting & bends as per site condition and drawing. Remove sharp edge of cut length of conduit by filing.

Install conduits and all accessories as per approved shop drawing and tight with saddle and screw, make joints using threaded fittings.

Installation of GI conduits shall be checked by internal quality engineer as per drawings and quality of installation before offering consultant/client for inspection.

Conduits are not to cross pipe shafts, vents or opening.

Additional threaded cuts on GI conduits are to be painted with zinc based coating resistant to corrosion.

Approved clamps to be used for the supports.

Maximum spacing of supports for different conduit sizes to be clarified.

Conduits on walls are to be run neatly, horizontally or vertically.

Conduits are to be used for exposed installations over false ceilings when the false ceiling is used as return plenum.

Conduits is to be used for all installation in elevator machine room and shafts, electrical equipment rooms, parking floor, solid waste rooms, etc.

All works on site will be as per electrical specifications and as per applicable electrical wiring regulations.

The risk assessment mentioning necessary control measures shall be attached to this method statement to follow and implement the requirements

Method Statement for PVC Conduit Installation In Concrete Slab

Following tools should be arranged before starting the job.

PVC Conduit Installation Steps in Slab

Method statement for conduit installation (GI Box & GI/PVC Conduit in Walls)

Following tools should be arranged before starting the job.

Method Statement for Conduit Installation inside the Wall – PVC

Quality Inspection and Testing

The work area shall be maintained neat and tidy as reasonably practical at all times.

 Executed works in areas where other works are still being carried out shall be protected as per the contract requirements.

 In accordance with the project quality plan, necessary records will be maintained as documentary evidence of the establishment of this electrical method statement.

All the in process works shall be monitored for quality of workmanship and installation against approved shop drawings by the relevant supervisor.

Installation works shall be inspected for conformance to project electrical specifications.

The inspection formats shall be used in accordance with the requirements of the main contractor.

An inspection request for the PVC & GI conduits and boxes shall be submitted one day prior to the consultant.

Attachments

Exit mobile version