Site icon Method Statement HQ

Gypsum Board Suspended Ceiling Installation Method Statement

Below is best method statement for gypsum board ceiling that can be useful for any kind of project submission and site works.

The purpose of this ceiling method statement is to ensure that the Gypsum Board Suspended Ceiling and related activities are executed safely, in accordance with the contract requirements and that all quality assurance / control activities are conducted in a systematic manner.

Also to ensure that false ceiling works are inspected, conformance is verified and documented.

Scope of this procedure covers the installation of any kind of gypsum board suspended ceiling as per approved shop drawings.

Roles and Responsibilities

Project Manager shall be responsible for the overall implementation of this procedure for suspended ceiling works, ensuring the works described in this method of statement are conducted to required codes, standards and best practices in conformance with approved drawings and specifications.

Site Engineer along with Surveyor / Foreman will ensure that the ceiling works are carried out in accordance with the specifications, approved drawings and in accordance with this method statement

QA/QC Engineer shall ensure that the works are carried out in accordance with the project’s quality requirements. He shall be also be responsible for the implementation of related QA/QC inspection works as detailed and as required in this procedure

HSE Inspector / Safety Officer shall ensure implementation of all safety procedures and regulations as per project HSE Plan and also in accordance with the safety plan set by main contractor. He shall conduct necessary and recommended trainings and tool box talks on the hazards, dangers and controls before commencement of works. He shall observe and ensure that all local legal occupational health and safety regulations are complied with.

Sustainability Manager: shall oversee the Environmental & Sustainability controls and measures of the installation process. Construction practices shall be in conformance with project CEMP, the manufacturer’s standards and to the satisfaction of the projects Environmental Managers.

Necessary Tools & Equipment

Below is the list of necessary tools and equipment needed for performing the suspended ceiling works:

The capacity / size of the above equipment shall be judged in accordance with site conditions, requirements, and availability at the time of execution.

All the above tools or equipment will be operated by skilled labors, and will be checked and maintained regularly by supervisors.

Health and Safety Requirements

Suspended Ceiling Installation Procedure

Before start of suspended ceiling works the following works need to be completed and assessed by the QAQC engineer from all concerned parties.

Before starting of the first fix services of false ceiling clearance will be obtained from the contractor, consultant and MEP sub contractor as the first fix services of M.E.P above the false ceiling to be
completed and approved.

An area for mock up will be prepared for inspection and approval before proceeding with the overall installation.

QAQC procedures shall be followed, WIR shall be raised, inspections shall be carried out at different work tiers and clearances shall be obtained at progressive levels as mentioned therein.

Fixing of Suspension Grid

 Fixing of Gypsum Board:

Before starting of the Gypsum Board fixing services of false ceiling clearance will be obtained by the
contractor, consultant and M.E.P sub contractor, services of M.E.P above the false ceiling to be completed and approved as well inspection of the suspension frame of false ceilings should be carried out by the consultant and should be rectified to comments if given by them.

Finishing of Gypsum Board

Before start of the finish works including filler and paint, services of false ceiling marking will be made by M.E.P sub contractor as per approved shop drawings for all the electrical points, A/C supply and return air diffuser position, sprinkler points and position of access panel as per approved coordinated drawings and inspection by the consultant and contractor to be obtained for final approval of cutting, gypsum boards shall be cut mechanically

Refer Technical Data Sheets for finishing materials application, manufacturers recommended application standards shall be followed.

Sustainability and Environmental Measures

The materials in the installation include gypsum plaster board on a GI channels for the supporting grid, paint and primer coat finish.

Special care needs to be taken in the storing and use of Gypsum Boards considering the humidity and temperature. Ideally to be stored in air-conditioned environment, in the absence of which the material needs to be covered by a tarpaulin at all times.

Considering the fragility of the material especially around its edges, care should be taken in handling and storage so as to avoid impacts on the edges.

 Energy use will mostly be mostly limited to hand tools (drills, cutting machines etc.), with material handling and waste management forming the major concerns for environmental control.

The paints are preapproved and fall within an acceptable VOC limit, painting works shall conform to the product’s technical data sheet.

As standard practice the following environmental friendly precautionary measures shall be taken, while conducting the work as described in this statement, workers shall be trained and/ or allocated for conducting the same as necessitated:

ACCESS & EGRESS

To maintain proper access and egress, sufficient ladders are to be provided for safe work. The work shall be executed as per approved Methods statement & Shop drawings. Housekeeping on daily basis.

ATTACHMENTS

Exit mobile version