Method Statement For Installation of Control Valves & Actuators for HVAC System

Purpose & Scope

Set out a clear and defined method of ensuring that the correct control valve is selected and installed in the correct position in the HVAC system. In addition a method is also set out which will ensure that the correct actuators for each specific control valve assembly are also correctly selected and installed.

This Procedure is to define the method that will be used to ensure that the correct selection and installation of all control valves and control valve assemblies are correct, acceptable and conforms to the contract documents and specifications.

Method Statement for Installation of Control Valves and Actuators

Below procedure will be followed to ensure that no mistake is made at installation stage with regard to the correct selection, positioning and installation of all the control valves and actuators assembly.

L –   indicating “ Low Flow”

M – indicating “ Medium Flow”

No imprint – indicating “ standard Flow”

When the correct valves , test points, vents and drain points have been identified for a specific control valve assembly.These will be tagged and stored ready for installation stage.Their tag numbers will be identified on contractors drawings, and commissioning valve schedule.

Installation of actuators (where applicable) will be in conformance to manufacturer’s recommendation.

Inspection

After site installation assembly of the control valve a final inspection will be made prior to pre-commissioning, in accordance with approved system Commissioning Valve Schedule and then tagged.

The above procedure will eliminate confusion and allow ease of installation and trouble free commissioning of control valves and actuators.