Site icon Method Statement HQ

Electrical Method Of Statement For Installation & Termination of Cables and Wires

This method statement for electrical work shall help you understand the requirements before and during the cable s and wires pulling process. The document is very helpful for MEP QA/QC engineers to develop the professional electrical method statement for their project.

Below is the list of equipment / Tools required for installation of cables and wires, which can be used for different projects after doing the customization as per the project requirements.

Installation Of Wires & Cables

TRAINING QUALIFICATIONS OF PERSONNEL

INSPECTION & STORAGE OF MATERIALS

Pre Installation Requirements for Cables and Wires

Wires Pulling Method

Cable Pulling & Termination

Transport and place the cable drums as per drum schedule and at the locations where space is available for working. The cable drum shall be placed on a jack & spindle arrangement to ensure free rotation of the drum. Erect scaffolding where required as per the site requirements.

Cable rollers shall be placed under the cable during pulling over longer distances and standoff rollers for acute bends, to ensure that the cable is pulled with minimum effort and the cable outer jacket is free of scouring lines. The cable shall be pulled by using pulling means such as fish tape, rope and basket weave wire/cable grips so as not to damage cable or its containment system. Care will be taken to ensure that the maximum pulling tension of all the cables is not exceeded at any time.

Cable should be free of any static load i.e. to be places side by side parallel on the cable tray or ladders. Any kind of dead weight on the cable shall be avoided. At all times the cable schedule & section drawings for the relevant area will be referred to ensure proper location of cable on the required ladder and to ensure compliance with project specifications.

A pulling compound / lubricant shall be used where necessary as per site conditions i.e. in slabs and underground conduits etc, the lubricant should not deteriorate the cable insulation. The cables shall be secured to the containment system using approved cable ties for horizontal runs and cable cleats for vertical runs. All control cables will be installed at a minimum distance of 100mm from power cables unless otherwise agreed with consultant as per site conditions.

Earth (green/yellow) cables shall also be pulled along the power cables. At all time of pulling, mark both power and earth cables for pairing them on both sides of connection i.e. at sending and receiving ends. Before termination complete length and route of the cable shall be inspected by QA/QC engineer , after which a WIR shall be raised for consultant approval. Cable shall be caped and sealed on both ends after installation until termination is done.

Termination shall be done by using the approved termination materials that include glands, lugs and other accessories part of termination kit, by using proper crimping tools. Matching colour gland sheaths shall be provided. All termination shall be provided with tight fitting covering sleeves.

Insulation Resistance Test: Set the Meggar meter to 1000 volts DC for cables and 500 volts DC for wires. Take reading between phase, phase and neutral, phase and earth neutral and earth. Note that resistance reading must not exceed 2 mega-ohms (MΩ). Check and record the resistance readings as per specification on the approved insulation resistance test forms.

Cables Identifications

Alternative Procedure no: 1 for cables and wires installation and termination

Storage of Materials at Site

All materials received at site shall be inspected and ensured that the materials are as per approved material submittal. Any discrepancies, damages etc.shall be notified and reported for further action. Material found not suitable for the project are removed from site immediately.

Cables are stored with the factory packing on the flat surface with stoppers to prevent drums rolling, as demonstrated on the attachment. Protection shall be provided from direct sunlight. Wires shall be sorted and stored size-wise for easy retrieval. Wires shall be stored in covered and ventilated place.

Installation Procedure for Cables

Installation of Cables & Wires Procedure

Exit mobile version