Testing & Commissioning Of Pressurization Unit – Chilled Water

1. Purpose

The purpose of this procedure is to define the step by step method to implement the correct practices for the pre-commissioning & commissioning of Pressurization Unit through the guidelines contained herein so as to ensure that the job execution complies with the project requirements and serves the intended function to satisfactory level.

2. Scope

The scope of this Method Statement is to define the method of Testing and Commissioning of Pressurization Unit installed within the project in accordance with the part of commissioning checks at site.

3. References

4. Tools / Material /Testing Instruments 

4.1 Material

4.2 Tools / Testing Instrument;

5.    Quality Control

In general, it shall be ensured by Site Engineer that product manufacturer’s recommendations are followed and shall be monitored by QA/QC Engineer.

Project Engineer shall further oversee the Pre-commissioning and commissioning activity as per the approved method statement for Start-up and Commissioning of Pressurization Unit.

The Pressurization Unit shall be tested under direct supervision of manufacturer / local dealer’s representatives while respective engineer shall monitor the work progress and final inspection by consultant / Engineer.

6. Pre – Commissioning & Commissioning Procedures

6.1.    Mechanical Checks

  1. External pipe work connected to the unit should be supported so as not to stress the pipe work connections
  2. Water and other connections are intact, and that water is available.
  3. Check operation of water tank float valve, ensuring valve will open, and close drip-tight.
  4. Check inside break tank for any debris or sediment and if necessary drain tank and clean out.
  5. Generally check over and clean the exterior of the unit, at the same time checking for leaks.
  6. Check that the pressure gauges / switches are installed and is operating

6.2.    Electrical Checks

6.3.    Start – Up and Testing

6.4 Sequence of Operation of Pressurization Unit:

7.    Inspection & Records:

8. Safety

 9. Attachments

Pre – Commissioning & commissioning check list.