Testing & Commissioning Of Chilled Water Pumps

The purpose of this method of statement or standard operating procedure is to define the step by step method to implement the correct practices for the pre-commissioning & commissioning of Chilled Water Pump” through the guidelines contained herein so as to ensure that the job execution complies with the project requirements and serves the intended function to satisfactory level.

Before doing the pump testing make sure that chilled water pump installation work is complete and approval is available in writing.

References

Tools / Equipment /Testing Instruments

Chilled Water Pump Commissioning Procedures

Visual Checks

Chilled Water Pump Start Up Procedure

Inspection & Records

Health & Safety

All safety precautions shall be followed as per the established Project Safety Plan.

Only experienced and skilled technicians shall be engaged for carrying out Start-up and Commissioning of “Chilled Water pump”.

Safety Guards shall be in place and secured prior to start-up.

Cable test reports shall be verified prior to energisation.

Appropriate Warning signs and tapes shall be placed during start-up and commissioning as required.

All PPE shall be worn as appropriate according to the nature of the job.

Work area shall be maintained neat and clean.

Attachments